2003-50
""""
CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
DA TE:
Mav 27. 2003
RESOLUTION NO:
2003-50
MOTION BY:
Peterson
SECONDED BY:
LundQuist
A RESOLUTION AUTHORIZING FUTURE CHANGE ORDER FOR ADDITIONAL
WORK ON TH 101, PROJECT NO. 97-12-3
WHEREAS, on May 12, 2003, representatives of the engineering, street, and parks
departments along with the design consultant and contractor for the above project walked the entire
length of the trail; and
WHEREAS, several items were identified to improve safety, drainage, and facilitate trail
maintenance; and
WHEREAS, staff requests Council approve the tasks with the formal change order to be
prepared after completion based on actual costs; and
,...
WHEREAS, the total project budget is $1,300,000. The City has spent $942,884.35 to
date, leaving $357,115.65 to complete the project.
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council hereby
approve the future change order, expected to be below$50,OOO,for additional work on TH 101,
Project No. 97-12-3.
Passed and adopted by the Chanhassen City Council this 27th day of May 2003.
ATTEST:
~~A
Thomas A. Furlong, Mayor
YES
NO
Furlong
Ayotte
Labatt
Lundquist
Peterson
None
None
,...,