1992 08 11 Agenda
.
.
.
FILE
1
AGENDA
PARK AND RECREATION COMMISSION
TUESDAY, AUGUST 11, 1992, 7:30 P.M.
CHANHASSEN CITY HALL, 690 COULTER DRIVE
CALL TO ORDER
1. Land Development Proposal, Preliminary Site Plan Review.
Target
Ryan Construction Company
700 International Centre
900 Second Avenue South
Minneapolis, Minnesota
RLK Associates, Ltd.
922 Mainstreet
Hopkins, Minnesota
2. Land Development Proposal, Preliminary Site Plan Review.
Johnson, Dolejsi, Turner Property; a Single Family Residential Planned Unit Development
Concept.
Lundgren Bros. Construction, Inc.
935 East Wayzata Boulevard
Wayzata, Minnesota 55391
3. Carver Beach Park, Vehicle Parking.
4. 1993 Park Acquisition and Development Capital Improvement Program.
,
e
I-
Z
~
u
::i
Q.
a..
<(
e
~
~
W
I-
-
(f)
e
PRC DATE: August 11, 1992
CC DATE:
HOFFMAN:k ~
/
CITY OF
CHANHASSEN
STAFF REPORT
PROPOSAL:
Ryan Construction Company proposes rezoning 25+ acres of property from BG,
General Business District to PUD, Planned Unit Development, a conceptual PUD
and site plan approval for Target Development on 18+ acres.
LOCATION:
See attached vicinity map.
APPLICANT:
Ryan Construction Company
700 International Centre
900 Second Avenue South
Minneapolis, MN
RLK Associates, Ltd.
922 Main Street
Hopkins, MN 55343
PRESENT ZONING:
BG, General Business District
ADJACENT ZONING
AND LAND USE:
N - BG, General Business District
S - Highway 5
E - BG, General Business District
W - Highway 5 and County Road 17
COMPREHENSIVE PLAN:
This site lies within the service area of all the city's developed
community parks (Lake Ann, Lake Susan, City Center, and South
Lotus Lake), and within the neighborhood park service area of
Chanhassen Pond Park. In light of the site's proximity to these
park facilities, and its zoning, the need to acquire parkland as a
part of this development does not exist.
COMPREHENSIVE TRAIL PLAN:
The Comprehensive Trail Plan addresses the need to accommodate non-vehicular pedestrian, biking, and
other transportation movements on three peripheries of this site; south, north, and west.
Target Proposal
August 11, 1992
Page 2
I
e
South: The construction of an 8 ft. wide bituminous trail on the north side of Highway 5 has
occurred in conjunction with the upgrading of the same. This newly constructed trail extends
west to Powers Boulevard and east to Eden Prairie and beyond.
North: The site in question is located in a General Business District of the city. As such, the
applicant will desire and is required to install sidewalks to service the pedestrian needs of the
site. The Planning and Engineering Departments will review the location and design standards
for these concrete sidewalks.
West: The western fringe of this site is comprised of an area which will be developed by the
city as a "gateway" to the community from Highway 5 via Powers Boulevard. Future
improvements in this area will include the construction of trail connections linking the Highway
5 trail with the West 78th Street sidewalk.
No trails are proposed to be constructed by the applicant, thus no consideration for trail fee credit
IS necessary.
RECOMMENDATION
It is recommended that the Park and Recreation Commission recommend the City Council require e
the applicant to pay full park and trail fees in lieu of land dedication or trail construction. These
fees are to be paid at the time of building permit application at the per acre rate then in force for
commerciaV industrial properties. At present, these fees are $2,500 per acre and $833 per acre,
respectively.
e
-----...;:.~' ~-o.
~ ..... T' \...- ~Q). I ,:?l.S +
~ "r-- >'2' ..." I~ ~ IJ ' ~ RO..... ~ ~ I,
o . .Ii..., r V Q ..... ~ ,,~ .....11".. " ~r~ ~\ ((.\ Y /'
~ '--{ ~ib ~ ";3;:~ ''<-C"n ~ ,....,.....: . J~ "'cq;>)-
~ Y jr'l - - 1'\ !I! "...... a; . "'i0 ~ '~.::i T"-; ORY -... ~. ~ .' :1('-
/",,": - ~ !4 r-- h),H ~ = ~ ""\ ~I'ol:l,,\ 'i,.. "- .,~ ~\ ". ~
a ~~~ l~t-jZHI--~~.e ~jllll"lll' \::~~~r~ "' \\\.\JI ~ fI \
· '--(j -f -~ I- t- .); ~, ;;/)., 1 ~ L,lJ ~ .'\ '/J
~ _M . II' LA' I.ll.lf ~~ · J~ ,I 'I~
- J '..~ ~ /U ~ ~'~J:'#. \\-r1 II .o<~: ~~. /?ra<-:-<t!\ :-( 11 .... f.Yr-.f(/ ~.~
~ x. . \~" . 'I;!~'" , l.LJ. y./'~\6", no.., > 1,1
1"GREENWOOU r\'(/' 0 \~\ '\.. j:Jy-~)
", ~ SHORES t;.\\ /,!i'l' 'U\~U.. ~~-r-S-'-'.' b ~~~~" LAKE
,. PARK ~\\ I 'I" .. ~.J'.fl".:1 I::; .~ 'd ~ y-- ~\
./ 1 7'. ',.,~'^-.~ ~ " ~ \ mM'
' .4IEAOOW ~1l1_~~, ~ ~." I .':
': GREEN PARK) \'? g, c:J.J''t--i. "'T1 ? . k-' I '-1, f[3&':)
0\\ y:::; ~ ~ J'1 J, ~. ~ : ~ '-"'" I I, 'I/'''
/ j ~\t::i c ~~ r I,I)~"""... Ii ;!;'"] "-L I GH Il 0 . ,/'l
'Z ~ 2"1 2'1 "'\~\,..../, 0~ \,.lJ,. /Iij ~\lq b .~kt.~~
· .). I t.. \~0\1-l ~ :t1""O ~ A IlC.9? ~~
~ <. ..J _..J "5f~\8 r ,.~ _i!~; ~f\5J-
-- ' ~\Ij ~~:.~~y~~ R n ~ ~I\f,
:1 ~~.A~~ ~ ~~-rimD~= __ .
'" "",/lilT Srmr~~........:1
~ pO '; ~ ~i ~ /j]!lB3~En9L,~
~ VICIN1Y ~~Pl / ~ "~l;~q~lil
# . ./ ~""-" , ~ rm L....J W, ST '9 PH ST\-i iiJi~~ 5 IllP.1;
lARD }JL r l= ~:::v/
{PA K L - _ fii:: ~ ~ _ ~ . 0;
.I '( --" > , ..... > . -.- k& 1 Tf"
'( ~o 0 ",,4 ,- ~ "- I
,~-----.,. ~4 -) R~~;;;o- :' :\ \ ~ ~.) ~
---- .. --"'.,..- s r ~. .
,~ ." -----=- !IrE H'iGi<"'~ ~!~
~ )J'/ ptt.C h [1 DRIVE I '- --" ~ ,ii . ;
~ ~ - ~---- ~~'-J l!! h"'" B?( ?-:1\~ ~
& · "'" .~ ~ ~ liIo...." "i. 11:: ~
1 C <, , r,;.Cl: " .
.\ l __:;- ".1Iili!I J /)<"
' \ .- I _11!:iF.i n..k
~% ,~ -,(~,~.lI'~l:'~ ) ~ ~ !U'liG ~ ".
,'i:m). ~II ~ ~ \ .)~ l T 1I
- 0 ~", I ,'" .. I ,
~.~: l..~i, ~... PARK \\~.~ ( \ LY' ~ L r,.1 ~
.. ~.. s~ i..4l
'. \/:'.0 .. --' __
,v ~......, "'"' '."',:':' '~_~\..~~"! ~ ~~~~
f 8:. 1\\ I 1\' ,?? -~~ - = - ". ~'~ \'---t...
" .'~' :lJH IJ~ ,; \\ I & l:>) . ,,~.
'. \~ ;'--,~'" '"'\ .L~' t>:f_ r-,,; ~ ! ~J/ /!J 1 ,... ~
~ ~ ~ Il" ::i 'ii ::t I ': . -fJI{//ljJ "';-, 'I ;
~~ t:Xjy '" ../o~';k7 ib "'~ ~~'/ \! I
I l]~ -t9~~\ r- ~T ! '\\11 ///-~ ~
. .,., m ~'Y .J;IG~ i
'N
W
PA'iK
e
\
\
\~
!
~ ,
\
\.- ' .' \
~\~
~ '"
{;J ~
/'
"'-"
~
.J___.
-~. ._~ --"',...;Y
'"
'" .
.~:--- -- -' /,!' ~:'./
-------....
.-
<:'
"
l
'-.
\ \ 'I...
\, or. j
'--I" .
j~.~\
\ ,
\ <> \
\
\ \
I
~ 'I
~ I
~ "1- !
~ .1
~'y " ~
0
o~ ~
0 ~
~
~ ...
I
I
~,~, ""----.
I
I
I
J-
I
II'
~
~
.
t 'IIf-- A
'$
o
C T
~
... ~
0
.. ~
"!
~
<...
G'~
n
l
~
l
en
en
"1
~
,
!
e
t
\
'....
...
r
~
n'
~. ;
~i !
e
,
e
e
~ ] [
CONCEPT PUD NARRATIVE
AND
PRELIMINARY SITE PLAN APPROVAL FOR TARGEI' SITE
CHANHASSEN TARGET DEVELOPMENT
-
Prepared for:
RYAN CONSI'RUCTION COMPANY
700 International Centre
900 Second Avenue South
Minneapolis, Minnesota 55402
Prepared by:
RLK ASSOCIATES, LTD.
