Engineer's Estimate 5-7-07
Fox Hili Engineer's Estimate for Utilities and Roadway Construction
Location: ~ Fox Hill subdivision '
Chanhassen, Minnesota
BID ITEM DESCRIPTION QUANTITY UNITS UNIT PRICE EXTENSION
NO.
SANITARY SEWER SYSTEM
1 Construct Manhole
2 8" SDR 35 Sanitary Sewer main at 8' deep
3 4" Sanitary sewer services to 9' beyond property line
WATER SYSTEM
4 Connect to 8" Watermaln with tapping sleeve & valve
5 6" CI. 52 DJ.P. Watermain, 7.5' cover wrapped
6 Hydrant and valve
7 1" Copper water service lines to 9' beyond prop. line
STORM SEWER SYSTEM
8 Connect to existing catch basin
9 2' X 3' Catch basins
10 12" PVC Storm line at 4' deep
11 4" PVC Drain line at 4 - 6' deep
12 Infiltration area and outlet
13 Subgrade drains
14 Cleaning & Maintenance
STREETS
15 Surmountable curb and gutter
16 Select granular fill 24"
17 Crushed aggregate base 12"
Tack coat
18 Bituminous binder course 2"
19 Bituminous wear course 1.5"
EROSION CONTROL
20 Silt fence
2.00 LF $2,000.00 $4.000.00
218.00 LS $35.00 $7,630.00
3.00 LS $2,000.00 $6,000.00
Total Sanitary Sewer System $17,630.00
1.00 LS $5,000.00 $5,000.00
274.00 LF $35.00 $9,590.00
1.00 LS $1,500.00 $1,500.00
3.00 LS $1,500.00 $4,500.00
Total Water System $20,590.00
1.00 LS $2,000.00 $2,000.00
2.00 LS $2,000.00 $4,000.00
115.00 LF $27.50 $3,162.50
385.00 LF $15.00 $5,775.00
1.00 LS $20.000..00 $20,000.00
578.00 LF $5.00 $2.890.00
1.00 LS $5,000.00 $5,000.00
Total Storm Sewer System $42,827.60
578.00 LF $20.00 $11,560.00
1160.00 TONS $16.00 $18,560.00
640.00 TONS $16.50 $9,920.00
40.QO GAL $2.64 $105.60
29.60 TONS $38.50 $1,139.60
22.20 TONS $38.50 $854.70
Total Streets $42,139.90
1060.00 LF $2.50 $2,650.00
crTY OF CHANHASSEN
RECEIVED
MAY 0 7 2007
CHANHASSEN PLANNING DEPT
.....
,-
<"
21 Rock construction entrance
SITE RE~TORATION
22 Sod behind curb
23 Mulch & seed by hydro spray
SITE GRADING
24 Demo of existing structures
25 Subcut of streets, distribute per grading plan, balancos
STREET LIGHTS & SIGNS
26 Street lights
27 Stop sign
28 Fire lane signs
29 Street sign; private roadway
ENGINEERING, SURVEYING & INSPECTION
30 Surveying (Done and paid for)
31 Engineering (Done and paid for)
32 Staking
LANDSCAPING
33 Landscaping
TOTAL ENGINEER'S ESTIMATE
1.00 LS $1,500.00 $1,500.00
Total Erosion Control $4,15Q.00
330.00 SY $5.90 $1,947.00
1.50 Acre $800.00 $1,200.00
Total Erosion Control $3,147.00
1.00 LS $7,000.00 $7,000.00 CITY OF CHANHASSEN
RECEIVED
653.00 CY $9.00 $5,877.00
Total Site Grading $12,877.00 MAY 0 7 2007
3.00 EACH $500.00 $1,500.00 CHANHASSEN PLANNING DEPT
1.00 EACH $500.00 $500.00
6.00 EACH $500.00 $3,000.00
1.00 EACH $500.00 $500.00
Total Lights & Signs $5,500.00
2.00 EACH $0.00 $0.00
1.00 EACH $0.00 $0.00
6.00 EACH $1,500.00 $9,000.00
Total Engineering & Surveying $9,000.00
1.00 LS $20,000.00 $20,000.00
Total Landscaping $20,000.00
5177,861.40