Building Official Referral Response Memo 5-24-07
MEMORANDUM
TO:
Robert Generous, Senior Planner
FROM:
Jerritt Moho, Building Official
DATE:
May 24, 2007
SUBJ:
Review of request for an Interim Use Permit to import
approximately 43,250 cubic yards of soil to property located at 8601
Great Plains Boulevard.
Planning Case: 07-16
I have reviewed the plans for the above project and offer the following comments.
These comments should be included in the conditions of approval.
1. A demolition permit is required for the removal of any structure(s).
2. If future construction in this area is anticipated, these soils must be
engineered for the intended structural loads and their placement must be
properly compacted and tested as required by such soil engineering. A
report, verifying placement, compaction and soil suitability, from the testing
agency will be required before building permits will be issued.