922 Mainstreet
Hopkins, Minnesota 55343
.
July 20, 1992
0 C_
e
RLK ASSOCIATES, LTD.
CONCEPT PUD NARRATIVE
CHANHASSEN TARGET DEVELOPl\iENT
.
INTRODUCTION
Located in the east central portion of the City of Chanhassen, on the western edge of the
Central Business District lies two parcels identified as Burdick Park 2nd Addition and Block 2
of the West Village Heights 2nd Addition. These two parcels in addition to the vacated West
78th Street right of way form a 18.92 acre parcel of property being proposed for commercial
development. Refer to Figure 1 for project location. Ryan Construction Company, hereinafter
referred to as the developer, is proposing to develop the property into what shall be referred to
as the Chanhassen Target development.
The first step in the implementation of the Chanhassen Target development is to rezone the
property from its current BG (General Business District) zoning to a PUD (planned Unit
Development) zoning. This document represents the narrative that accompanies the seven site
plan sheets submittal proposal and the one architectural plan sheet. The developer, via this
submittal package for concept PUD and the Target site plan approval, intends to go through the
PUD process. Upon successful completion of this stage, the preliminary, the final PUD and
final site plan will be pursued. It is the expectation of the developer that the following schedule
is realistic.
Concept PUD and Site Plan Submittal
Planning Commission Hearing
City Council Hearing
Resubmit preliminary and Final PUD Plans
with a final site plan and Developer
agreements for City Council meeting
July 21, 1992
August 19, 1992
September 14, 1992
September 28, 1992
e
It is the expectation of the Developer to have a final decision on this site prior to October 1,
1992. The developer is committed to working with City staff on this schedule, in the
anticipation construction would be under way prior to the onset of winter.
PROJECT GOALS
Ultimately, the primary goal of the developer is to develop the 18.92 acre site into a Target
store encompassing 10.03 acres and an additional six outlots totalling 6.1 acres. In addition,
the proposed public right of way is 1.08 acres and Outlot A for draina&e pwposes is 1.70
acres. There are several objectives that suppon the primary loal.
1. To integrate the Burdick Park 2nd Addition and Lot 1, Block 2 of West VJllage Heipts
Second Addition into a Planned Unit deveJopment with compatible site organization and
development standards.
2. Provide as a catalyst to the City to finalize the design and reconstruct West 78th Street per
the Year 2000 Land Use Plan and 1992 SRF Feasibility Study.
NARRATIVE - CHANHASSEN TARGET CENTER
Page 1
e
RLK ASSOCIATES, LTD.
.
3. To create a utility system, ponding area and combination public and private roadway system
in conjunction with the site development.
4. Protect the majority of existing hardwood trees at the southeast comer of the lot in
accordance with discussions with members of the City staff.
s. Develop a quality commercial/retail area compatible with the west CBD sub-area study
prepared in April 1992 and the City's Year 2000 plan and code standards.
The commercial site described and shown on Figure 1 is guided for General Business by the
City's Comprehensive Plan. It is also zoned for General Business. In order to create a PUD
for this site, the developer intends to follow the City PUD zoning approval process. The
developer wishes to enhance the flexibility of development of the sites within the 18.92 acre
tract of land through the relaxation of the zoning district standards. In return, the developer's
intent is to exchange improved quality of the ~hed development project.
The PUD will encourage the items listed in Article vm, Division I of Section 20-501. Later,
in the details that are contained in this narrative document and attached plan sheets, the methods
by which the City's expectations will be met are demonstrated.
-
DEVELOPMENT SUBMITTAL PACKAGE EXPLANATION
e
Discussion in this section of the narrative introduction briefly explains the contents of the
submittal material. This data was transmitted to the City, with the appropriate Concept Stage
PUD, Rezoning, Site Plan Review and Sign Package Fee. The items listed below are either
included in this Narrative Booklet (N) or they are included with the plan sheets (P). On July
21, 1992 the submittal package was delivered to City Hall in Chanhassen, Minnesota.
1. Completed application for Development Review (N)
2. Written consent of all property owners within the PUD (N)
3. Project narrative booklet explaining the project in detailed fashion using verhage, sketches,
charts, and an appendices (N).
4. Set of seven plan sheets that describe in concept schematics the components of the project
with detail (P). Sheet 1 - Site Plan; Sheet 2 - Existing Conditions; Sheet 3 - Concept
Utilities; Sheet 4 - Concept Grading; Sheet 5 - Concept Landscape; Sheet 6 - Preliminary
. Plat; Sheet 7 - Tree Survey.
S. Plan sheet identifying the architectUral detail for the TarJet store.
6. List of property owners within 500 feet of the site (N).
7. Topography map and legal description of property proposed for PUD zoning and
development (P).
e
NARRATIVE - CHANHASSENTARGET CENTER
Page 2
RLK ASSOCIATES, LTD.
BACKGROUND OF THE DEVELOPMENT TEAM PARTICIPANTS
CHANHASSEN TARGET DEVELOPl\1ENT
.
.
Ryan ConstnIction Company of Minnesota, Inc. will be the Developer. of the Chanhassen
Target site and the six outlots. Under the direction of Bob Goodpaster, the project will be the
first commercial retail development that Ryan has developed in Chanhassen. Target Stores,
Inc. will be the owner of the Target store and propeny. R.yan has considerable experience in
developing Target stores and their associated developments such as the Rockford Road Plaza in
Plymouth and the Cliff Lake Centre development in Eagan. In addition, Ryan has developed a
number of Industrial and Office Corporate Parks including the Chanhassen Business Center
proposed for Audubon Road. Their commitment to the business client and the City to provide
a quality retail and business environment helps to assure that the Chanhassen Target
development project will be a successful development venture.
Architecture for the site development within the Target proposal will be performed by the
architects on the Ryan ConstnIction Company staff. Greg Madsen will be in charge of the
architecture design and coordination with the other desip team members. .
Site planning, surveying, engineering and landscape architecture services will be provided by
RLK Associates, Ltd. Dick Koppy will serve to facilitate the project's involvement between
the City and the developer on all items related to site planning and infrastnIcture development.
RLK Associates has served Ryan ConstnIction Company for over 5 years on many of their
retail. industrial and office park development projects around the Twin Cities metropolitan area.
. . . .
.
PROJECT DETAILS
e
Planning Unit Developments (PUD) offer enhanced flexibility for the developer to achieve a
more creative use of the land while easing the normal zoning district standard. In exchange.
the City expects that the development plan will result in a significantly higher quality
development and more sensitive proposal than in the more standard zoning district development
proposal. This section of the Narrative discusses the strategies of the development plan for the
Target Development related to criteria the City has indicated an interest in reviewing.
Through the variety of land use. efficiencies of the utility and roadway system the proposed
PUD can maximize the development potential of the subject parcel while re1J)Jlining sensitive to
its unique natural features. Powers Boulevard and State Highway 5 serve as a focus location
for the City of Chanhassen with respect to the downtown Chanhassen amenities.
The proposed site plan identified on plan sheet one of seven identifies the suggested layout of
the stnIctures. roadway and parking areas. Several key issues identified on the site plan are
proposed in order to meet the City's objective of a PUD zoning district.
1. ConstnIct West 78th Street according to the Year 2000 plan and 2/19/92 SRF FeasibiIity
Study to enable the six outlots and Target site to be developed concurrently with an
organized internal roadway system and coordinated access plan from West 78th Street.
NARRATIVE - CHANHASSEN TARGET CENTER
Page 3
e
RLK ASSOCIATES, LTD.
.
e
2. Target service area is to be accessed from Picha/Monterey Drive to minimize the impact on
the existing woodland at the southeast comer of the site.
3. The stormwater ponding area south and southwest of the Target store is located to minimi7.e
the impact to the southeast woodland area.
4. Develop the site and incorporate the design objectives featured in the Apri11992 West CBD
sub-area study of signage, access, preservation, gateway and landscape buffer areas.
The following items for discussion and explanation have been taken from Article vm Planned
Unit Developments section 20-501 through 20-504.
1. Allowable Uses
The proposed Target Retail store and the outlot development is consistent with the Year
2000 comprehensive land use plan which identifies this site to be used for commercial
purposes. The current zoning of BG - a general business category is DOt equipped to
coordinate a large, integrated site development which is being proposed.
Specific uses and performance stand~ds for this commercial site development are addressed
later in the narrative and on the plan sheets. .
2. Preservation of desirable site characteristics, buffer areas, and protection of sensitive
environmental features including mature trees, ponding areas and scenic views.
e
The site is a combination of gently, sloping land, containing open space, ponding areas,
shrub massing and a significant woodland on the southeast comer. The open space areas
south of the existing West 78th Street is still in an agricultural state. Plan Sheet 2 -
(existing conditions) identifies the existing characteristics of the propeny. The existing
utilities are shown on the map and the anticipated drainage patterns will be compatible to the
SRF Feasibility Study for West 78th Street. The existing trees on the southeast comer of
the site have been inventoried and surveyed. The trees over six inches in caliper diameter
have been recorded with their size, species and physical condition. Generally, there are
three significant tree groupings:
A. Boxelder with a few oak and elm
B. Basswood with boxelder and a few oak, elm and ash
C. Oak with boxelder and a few elm and ash.
The significant clusters (B and C) with the dominate oak trees and other quality hardwoods
have been designated to be preserved in most of their entirety. The trees designated for
removal on the average are the boxelder and elm clusters and individual hardwoods which
have suffered disease or storm damage. Refer to plan sheet seven of seven for a print of the
tree survey. The replacement landscape quantities identified in the plant schedule generally
replace the quality hardwoods lost to the site improvement.
e
NARRA TIVE - CHANHASSEN TARGET CENTER
Page 4
RLK ASSOCIATES, LTD.
