2004-03
e
e
e
CITY OF CHANHASSEN
CARVER AND HENNEPIN COUNTIES, MINNESOTA
DATE:
January 12. 2004
RESOLUTION NO:
2004-03
MOTION BY:
A votte
SECONDED BY:
LundQuist
A RESOLUTION APPROVING CHANGE ORDER FOR WELL 9 TEST DRILLING
PROJECT 03-02
WHEREAS, the attached change order is necessary due to the failure of the first test
drilling at Well 3 to yield a quality water producer from the drift aquifer.
NOW, THEREFORE, BE IT RESOLVED that the Chanhassen City Council hereby
approves the change order for Well 9 Test Drilling Project 03-02 in the amount of $11,483.00
bringing the contract amount to $34,168.00.
Passed and adopted by the Chanhassen City Council this 12th day of January 2004.
Thomas A. Furlong, Mayor
YES
NO
ABSENT
Furlong
Labatt
Peterson
Lundquist
Ayotte
None
None
-
e
e
..
SECTION 00991 - CHANGE ORDER
(In:structions on reverse side)
No;1
PROJECT: Well No.9 - Test Well
bATE OF ISSUANCE: January 5, 2004
EFFECTIVE DATE: September 24,2003
OWNER: City of Chanhassen
OWNER's Contract: Well No.9 - Test Well
CONTRACTOR: . Keys Well Drilling Co.
ENGINEER: Bolton & Menk, Inc.
You are directed to make the following changes in the Contract Documents.
Description:
See Attached Table for Contract Modifications.
Reason for Change Order:
We began test well at well #3 site, abandoned this site due to poor aquifer formation at this location. Relocated at
Sugar Bush Park site.
AttachmentS: (List documents supporting change)
N/A
CHANGE IN CONTRACT PRICE:
Original Contract Price
CHANGE IN CONTRACT TIMES:
Original Contract Times
$22.685.00
Net changes from previous Change Orders No._to No._
Substantial Completion :.2!L-days or dates
Ready for final DaYffient ; 30 days or dates
Net changes from previous Change Orders No._to No._
$0.0
Contract Price Prior to this Change Order
o days
Contract Times prior to this Change Order
$22;685.00 .
Net Increase (Increase~) of this Change Order
Substantial Completion :~ days or dates
Ready for final Dayment : 30 days or dates
Net Increase (Increase/Deerease) of this Change Order
$11,483.00
Contract Price with all approved Change Orders
80 days
Contract Times with all approved Change Orders
. .. $34,168.00
Substantial Completion : 110
Ready for final payment : 11 0
days or dates Nov. 25, 200'3
days or dales Nov... 25,2003
RECOMMENDED:
APPROVED:
ACCEPTED:
By:
By:
By:
Contractor (Authorized Signature)
Engineer (Authorized Signature)
Owner (Authorized Signature)
Date:
Date:
Date:
EJCDC No. 191Oc8.B (1990 Edition)
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America.
CHANGEbRDER
PAGE 00991-1