2003-98
.'
e
e
e
..
CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
DATE:
Novennber 10. 2003
RESOLUTION NO:
MOTION BY:
Peterson
SECONDED BY:
2003-98
A votte
A RESOLUTION APPROVING CHANGE ORDER NO. 10,
CHANHASSEN LffiRARY PROJECT
WHEREAS, there have been a number of change orders for the above-mentioned project
during construction, with Change Order No.9 being approved August 11, 2003; and
WHEREAS, the attached change order provides a breakdown of costs associated with
Change Order No. 10.
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council hereby
approves Change Order No. 10 for the Chanhassen Library project increasing the original contract
sum by $13,897.76, which will bring the total contract to $5,144,057.20.
Passed and adopted by the Chanhassen City Council this 10th day of November 2003.
A TIEST:
g:u~-~t-~A
Todd Gerhardt, City Manager Thomas A. Furlong, Mayor
YES
NO
Furlong
Labatt
Lundquist
Ayotte
Peterson
None
ABSENT
None
"
.
e
Change Order
. Contractor
. Owner MS &R
. Architect
. M + E Consults
. Structural Consults
Project:
Change Order Number: 10
Contractor:
Chanhassen Public Library
690 City Center Dr.
Chanhassen, MN 55317
Date: 13 October 2003
Kraus Anderson Const'n Co.
2500 Minnehaha Ave
Mpls, MN 55404
Architect's Project No.: 2001021.00
Contract Date: 28 May 2002
Contract For: General Construction
The Contract is changed as follows:
CCD 40-2
~'$eefr36-5
CCD 41
CCD 40-1
CCD 39
CCD 29-2
Add sealer coat to concrete flooring
Add custom tile to the Children's Toilet
Add access panel for the fire sprinkler valve
Add six toilet mirrors
Repair the truck damage to the brick wall above the garage door
Roofing modifications
$7,288.76 -
$384.00 ,.
$105.00 -
~~~.~~ -:v.
$860.00 ./
add
add
add
add
add
add
Attachments: All the back-up data has been included with this Change Order for your convenience.
e
>t eN: 1\1 ~ Ch"rj~^ ~ {k co'^""~
Not valid until signed by the Owner, Architect and Contractor
The original Contract Sum was ............... ................,............... ............................. ........... ...... $4,865,000.00
Net Change by previously authorized Change Orders ................................................................$265,154.52
The Contract Sum prior to this Change Order was .................................................................$5,130,154.52
The Contract Sum will be increased by this Change Order in the amount of ............................... $13.897.76
The new Contract Sum including this Change Order will be .................................................$5,144,052.20
The Contract Time will be increased by ..,........................................................................................ 0 Days
The date of Substantial Completion, resulting from this Change Order is ..............................23 April, 2003
By
e
Contractor
Owner
City of Chanhassen
690 City Center Dr
::a0?A%r
Date 12-} -03
L:\2001021 CHA \doc\l 021 COl O.doc