The tree preservation plan includes thinning and removing a ponion of the trees in the
southeastern ponion of the site. The plan was conceived in recognition of past discussioDS
with the City staff and the developer (specifically note the May 15, 1992 and the May 20,
1992 letters between Todd Gerhardt, City staff, Don Ashworth, City Manager, and Bill
McHale, Ryan).
.
e
3. More efficient and effective use of land, open space and public facilities through the
coordination of West 78th improvements, access to the site and coordination of the utility
system.
West 78th Street has gone through the feasibility phase and the cost of the UParading are
known. The ability to refine the proposed arades of W. 78th Street at the entrance to. the
Target store will make for a higher quality development. The in place sanitary and water
mains on West 78th will adequately service the six outlots and the Target Store. Access to
the outlots will be constructed with a right in and right out at the access closest to Powers
Boulevard. The outlots are clustered adjacent to an intemaI looped road which joins the
Target looped road system.
The right of way on West 78th Street has been shown at 50 feet from center line for the
entire length of this development. 5Q feet allows for the necessary acceleration/deceleration
lanes, sidewalks and landscape boulevard, enablini this site to be compatible with the
existing Chanhassen CBn landscape pallet. Area has been set aside adjacent to Power
Boulevard for the City to create the Gateway landscape feature. Access between the Target
site and the property to the east has been requested; however, due to the need for a rB"ining
wall on the south side of West 78th Street on the Target site there is a 10-14' elevation
difference at the property line. Further site adjustments to the arades between the two _
propenies will be necessary. .,
4. High quality of design and design compatible with surrounding community standards. Site
planning, landscaping and building architecture should reflect hiper quality desilD than is
found elsewhere in the community.
The layout of the 18.92 acre Target site and the six outlots totalling 6.1 acres shall be
committed to architectural standards which will be established by the Tariet Store and
compatible with the City requirements. The site plan concentrates the ponding area into one
location adjacent to the cluster of existing trees. The resulting open space and grove of
trees will resemble a 2 to 2 1/2 acre area of rreen open space. The development plan is .
within the 70% hard surface coverage required for commercial site development and the site
plan allows for the open space to be clustered at the southeast and southwest comers of the
site plan, consistent with the community's aoals.
The Target store is the only site of the development being proposed for site plan review at
this time and is identified on the attached plan sheets. The rM\"ini"l outlots will be
congruous with Chanhassen codes and consist of: .
A. Brick, concrete block and other cementitious facade treatments
B. Glazing
NARRATIVE - CHANHASSEN TARGET CENTER
Pile S
e
RLK ASSOCIATES, LTD.
.
e
C. Sloping roof lines constructed of metal or asphaltic shingles which will adequately
conceal any rooftop mechanical equipment.
D. Landscaping as required to meet City codes and to be harmonious with existing
streets cape features.
Individual site plans will be submitted to Ryan Construction Company, the property agent,
for approval relative to architecture, building materials, and site improvements. The basis of
their approval shall adhere to the general guidelines briefly mentioned above and more
explicitly contained in the Planned Unit Development, Developer's agreement for the
ChanhassenTarget Development.
1.
2.
3.
4.
S.
e 6.
A. Building Materials and Design
All materials and colors shall be approved by the property agent prior to
commencement of property improvements.
Brick may be used and must be approved to assure uniformity.
Stone shall have a weathered face or be polished, fluted, or broken face.
Concrete masonry details must be approved by Ryan prior to construction or alteration
and shall be finished in stone, textured or coated (smooth surface or rock face).
Metal siding will not be approved except as a suppon material to one of the above
materials.
No ancillary structures that are considered to be pan of the building structure can be
constructed without prior approval of Ryan Construction Company.
B. Site Landscaping and Screening Standards
1. All open spaces and non-parking lot surfaces shall be landscaped, rockscaped, or
covered with plantings and/or lawn materials.
2. Approved screening techniques shall be used to block sight lines from adjacent
properties and roadways of service area.
3. The master landscape plan for the PUD shall be the design guide for all of the specific
site development.
C. Open Space, Trails, Park Dedication
e
1. Outlot A for drainage purposes, the internal public roadway servicing the six outlots
and the additional 10 feet of right~f-way along West 78th will be deducted from the
total acreage to be charged the developer for park dedication fees. Construction of the
road, pond and suitable grading will be completed by the developer. The proposed
park dedication fee is S2,soo.oo/acre and the trail fee shall be S833.oo/acre. The total
amount due on a per acreage basis is S3,3oo.00. The total acreage to be assessed is
Page 6
NARRATIVE - CHANHASSEN TARGET CENTER
RLK ASSOCIATES, LTD.
17.04 acres. The amount due the City shall be paid at the same time permits are being
purchased.
D. Signage
1. Identification Signs will be building mounted in conformance with the City's sign
ordinance and consistent with the Target standard. Each propeny shall be allowed one
free mounted pylon sign located near the driveway into the private site.
.
e
2. The signage will have consistency throughout the development. A common theme will
be introduced at the development's entrance monument, the signage monument adjacent
to Highway 5 and used throughout.
E. Lighting
1. A decorative, shoebox fixture (high pressure sodium vapor lamps) with a square
ornamental pole will be used throughout the development area for roadway and
parking lot lighting.
2. The same lighting equipment th~ is mounted in the public street right of way shall be
used in the new public roadway areas. . .
3. Lights will be on a photoelectric ceIl to turn them on and off automatically as dictated
by yearly conditions. This type of lighting is as enerl)' efficient as possible.
. . . . .
e
Agreement with details of the PUD Concept plan for the ChSlnb,ssen Target Development and
for site plan approval of the Target Site is being sought on this first submission.
PLANSHEETDE~ON
The verb age in the following section of the Narrative briefly describes the contems of the plan
sheets that are part of the proposed Chanhassen Target POD.
Sheet 1 - Master Site Plan: This plan sheet descnoes the basic intent of the entire
development proposal. It includes, but is DOt limited to, the foUowin& items:
J. Overall site impervious/pervious calculations and building density covera&e
2. Identification of each lot size and acreage.. .
3. Location of building, service area, streets, pedestrian walks, parking and landscape
areas. .
4. Location and extent of public and common open space.
S. Location and general type of land uses and intensities of outlets.
NARRATIVE - CHANHASSEN TARGET CENTER
Page'
e
RLK ASSOCIATES, LTD.
.
e
Sheet 2 - Existing Conditions: The project boundaries are identified and existing conditions of
the site are shown through the use of a two foot topographical survey. Topographic
information was provided by the City and MnDOT and verified in the field. In addition, the
adjoining properties, roadways and significant features are shown. A tree survey was
completed on July 18 to identify and quantify species, caliper inch and location. The trees
found on site generally are within three basic groups (see Sheet 7).
Sheet 3 - Concept Utility Plan: This plan identifies the location of the proposed water main,
sanitary and storm sewer. In addition, the realignment of West 78th Street has been
considered. .
Water Main:
Has been sized to effectively provide domestic and fire protectiQn to
each parcel. Looping of the system will be completed per City
requirements.
Sanitary Sewer:
The site is within the MWCC service area and service is available along
existing West 78th Street. Inverts of the sanitary are deep enough to
allow the road access to be lowered from West 78th Street to the Target
site.
Storm Sewer:
Pre-development drainage patterns will be maintained, with the ponding
area adjacent to the Highway S embankment. All disturbed areas will
be resurfaced with pavement, sod, landscape materials or seeded to
minimize erosion both during construction and after. The ponding areas
will be constructed per City of Chanhassen requirements and according
to the N. U .R.P. Design Guidelines.
e
Sheet 4 - Grading Drainage and Erosion Control: The grading plan identifies proposed
contours, ponding areas and suggest new roadway contours for West 78th Street. It is
imperative the Ryan Team and the City work together to construct West 78th and the Target
proposal in concert. Due to the service access for Target designed to come off of Picha, the
floor elevation of Target has minimal ability to be adjusted. The contours on West 78th Street
will have to be adhered to in order for the entry grades for the Target site plan to function
properly. All contours shown are 2' contours. .
Sheet 5 - Landscape Plan, Exterior Lighting: The landscape plan identities the location and
placement of all new plant material, ground cover, and surface treatment. In addition, the area
identifying protection of oak trees and other signiticant species is shown. All plant material
will be installed per the planting details and notes and will conform to the City standards and
species. The plant material for the Target site, which is being reviewed for site plan approval
identities caliper size, species and totals of plant material proposed.
Sheet 6 - Preliminary Plat: The preliminary plat is a combination of two platted parcels and
the vacated western extension of West 78th Street. The proposed plat will be named
Chanhassen Retail Addition with a total of 7 lots and one outlot proposed. A public road
servicing the six outlots at the northwest comer of the site is included in the preliminary plat.
e
NARRATIVE - CHANHASSEN TARGET CENTER
Page 8
RLK ASSOCIATES, LTD.
Sheet 7 - Tree Inventory: The stand of existing trees have been inventoried with all trees over
6w in caliper inch identified. The plan addresses all trees in size but makes DO value of a
Boxe1der vs. an oak tree or the quality of the tree. It is anticipated 1300 caliper inches of
quality hardwoods are being retained. The quantity of quality trees proposed to be removed,
excluding boxelder trees and/or diseased or storm damaged trees, is estimated to be S60 caliper
inches.
.
e
Sheet 1 or 1: Architectural Cross SectionslElevations: Preliminary elevations are shown on
Sheet 1 of 1. The elevations proposed are taken on all four sides of the Target plan, the
materials are a combination of eMU block (smooth) and brick, with accent colors within the
typical Target Red Range.
e
NARRATIVE. CHANHASSEN TARGET CENTER
e
Page 9
'\
e
e
e
TARGET DEVELOPMENT
CITY OF CHANHASSEN
City of Chanhassen
690 Coulter Drive
Chanhassen, MN 55317
Phone: 937-1900
Fax: 937-5739
Don Ashworth, City Manager
Paul Krauss, Planning Director
Kate Aanenson, Senior Planner
Charles Folch, City Engineer
Todd Gerhardt, Assistant City Manager
Todd Hoffman, Park & Rec. Coordinator
Mark Littfin, Fire Marshal
Steve Kirchman, Building Official
CITY'SCONSUL TING ENGINEERS
Strgar-Roscoe-Fausch, Inc. (SRF)
One Carlson Parkway North, Suite 150
Minneapolis, MN 55447
Phone: 475-0010
Fax: 475-2429
BRW, Inc.
Thresher Square
700 Third Street South
Minneapolis, MN 55415
Phone: 370-0700
Fax: 370-1378
Dennis Eyler, Engineer
Jim Dvorak, Engineer
John Horn, Engineer
TARGET
Target Stores, Inc.
P.O. Box 1392
33 South Sixth Street
Minneapolis, MN 55440
Phone: 370-6073
Fax: 370-6008
Ryan Construction of Minnesota, Inc.
700 International Centre
900 Second Avenue South
Minneapolis, MN 55402
Phone: 339-9847
Fax: 337-5552
Dick Brooks, Director of Real Estate Dev.
Direct Line: 370-5844
Jim Theusch, Project Architect
Direct Line: 335-4560
William (Bill) McHale, Vice President
Robert Goodpaster, Division Manager
Greg Madsen, Project Architect
T ARGET'S CONSULTING ENGINEERS
RLK Associates Ltd., Consulting Engineers
922 Main Street
Hopkins, MN 55343
Phone: 933-0972
Fax: 933-1153
Richard L. Koppy, Engineer
Francis D. Hagen TI, Director of Engineering
John Dietrich, Landscape Architect
Bloomberg Companies, Inc.
545 West 78th Street
P. O. Box 730
Chanhassen, MN 55317
B. C. Burdick
426 Lake Street
Excelsior, MN 55331
Douglas M. Hansen et al
17001 Stodola Road
Minnetonka, MN 55343
(
e
Frontier Development Corp.
c/o Bloomberg Companies
P. O. Box 730
Chanhassen, MN 55317
Roberts Automatic Products
880 Lake Drive
Chanhassen, MN 55317
Lutheran Church of the Living
Christ
Box 340
Chanhassen, MN 55317
E. Jerome Carlson
Instant Web, Inc.
6950 Galpin Lake Road
Excelsior, MN 55331
Frank Beddor ill et at
1000 Park Road
Chanhassen, MN 55317
Eckankar
P. O. Box 27300
New Hope, MN 55427
Mithun Enterprises, Inc.
900 Wayzata Blvd. E.
Wayzata, MN 55391
Richard S. Brose et at
c/o T. F. James Company
P. O. Box 24137
Minneapolis, MN 55424
DEAN R JOHNSON CONSTRUCTION
POBOX 1533
MAPLE GROVE MN 55369-0028
Twins Cities and Western RR
723 11th St. E.
Glencoe, MN 55336
e
e
.
CITY OF
CHANHASSEN
PRC DATE: August 11, 1992
;;
CC DATE:
-#t-
HOFFMAN:k
STAFF REPORT
PROPOSAL:
Rezoning, Planned Unit Development and Subdivision of 95.19 acres of property
into 120 lots, alteration/filling of 2.81 acres of wetland, Jolui.son/Dolejsi/Turner
property; a single family residential Planned Unit Development concept.
r-
z
<t
U
::i
Q.
a..
<(
LOCATION:
See vicinity map
APPLICANT:
Lundgren Brothers Construction, Inc. .
935 East Wayzata Boulevard
Wayzata, MN 55391
Mr. Terry Forbord
e
PRESENT ZONING:
A-2, Agricultural Estate District
ADJACENT ZONING
AND LAND USE:
N . RR, Rural Residential District
S - A2, Agricultural Estate District
E- RR&A2
W - State Highway 41
COMPREHENSIVE PLAN:
The intent of the City's Comprehensive Plan, Recreation Section
for public recreation open space is not being met as a part of this
proposal. The provision of a 2.3 acre "private" or association park
does not meet the city requirements of providing public parkland
as a part of the subdivision and development of a parcel or parcels
of land. In addition, open space, which is comprised of wetlands,
is not acceptable for park fee credit under city ordinance. City
Code allows for the capture of one acre of developable land for
every 75 persons the platted land could house based on 3 persons
per single family dwelling unit for public park purposes. This city
ordinance is derived from state statutes. In this application for land
development review a.nd acceptance, that amounts to 360 persons
or 4.8 acres. Putting aside the proposed development plan for this
~
~
W
t-
-
(/)
e
Lundgren Brothers Proposal
August 11, 1992
Page 2
e
property and addressing the site solely on its proximity to existing or proposed neighborhood based
recreation sites, reveals the void currently existing in this area in respect to neighborhood parks. Being
historically agriculturally based with intennittent estate residential areas, there has been no impetus up
until this point to acquire and develop neighborhood parks. Requiring a public park space as a part of
this subdivision may be advisable; however, if the applicant confnms their intent of developing a private
recreational facility in this neighborhood, it is preferable that the city retain the park fees generated by
this development as capital to be used in a combination purchase/land dedication venture in a future
development in this area. H the applicant chooses not to pursue their private facility, then it is
recommended the city require parkland dedication in an amount not to exceed 4.8 acres in a location
deemed appropriate and desirable by the Park and Recreation Commission with park fee requirements
being reduced by the appropriate percentage.
Staff is not opposed to development of a residential neighborhood containing a private or association
park; however, there would be no public use or control over such a facility. The types of amenities
proposed for the private recreation area, i.e. a tennis court, basketball area, and children's play structure,
are appealing to the home buyers targeted by this development. Lundgren Brothers has found this
approach successful in other cities, such as Plymouth, which is why I assume they are proposing it here.
For their private parks in Plymouth, Churchill Farms and Stromseth, Lundgren Brothers did not receive
any park fee credits, and the granting of any credit was never considered. e
COMPREHENSIVE TRAIL PLAN:
The City's Comprehensive Trail Plan calls for the future installation of a trail along State Highway 41
(the western edge of the Johnson/Dolejsi/furner property abuts Highway 41-see attachments). Highway
41 is classified as a Class I minor arterial and currently has a 150 ft. right-of-way. The attached diagram
details the cross section of a Class I minor arterial showing Highway 41 will in the future be a four lane
highway with a median, leaving approximately 27 feet of clear zone at its edges. In many instances,
27 feet will not accommodate the utility and drainage needs and the construction of a trail combined,
due to constraints such as the presence of stands of trees or specimen trees, excessive slopes, uneven
terrain, etc. It is therefore appropriate to require the dedication of a 20 ft. wide easement for potential
future trail construction purposes along the entire western border of the subject property abutting State
Highway 41.
It is also advisable to install a concrete sidewalk along Street A which will in the future be the thru
street in this development. The City's Planning Department will address this need. No trails are
proposed to be constructed by the applicant, thus no consideration for trail fee credit is necessary.
RECOMMENDATION
Based on the preceding comments, staff recommends that the Park and Recreation Commission
recommend that the City Council: _
e
e
e
Lundgren Brothers Proposal
August 11, 1992
Page 3
1. Accept full park and trail dedication fees in the absence of land dedication or trail construction.
These fees are to be paid at the time of building permit applications at the per lot fee in force
for residential property at the time of permit application. The current fees are $500.00 and
$167.00 per lot, respectively. The above recommendation being contingent upon the applicant
indicating their intent to develop the "private" park area as indicated on the general development
plan.
2. The applicant supply a 20 ft. wide easement for potential future trail construction purposes along
the western border of the suJ:>ject property abutting the right-of-way of State Highway 41.
3. The inclusion of the "private" park does not diminish the requirements for public recreation and
open space as part of a subdivision, therefore, no credit will be considered for the inclusion of
this private facility.
.
-.
A ~~r B~~~~ C
PARK HCKiHr$ PARK- i I f ~ 2
f 1ft ~ t I , LJ I ~ , ~.J... J- i J.d:::J i
-~ -- I . - ~ \\L -Il:~\.m .1..t:l2.&: III _ 0:
LAKC~ ~LJ lAc. .:...'~ ~ ~I - .\ \ \\ ~ >~I~~~ET.._~ ~ I'f;i;l
~~ ~ q J..~." ~~""'--\' ~~~~UW~':JI'~. L--. ~
~ k. ~lJ~ . ~\'IT"" ,~. "'; y ('7 .
_..~ r /' ~ ~. \ J L~':._.~'.. ----..~, !,_ "i.'\ rill f:3f ~ANFIEU) 'o.il ~) T .: Wi
~ L ~ ~ 0$ v ~ , ." ;: ~~
~r.;. "--Ii, G ~ /~. :.:- ~ 'jl~ r ~~., ~
E") ::. ~~d At INN E It' A $ H T A ~!. ' I., . ; "-
- .....0::..- W III
- (' , ~IONAL IL ~ I_
I ,) 't-
-; ~..... .... I:r ""'", ffi .~ - - ,...: >'-1 ry:""F-' :/1
-~i CKE~/~1F,,_'~~,--_ r-"' .~ Pr't''1J. ; _
> I .~..~$ToInUry;'If:. ~~ """"--~~)""" I j ~
~~ '~..~. .... , .'" rl
t 1 1 ... .," f, , ~
t ~ r;' AIL. /':'1" .....lY'..~ A "
-- u __:::(: L _ a: . ~ ~
p -- i=i-. @ ~ l · ~.., ~lT IlIlli 0
I:~'... I~ ---' I ~ T !
~ IY''''''''''" . =, _ I I( ~
:.. /f -~. ~~ 1, YJCII~n'V
..., ~ 0=; 1'<"",,
- -- . 1 . y
~V~, u
D
~s j I :
l~~I~I"'T".
-
(L.
I 1
e
".-t j'?~>
'-'r~~/ r
IAph ~I
I,A J 1
-
r Q -
I '
0:
~
-
e"
..
~
~
J fJr;g )' ..u,,~
"~
.I#~_I)"I)
-~I'~
8
..
-.
I
~
i700-.
.
~T J<< IJ
" .~~~~
/ \. .J..... h_ 7J:;? '0"3.
r~ b-7~!GV ,u
---'9 ~ -~\ T.
~ - rl~~,*,".~'f'
I ~
I
(C~181 i~ / e
~'~:-- ~n
-
,
8
.
r I
! I
8 ~
:: -.
I I
~ J
-. -.
1 j 1 I 11 ~.
~ :: ~ ~ -. :
LyMAN
BLVD
.~;'0~.~i;~;~;:<".".?,:',.._. .,-"....ii;~~~;~il.:<:7'. ..~c::~~~"C~~' 1~~.::';.it!i>~:.c7g
8800-
" .t\r
. ..;. .
- 0 'I
.~:,......,..................--~ I.
0..
.'"1
.. ...- :D .-i :1 i-
f .~...
z =
m
:D
"'0
~
~ i:
<<
...
I:
1
~Ae IlllIiNCIllA$HTA
,....
I,
I
0/
'I
:!
! '0
,
J
" C"
ii
i
l
..~
at
"
II
~
l
,
.
, :
---I
() (...0
::t
i~
'J>Cf> I:
.1 ~ 0 ':
!. ~ Z :.
',/" . . "
"I 8 0 : i,
r.' ,
J r: ~: j
~. r2: 1
(J) ;. I
- ~..!., ::7.- .'
I'
. .
I
.;
~!
.'
. 'InTt .. .-
~II
Ii :t
11 r~ '
I 1 U I
e------ _I_~i
I'
I,
I.
'1
'{
I.
. ..
II
~ .i
-----"tr'\O: --.\":::"
---~;- .
'I ;
t, .. ,.~ ..
..<1 ",(
---'. I;"~
I~
I,
Ii
_....r..~....
r" ~--~
,
..'
"'
I!.'
J
---, .
....-'-. .-.
.- . .,~.. I
I I I
.1
r I I'
I I~ + it
r ,
I
" I
s'
t I
I
.--
'\
'.
.'.
I'
'1
I
:1
I,
I
~
,
I.
.
. ".
.. c:
.
.
---
, ,
, '.
, " ~- os
(. '. " .
!.... "~"'~' ", .
:,,, .',. " '
", ..r.' \ ..... .
.. \, "
.- '1 ..\"'..
:;~ '; -. '" :~."
'11" , "'~ ....
. t.., ) I. ~;,., .
, ,...~ I , "'. ~ ~ .'
f r :.:)~, '~ :~ '.'. "~~~""~'~ ,.' I I
f" . ~ ., "11.." i:? , ...',
. ~ .. .. fl' , ,.p,. . ..,
~ ~\ - I" I ~,..;f(/' !~:-'" '.
\ ..~~ 1;iE W~/./M...f " " ~:.:~ \~~ .
~. ~'? ~"h~' ~ /.~ r t, ~~.....:~, ".
-'" ~",-'TI1'di:~~~' ':~"">,, "'.
S 1 r ~):~ :/J:"~~' .l\ c: ~ .~ }~{ -:'~\.' ,
D j I 'r~'o " ~ l' ~~;. . '\\lo.)o.t\.
: · ~; I.~I;~ /.. ,,' ~ ,,::~'1,~~~ ~~ . ~";,\,>;...
-;t-- I I \, ~ .~ . ",.... ," '<" ""~"~~"
. Ii t ;')1' l ~-'\i;;;.:-or ~l":"tI':t.. .~ "'. '.......
. 'i. r 1/,.,.. "1i; r!_.. --<:. ....~,.. ~: i ;" ,): "'. '
/. T J / /.~ . I ~\~ ...\~ "\iU..' . 's. .~,,;. _ , :...
.-' v /'::::., . '; r ,. \~~ ~""", I .,~ :o;....."~, JC'"
I if . ~~; ~ ~- -' ~ : (i/~ fl/ji,t~;(. ~~,;'
'I, .~ / ,. ~ n')oV ~~ 'i" .:r~~ ,.,.
I'j,;'"~')..,,\ ...~...,
ir.JKm I ,1I. /{rf,~h ( .' \j1'x.J1;;;[Il':{:j~G'" . ;.,_. .: '.',
J vI '\ Iffl{ I 'f., ~/n : ~~U '..', ,'L I . , , . . ~ '
'. J .. ,1\\' \.:J Il ~ I.. ' , ,I" . ~.I ,; 'r'" I )' '.
'J I~ I'" . ~ I' \ . . , , I: ..
.,' 11' ~~' '. ~,. '"!,, ft\ \" ~.. " ,
-- ;:'::=' - - - ./' -..It. -:. . - r:-, ~ ~ Ii' -t I'-'i' ,\,;;;? ~~<, ... :; J
. I . ';;'-. . ,,'::. "". . . ~ ,\'. :.~ ~.... ~ . ~ :;t'/Ij 14') \1;, ;'\~\A .. ;::
''t....' .. ., ct~~ \1l:T\,~ /2' " /",'.,"':. ,\\h.., I I
-"," --l~ ..~(. -'I ".-( >,1 i~~.. '~I{~ii~>~)::';'~~'d("~~1~'-:-17)
;.' I!, I tI'l""'1t'I _ _ ~ 'I~':d \~I'lI. '.. ':'{'/'
.' -' r ltl..{ I i~ /-, ~ ~I ' , ) i "
L/ ! ,~I /J~ ..!~ ~r~~~;~ir~~~..~~~A\~r
~....- ~_~ '.// ,,~. :~.~ /...... r"{)'~I\\ It \ I -e.":'/
.. ~..-.-.--- ~. r.;.1f. Y-.e " . -.ft;:.. :~;:: -- _ - ';oo.F/J ' . ~", 'i',
~ .. -.I... . .".,....... . . 4 1.} -..,,.. ~ Y;'J ) ~f6 ~ ,\ I
-,: [>.:9'\~' ., . ,: . !I:~~, _'"'" l \ I \
r1 I 1/' ~ ~ .. .. . ,.. ".' < '.1' _ , I
~I, / \ ;~~ :_~_....'~ '<-41'~ -, -: .-, ~ '>~~~~~!j)' ))~- ~~~~~t~~i'~
I ../. - * A,{/";'2.~ ,.IT I . Z~ '\~"'"':I t~
JA";;' .;;C~ ,;,q~~ ~ ~"")L~ ~~)~.~. .' : Y>1~:;..~,{
~Lln' .;,/..-~,(::ra /....~~-~'~\ '11~'!t.~~.'~.' 'JrI"" S1'1...- ~'r- It'.
I L ., . . h'/II~~". Ihl) ..- .~'f~ W . .. \T':'\. I.~
... · ~ I_.l' - . "~~". '~~(~ ~ 7T'4t'7.1.;' ._...~~~.J":r&\,~ ...; ~.:~: ,:~,;,...
- C-":'__" 7 11fi"~~~"~--f1 ~~\\f.';i;1),1 i?T,P"/ ._J;;'Io:"~;'.4 I '-,;; ............ ..~") '. - '~" I
.. ....,....
!t ",~,\~
!t , ,,''''
-. ~,
~,~
g I
-
;-
~
A
I I
I I
i i
J ~ ~ !
9 9 ~ !
II ~ I
, .
~ I
"N"~
c,~ ..
IN"
~i ~
~~
, ,
~__.....,....."...r""... .'"s.,
:..;,;-
3-:11""1,
~ jII J 0 ~
mPi~ <
(j~ i
I ~1!li
~. "
~~;;J
I J"i Ul
~filli
f5 III
_ ij!i'lll ~
'15 ll~i. i
11=
11"j:
It II j!
II 'i' 5
P
n~
:0
U
enO
~z
.8
~
I
~
~
I
'.
i
Iftg!
~~~~
2
~
!B
I
H
ii
Ii
"
,.
,.
i!
.
I
~
z
I
J
It/)
I~
'.
'1.
~~'I :r
''V .' i
"
:D
o
'"'0
, m
"
:r:J
o
"
o
en
m
o
(')
o
r-
r-
m
(')
d
:r:J
>
r-
i5
z
~
m
z
-I
e
e
:
;;
-
5'
CG
I
CG
..
-
II
-
0-
~
e
,..,
.
e
7/
,> /
~ ,
/// .>~
e
---7~6 07
5 8..59' 13" W ---
o
2
WALTER WHIT~HILL
81( 119, P. 125
"-
'''',
~
:.
, .
I
I
8"luCf .to lOfSI(!
OOC 86669
/,
. /
I',
...," _ J/~ _
'I 163~'
,.~~
, I
~'"
I
,
','>.,. /
/X,:~
,
;
~fJl' ~
50
~Oo .
"00
.r!
CIl
N
l
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
....
r1' I~' H' /~' ~' IP' /d' ~' 12' /~' 14' 27' I
,I: i'6"" ~/~~ ""t; gn .f.1l#'r. Ci 111111 1
. .~
r 'I ." . . -.
~
~
I
/D" /J '
C/4~S I Mhor ';r/~r/ir/
,
12' 2.' 2-1'
~i rtJ/le
,~
-I
, 'I'
/2'
Il"
CI. i'tJ//4
~
~
//Jd'
C/d6SJE MIJ6r Ar/t"/"/
II' I(J' /2' It' I/J' II'
CI. PI1I1t' Pi'I1f- PJAf- C~ 2(J#
.
r~ .LY
~
.~
'tI'
C/'s~ I C(J/Ne,tJ'
2.'
C/'t7r ~4/11
IJ'" 2~ '
t:/II/r 24Ae
,
~~
~
I
.1
r
.\.k
,,,'
C/ns.Jl' C"/I'erll,,.
FIGURE 19
1YPICAL URBAN ROADWAY SECTIONS
46
'--1.
1
e
e
JOHNSON, DOLEJSI, TURNER PROPERTY
CHANHASSEN, MN.
a planned residential proposal
by
LUNDGREN BROS.
17 JULY 1992
e
PLANNED UNIT DEVELOPMENT (PUD)
CONCEPT PLAN
AND
PRELIMINARY PLAN
PREPARED FOR THE
PLANNING COMMISSION AND CITY COUNCIL
OF
CHANHASSEN, MINNESOTA
Submitted by:
Lundgren Bros. Construction, Inc.
935 East Wayzata Boulevard
Wayzata, Mirmesota 55391
(612) 473-1231
e
/-
.
e
e TABLE OF CONTENTS
I. DEVELOPMENT TEAM
II. INTRODUCTION
III. GENERAL STATEMENT OF CONCEPT
A. Location
B. Legal Description
C. Zoning
D. Project
E. P.U.D. Criteria
F. Comprehensive Plan Acceptability
1. Land Use Guide PlanJDensity
2. Site Utility Availability and Service
3. Traffic Access and Circulation
e
IV. TENT A TIVE STAGING AND SEQUENCE SCHEDULING
V. FINANCIAL CAPABILITY
VI. NATURAL RESOURCE ANALYSIS
i
VII. WETLAND MITIGATION AND ENHANCEMENT
VIII. TREE PRESERV A TION/MONUMENT A TION/SIGNAGE
IX. COVENANTS
X. CONCLUSION
e
I. DEVELOPMENT TEAM
The developer of the Johnson. Dolejsi. Turner property is Lundgren Bros. Construction. Inc.. a
Minnesota Corporation located in Wayzata. Minnesota. The Lundgren Bros. tradition has been
synonymous with quality neighborhoods throughout the Metropolitan Area for 23 years.
e
The Development Team is coordinated by Terry Forbord. Vice President and Project Manager of this
development.
Consultants
Planner:
The site plan design by Dahlgren. Shardlow, and Uban. Inc.. Minneapolis.
MN.
Engineer:
The plat and public facilities engineering by Schoell & Madson. Inc..
Minnetonka. MN.
Surveyor:
Site surveying by Schoell & Madson. Inc.
Legal:
John Kuehn. Leonard Street & Deinard, Minneapolis. MN.
Wetland Biological
Analysis:
Regulated wetland pennits. delineation and monitoring by Summit
Environmental. Inc.. Minneapolis. MN.
Landscape
Architecture:
Entrance monumentation and landscape design by Dahlgren. Shardlow. and
Uban. Inc.
e
Market Analysis:
Preliminary market analysis by Conhaim & Assoc.. Minneapolis. MN.
II. INTRODUCfION
l'
Purpose of Presentation
The purpose of this presentation is to provide the O1anhassen Planning Commission and City Council
details of the proposed Planned Unit Development (p.U.D.) and to obtain the necessary concept plan.
preliminary plan and preliminary plat approval
III. GENERAL STATEMENT OF CONCEPT
A. Location
This proposed Residential Planned Unit Development by Lundgren Bros. is located in
Chanhassen in Section 9, Township 116, Range 23. The property consists of 95 acres. The
project is served by State Highway No. 41 to the west, State Highway No.5 to the south and
vacant land to the north and east.
e
Planned Unit Development Concept & Preliminary Plan
2
B. Legal Description
See attached.
C. Zoning
The project consists of four parcels of land owned by three different owners. The property is
currently zoned A2. The developer proposes to rezone the property to a Residential Planned
Unit Development.
D. The Project
The project consists of 120 single family residential home sites that will be developed on lots
ranging from 75' to 130' lot widths with lot depths varying from 130' to 400'. Each lot will
be developed to match the site with a choice of pre-<1esigned models. Each home will have a
minimum two car garage with a wide driveway and major emphasis placed on walkout
basements where topography allows.
Lot Size:
Gross Average Lot Size
Net Average Lot Size
Smallest Lot Size
Largest Lot Size
34,554 sJ.
21,485 sJ.
12,000 s.f.
71,300 s.f.
Proposed Building Setbacks:
20' Front Yard Setback (minimum)
30' Rear Yard Setback (minimum)
6' Interior Side Yard Setback for Garages
9' Interior Side Yard Setback for Living Area
15' Minimum Combined Between Buildings
40' Rear Yard Wetland Setback (minimum)
Meandering wetlands create a variety of constraints to development, which can be minimized
by mitigative efforts aimed at providing quality homesites while maintaining the integrity and
contributing towards the enhancement of the wetlands. Measures such as conservation
easements, reduced setbacks and restrictive covenants all contribute to this and will be
discussed later.
As noted earlier, lots will vary in size from 12,000 s.t. to 34,000 s.t. The range of lots in this
development is considerable and provides an opportunity to accommodate different home
styles. Besides offering the advantage of a highly varied streetscape, the mixture of home
plans and lot sizes can help to diversify target markets. Generally this option does not achieve
densities as high as those using conventional platting procedures evidenced by the gross
density shown on this plan of 1.3 units/acre with a net average lot size of 21,485 s.f.
Planned Unit Development Concept & Preliminary Plan
3
e
With the difficult constraints on the site, the mitigative measures that we propose such as
preservation of wetlands and vegetation with additional ponding proposed creates a
development that is aesthetically pleasing and environmentally responsible.
These mitigation measures speak to the purpose of the P.U.D. and successfully create the
ultimate condition that the P.U.D. was designed to affect.
Development Summary:
Total Acreage
Private Park
Open Space
R.O.W.
Net Developable
Number of Lots
Gross Density
Net Density
E. P.U.D. Criteria
95.19 ac.
2.30 ac. 2 %
22.08 ac. 23%
10.40 ac. 11 %
60.41 ac. 64%
120
1.3 units/acre (120 + 95.19)
2.0 units/acre (120 + 60.41)
The O1anhassen Zoning Ordinance (May, 1992) outlines three expected attributes of Planned
Unit Developments. Those expected attributes and the developer's findings are outlined
below:
e
I. Attribute: The City should be offered enhanced environmental sensitivity beyond
normal ordinance requirements.
Findin2;: The overall concept is oriented around the deyelopment of individual
neighborhoods defined by the road system and the integrated open space system. This
community was designed to accommodate moderate-size single family homes while
providing generous amounts of open space.
The plentiful open space shown affords the visual amenity provided by ponds,
wetlands, mounds and depressions and combines them with the landscape elements
such as grass, flowers, shrubbery and trees.
Over and above this, open space provides the means to preserve and enhance existing
natural amenities, thus preserving wildlife habitat and migration conidors. Open space
can beneficially influence the micro climate by improving heat radiation and by
providing channels for air drainage and favorable air flows. The system operates as
more than just open space; it provides a readily accessible place for informal
recreation.
The developer has used this process that embraces the delicate balancing act of
locating roads and home sites where it has the least effect on the wetlands, trees and
steep slopes to create a development that is innovative and harmoniously sensitive to
the environment
!
l-
e
Planned Unit Development Concept & Preliminary Plan
4
.
2.
Attribute: Lot sizes should be mixed to reflect the sites' environmental limitations and
opportunities and to offer a range of housing pricing options.
Finding: The proposed plan maximizes the potential of the limited developable land
on this property while providing an efficient use of open space that benefits as many
home sites as possible. Because of the unusual amount of constraints existing on this
site such as: the 10 wetlands, the visual and noise concerns of State Highway No. 41
and the extensive vegetation, Lundgren Bros. is requesting a P.U.D. on this property.
A P.U.D. would provide more efficient use of land and public services, consolidation
of areas for recreation, and reductions in street lengths and other utility related
expenses. The curvilinear road system, rolling topography, and general site design
help create many interesting and unique building sites which further promotes diversity
in housing within the development
3. Attribute: Quality of development in: landscaping, construction quality, provision of
public/private open and recreational space.
a.
Landscaping - By design, the road system locates entrances which identify
points of arrival to individual neighborhoods. The entrance features will
consist of entry monuments, ponds, extensive landscaping and planted
medians. The cul-de-sacs, while allowing development of rolling hills and
creating niches for smaller more private neighborhoods, also affords the
opportunity for landscaped islands, another feature of this development These
areas will be maintained by a homeowner's association as well as covenants on
the land that must be adhered to by owners.
e
b. Construction Quality - Lundgren Bros. invests a great deal of time and money
periodically upgrading its entire home product lj.ne keeping current with design
trends that are the most in demand and efficient The latest innovative
construction techniques are implemented upon their introduction to the
building industry.
Lundgren Bros. has been developing residential single family developments
and building quality homes in the Twin Cities area for 23 years. The
Lundgren Bros. tradition of quality neighborhood communities has been
recognized nationally by many industry publications such as: Better Homes &
Gardens. Professional Builder and Builder Magazine.
c.
Public and Private Open Space - The amount of open space together with the
neighborhood recreation area and the numerous ponds created within the
development are a direct result of the flexibility allowed under a P.U.D.
Additionally, because of reduced lot size and setback requirements the
developer is able to provide other neighborhood community benefits that
reduce the strain on other City parks and trails.
e
The plan addresses the need for neighborhood park activity by locating a 2.3
acre private park in the center of the development. In addition to a pond
Planned Unit Development Concept & Preliminary Plan
5
e
entrance feature, other features proposed are a tennis court, a l{l. basketball
court, a play structure, and other areas for infonnal recreation.
Through the departure from the strict application of required setbacks, yard
areas, lot sizes and other minimum requirements and perfonnance standards
associated with traditional zoning. Planned Unit Developments can maximize
the development potential of the developable land while remaining sensitive to
its unique and valuable natural characteristics.
F. Comprehensive Plan Acceptability
1. Land Use Guide Plan/Density
The property is currently guided for Low Density Residential Single Family Housing
by the City's Land Use Guide Plan. This designation allows 1 to 4 residential
dwelling units per acre. The Jolmson, Dolejsi, Turner property plan proposes 120
residential single family lots on approximately 95 acres for a density of 1.3 dwelling
units/acre.
2. Site Utility Availability and Service
The site is within the MUSA expansion area. The February. 1992 report prepared by
Boonestroo, Rosene, Anderlik & Associates presents the general plan for extension of
trunk sanitary sewer and watennain to this site.
e
Based on the report, sanitary sewer service will be provided by extension of a 12-inch
diameter trunk sewer from the Lake Ann Interceptor. This gravity sewer would
tenninate in the Song property which is immediately east of Ute Johnson, Dolejsi,
Turner site. A lift station is proposed in the southeast-.:portion of the Jolmson, Dolejsi.
Turner site which would pump the waste water by forcemain to the gravity trunk in
the Song property. The internal lateral gravity sewers would be extended from the lift
station. This would be done in phases as necessary to support the phased
development, beginning with the first phase at the west side of the site.
Trunk water service to the site would be provided by extension of a 16-inch diameter
watermain from the pumphouse on Galpin Boulevard to Highway 41. This main
would also pass through the Song property. Watermain laterals would be extended in
phases from the trunk as necessary.
Lundgren Bros. has been working closely with the Songs, and preliminary aligrunents
for the streets which would contain the trunk sewer and watermain in their property
have been developed.
A feasibility study for the trunk sanitary sewer and watennain extensions has been
ordered by the City. The preliminary schedule for the study and the project would
provide for a project bid award in February 1993 and July 1993 construction
completion.
e
l
~
e
e
e
Planned Unit Development Concept & Preliminary Plan
6
The stonn drainage system on the site consists of stonn sewers in streets which will
discharge into stonn water treatment ponds. These ponds will outlet into existing
wetlands. Storm sewer outlets are also provided from all of the existing wetlands to
allow controlling the water levels. In general, the site drainage pattern is from the
north portion of the site to the large wetland in the south portion. The drainage
facilities will be constructed in phases along with the other site improvements.
3. Traffic and Access Circulation
The road system, open space system and trails have been developed to best facilitate
the movement of traffic safely and conveniently in accordance with the City's
designated road system, while at the same time providing a unique neighborhood
community consistent with O1anhassen's high standards.
Primary access to the development will be off of an east-west collector connecting
State Highway No. 41 and County Road No. 117 additionally providing access to the
Song Property located adjacent to the east. The road system is designed to identify a
hierarchy of traffic with cul-de-sacs running into this collector.
The preliminary plan provides for the preservation of 25+ acres of natural wetland and
high ground areas to be used for private park, trails and open space.
IV.
TENTATIVE STAGING AND SEQUENCE SCHEDULE
The developer intends to develop the project in five phases over a period of approximately four to five
years. Obviously, economic conditions may affect the actual time frame and special areas of
development.
The attached accompanying phasing plan identifies the sequence of development of the proposed
development. This sequence is mostly derived by the approximate location of utilities.
V. ANANCIAL CAPABILITY
As the optionee, Lundgren Bros. intends to develop the Johnson, Dolejsi, Turner property once they
receive every governmental approval necessary for development to occur. Lundgren Bros. is a
principal developer in the City of Chanhassen and has never failed to meet its obligations throughout
its history.
VI. NATURAL RESOURCE ANALYSIS
Except for a few concentrations of steep slopes, the topography is generally rolling terrain with the
highest elevation being 1,034 feet and the lowest elevation being 954 feet There exists 24+ acres of
10 separate protected wetlands on the site with both the Anny Corp of Engineers and the City of
Chanhassen having jurisdiction.
Planned Unit Development Concept & Preliminary Plan
7
e
this neighborhood community.
In addition to these natural features, the development will include significant ponding and
enhancement of existing wetlands and along with additional landscape elements proposed by the
developer, we believe the result will be an overall development that is attractive and enduring.
VIll. WETLAND MITIGATION AND ENHANCEMENT
The project contains a total of 24+ acres of wetlands of various types. Generally, the wetland basins
on the project area have been heavily affected by past drainage activities. Virtually all of the wetlands
on site have been subjected either to ditching or subsurface tile line installation. . In some cases, this
drainage activity has been effective enough to eliminate wetland hydrology and in others it has
rendered historic wetlands so marginal that they serve few, if any, functional wetland values.
After extensive analysis and a conscious effon to minimize the development impact on the site,
approximately 2.81 acres of wetland were found unavoidable and are proposed to be filled (see Table
1). In general, the impacts would be incurred by the most degraded wetlands on the site. Of the 2.81
acre total, 1.65 acres or 59 percent consists of Basin 9 and 10 which are extremely marginal in their
soils, hydrology and vegetation. More than 87 percent of the impacts associated with the project will
affect wetlands classified by the City as Ag Urnan. Impacts to wetlands classified as narural have
been limited to fringes and degraded portions of these basins. Because of the extensive distribution of _
wetlands present, it is clear that some wetland impacts cannot be avoided. .,
Sedimentation ponds will intercept and collect storm water runoff prior to discharging it into the
wetlands. The developer's intent is that upon its completion, the site should have equal or greater
wetland acreage with overall higher quality than existed prior to development This should provide an
improved variety of plant types and a better habitat for more species of wildlife.
Compensatory mitigation for unavoidable wetland losses shall occur irl the form of several wetland
creation projects distributed among the least disturbed portions of the site. We have tentatively
identified 2.81 acres of potential wetland creation at seven locations within the site (see Wetland
Impact/Mitigation Exhibit). These sites would provide 1: I acre for acre replacement of wetlands to be
affected by the project The acreage encompassed by these sites is exclusive of storm water
storage/treatment ponds to be constructed for the project As the project moves into final design the
locations and designs of these sites may be altered.
Six of the seven replacement wetlands would be contiguous to and become pan of Basins 13, b or c.
These basins would be excavated to a depth sufficient to create wet meadow or shallow march
conditions. In general, the wetland types to be created will provide substantially higher wetland
functional value than the degraded wetlands affected by the project Bottom substrates for created
wetlands will consist of organic material excavated from existing wetlands to be affected by the
project.
A conservation easement will be established around each wetland. The design of this easement shall
show a natural perimeter that meanders around the edge of the wetland. The depth of the easement
shall vary with 10' being an absolute minimum. TIlis easement, with a minimum depth of 10'
combined with a use able backyard of 30', should provide setbacks to the wetland of 40' minimum.
e
.........---
e
Planned Unit Development Concept & Preliminary Plan
8
The primary purpose of the conservation easement is to provide nesting habitat and wildlife cover
peripheral to the wetland. In addition. the easement combined with the proposed sedimentation ponds
will work together to improve and maintain the character of the wetlands.
Many species of wildlife reside in wetlands and depend. in part. on the presence of a fringe of upland
habitat. The design of this easement shall depict a natural perimeter that meanders around the edge of
the wetland. The depth of the conservation easement shall vary depending on the classification of the
wetland.
Each lot shall have a deed restriction in recordable form and easement that forbids the home buyer
from violating and tampering with the conservation easement
Table 1
Wetland Impact Summary
Lundgren Bros. Chanhassen Residential Development
City Regulatory Acres
Summit Basin No.. City Basin No. Cowardin Type Classification Filled
la A9-7(2) PEMCd Ag/Urban 0.05
e Ib A9-7(2) PEMCd Ag/Urban 0
Ie A9-12(l) PEMCd Ag/Urban 0
2 A9-7(l ) PEMC Ag/Urban 0.25
3 A9-8(3) PEMC & PEMNBE Natural 0.25c
3a ---b PFOIE ---b 0
4 A9-8(2) PEMF Ag/Urban 0.18
5 A9-8(l) PEM/FOIC Natural 0.05
6 A9-4(3) PEM/SSC < Natural+ 0.02
7 A9-8(4) PEMA Ag/Urban 0.22
7a A9-8(4) PEMA Ag/Urban 0.08
8 A9-4(9) PFOI/UBC Ag/Urban 0.06 .
9 A9-7(5) PEMA Ag/Urban 1.65
10 A9-7(5) PEMA Ag/Urban
TOTAL 2.81
. See attached Wetland Impact and Mitigation Exhibit
b Basin No. and Classification has not yet been assigned by Svoboda and Associates. Inc.,
because of its marginal nature, this basin was under further review to determine if it met
minimum wetland criteria.
c Of this impact. 0.22 acres is composed of a man-made drainage swale which provide an
overland outlet for the natural portion of Basin 3.
e
...--
Planned Unit Development Concept & Preliminary Plan
9
e
VIII. TREE PRESERVATION/MONUMENTATION/SIGNAGE
The vast majority of the existing trees are located in areas along the southern large wetland and will
be subject to minimal impact by any home or road construction.
The design attempted to locate other large stands of vegetation in rear yards to preserve them and also
provide a screen to adjacent lots.
There will be some tree loss occasioned by this development. but it is the expressed intention of the
developer to keep tree loss to a minimum.
Professionally designed and landscaped entrance monuments shall be provided at each entrance to the
P.U.D. The elements of the monumentation and signage shall be consistent throughout the
neighborhood community. The design team shall take advantage of the creativity the P.U.D. ordinance
allows and develop an identity that blends well with the natural surroundings. All monumentation
shall be owned and maintained by the homeowners association and shall be consistent with the quality
monumentation found in other exclusive Lundgren Bros. neighborhood communities.
IX. COVENANTS
As in all neighborhood communities created by Lundgren Bros.. strict architectural and protective
covenants shall be established and recorded to protect the investment of each homeowner and the
wetland conservation easements.
e
X. CONCLUSION
Lundgren Bros. feels that the proposed preliminary plan for development of the Johnson. Dolejsi.
Turner property enhances the quality goals and objectives of the City of Chanhassen. It is our
pleasure to respectfully submit to you our proposal and request your acceptance.
e
PAUL & R YOUNGQUIST
. 7105 HAZELTINE BLVD
_EXCELSIOR MN 55331
JAY C DOLEJSI
6961 CHAPARRAL LN
CHANHASSEN MN 55317
JOHN P SAVARYN ESTATE
C/O PAUL SA V ARYN
1049 OAK TERRACE
N MANKA TO MN 56003
DONALD & BEITY LOU ROY
7205 HAZELTINE BLVD
EXCELSIOR MN 55331
TIMOTHY & ANN OAS
7305 HAZELTINE BLVD
EXCELSIOR MN 55331
BRUCE & YNONNE GESKE
7325 HAZELTINE BLVD
EXCELSIOR MN 55331
DAVID WEATHERS & WILLIAM & MERIL YN TURNER WALTER & M WlllTEHILL
KAREN EDELMANN TRUSTEES OF TURNER FAM 7250 HAZELTINE BLVD
7235 HAZELTINE BLVD 3501 SHORE DR EXCELSIOR MN 55331
EXCELSIOR MN 55331 EXCELSIOR MN 55331
---- - ~._---_.-
JANET C KOCH DEAN & J SIMPSON DAVID A STOCKDALE &
7331 HAZELTINE BLVD 7185 HAZELTINE BLVD ANGA MCBRIDE STOCKDALE
EXCELSIOR MN 55331 EXCELSIOR MN 55331 7210 GALPIN BLVD
EXCELSIOR MN 55331
GREGORY & N SCHMIDT TANNA L MOORE CHARLES & VIRGINIA GROSS
2700 CHES MAR FARM RD 2800 STONE ARCH RD 2703 CHES MAR FARM RD
CHANHASSEN MN 55317 WAYZATA MN 55391 EXCELSIOR MN 55331
e
CHAS & IRENE SONG DUANE E & M JOHNSON MILLS PROPERTIES INC
7200 GALPIN BLVD BOX 102 512 LAUREL ST
EXCELSIOR MN 55331 CHASKA MN 55318 POBOX 505
BRAINERD MN 56401
DOUG & THERESA BENlZ
BErrY O'SHAUGHNESSY CHASKA GA TEW A Y PARTNERS 7280 GALPIN BLVD
1000 HESSE FARM RD 3610 HWY 101 S EXCELSIOR MN 55331
CHASKA MN 55318 WAYZATA MN 55391
DARLENE TURCOTTE T F & MARLENE BENTZ J P'S LINKS INC
6430 CITY WEST PKWY #5314 7300 GALPIN BLVD 7750 GALPIN BLVD
EDEN PRAIRIE MN 55344 EXCELSIOR MN 55331 CHANHASSEN MN 55317
e
.
.
.
3
C ITY OF
CHANHASSEN
690 COULTER DRIVE. P.O. BOX 147. CHANHASSEN, MINNESOTA 55317
(612) 937-1900. FAX (612) 937-5739
MEMORANDUM
TO: Park and Recreation Commission
~
FROM:
Todd Hoffman, Park and Recreation Coordinator
DATE:
August 4, 1992
SUBJ:
Carver Beach Park Vehicle Parking
Upon receiving the Commission's recommendation in regard to the designation of four (4)
parking spaces at Carver Beach Park, I consulted the City Manager prior to forwarding this item
to the City Council. Finding the Commission's action consistent with the Carver Beach Park
adopted master plan, the Manager suggested I include the item in the July 27, 1992, City Council
administrative packet as an information item. If no comments were received, I would then move
ahead with the designation of four (4) parking spaces at Carver Beach Park.
No comments or questions were heard from the Council, but prior to moving ahead with this
project, I received a call from a resident of the area. This person stated that they did not believe
all their questions had been addressed satisfactorily at the Park and Recreation Commission
meeting. In talking with the individual, I could not resolve their concerns, and they voiced their
desire to speak with the Mayor.
The Mayor, upon receiving this call, talked with the individual at length. Mayor Chmiel then
took the time to arrange a site inspection with me, after which a meeting between all parties was
scheduled to discuss their concerns. This meeting was held on the morning of July 31, 1992.
The result of that meeting is this recommendation to reconsider your previous action of
recommending a total of four (4) parking spaces be designated, instead, designating a total of
three (3) parking spaces for Carver Beach Park.
RECOMMENDATION
It is recommended that the Park and Recreation Commission rescind their previous
recommendation of June 23, 1992, recommending the City Council approve the construction and
sign age of four parallel parking spaces on the south side of Lotus Trail for Carver Beach Park,
one of the four spaces designated for persons with disabilities as specified and shown on the
attached maps, and that Planning and Engineering take a close and careful look to ensure that
ft
\. ~ PRINTED ON RECYCLED PAPER
there is no damage done to any existing trees in the area; and to instead make the following ~
recommendation: .
The Park and Recreation Commission recommends the construction and signage of three
(3) parallel parking spaces on the south side of Lotus Trail at Carver Beach Park
consistent with the park's master plan, one of the three for persons with handicaps, and
that this project be carried out with the assurance that no damage will be done to any
existing trees in the area.
Action taken by the Commission at the request of Mayor Chmiel will then be forwarded to the
consent agenda of the Chanhassen City Council's August 24, 1992, meeting for City Council
approval.
.
fI
.
e
e
f
C ITV OF
CHANHASSEN
690 COULTER DRIVE. P.O. BOX 147. CHANHASSEN, MINNESOTA 55317
(612) 937-1900. FAX (612) 937-5739
MEMORANDUM
TO: Park and Recreation Commission
-$
FROM:
Todd Hoffman, Park and Recreation Coordinator
DATE:
August 4, 1992
SUBJ:
1993 Park Acquisition and Development Capital Improvement Program
This item was tabled at both the June 23 and July 28, 1992, Park and Recreation Commission
meetings due to time constraints. The 1993 CIP was originally intended to be the single item
of discussion for the August 11 meeting, but the land development proposals (Items 2 and 3 on
the agenda), require the commission's attention as well. It is imperative that the commission
handle these items in a timely manner to leave sufficient time for the 1993 Park Acquisition and
Development CIP to be completed.
At the request of several commissioners, the new 5-Year CIP (1992-1996) has been interfaced
with the CIP document for years 1988-1991 to enable commissioners to identify improvements
which were funded and completed in these years. As previously mentioned, the development of
an annual CIP is one of the most important and detailed requirements of the commission.
n
~ ~ PRINTED ON RECYCLED PAPER
PROPOSED 1992 FUNCTION 410 PARK ACQUISITION AND DEVELOPMENT
CAPITAL IMPROVEMENT BUDGET e
AUGUST, 1991
Current Estimate
Bandimere Community Park
Bandimere Heights Park
Wood Park Identification Sign $ 250.00 $ 200.00
Bluff Creek Park
Carver Beach Park
Play Area Refurbishment 2,200.00 2,200.00
Carver Beach Pia yground
Wood Park Identification Sign 250.00 200.00
Replacement of Swing 950.00 950.00
Addition of Two Spring Animals 1,000.00 l,cm.OO
Border Wood and Pea Gravel 1,400.00 1,400.00
Chanhassen Estates Mini-Park
Wood Park Identification Sign 250.00 200.00
Chanhassen Hills Park e
Wood Park Identification Sign 250.00 200.00
Construction of a Ballfield 1,500.00 1,500.00
Installation of Trees 800.00 00.00
Chanhassen Pond Park
Wood Park Identification Sign for Kerber Blvd. 250.00 200.00
Wheel Chair Accessible Picnic Tabel 500.00 500.00
Picnic Table 450.00 450.00
City Center Park
Play Equipment Expansion (50% Share) 10,000.00 00.00
New Basketball Poles and Standards 1,200.00 00.00
Curry Farms Park
Wood Park Identification Sign 250.00 200.00
Greenwood Shores Park
Herman Field Park
1st Phase Play Area with Border WoodlPea Gravel 13,000.00 1 3,cm.00
Superdeck Boardwalk 6,000.00 6.cm.OO e
e Picnic Tables and Play Area Bench 1,500.00 1,500.00
Lake Ann Park
First Aid Supplies 400.00 00.00
Lifeguard Room Equipment 1,500.00 00.00
Rescue Board 500.00 00.00
Cash Register 750.00 150.00
Freezer 400.00 00.00
Refrigerator 500.00 00.00
Microwave 300.00 00.00
Menu Boards 300.00 00.00
Building Supplies and Equipment 3,000.00 00.00
Row Boats 650.00 00.00
Canoes (2) 1,000.00 00.00
Paddle Boats (2) 1,650.00 00.00
Life Jackets (20) 500.00 00.00
Canoe Paddles (10) 200.00 00.00
Play-Aks (6) 1,800.00 00.00
Play-Ak Paddles (8) 200.00 00.00
Outboard Motor 750.00 00.00
Shelter Landscaping 1,500.00 00.00
Drainage Improvements, Field #6 1,000.00 l,cro.OO
e Supplies for Conversion of Field #2 to
Little League 500.00 500.00
Bituminous Trail Loop 10,500.00 00.00
Basketball Pole 600.00 00.00
Fencing 2,200.00 2,200.00
Boundary Buoys 1,300.00 00.00
Lake Susan Park
Trail Link to Chanhassen Hills 21,000.00 *21,000.00
Archery Range Targets 300.00 300.00
Aeration System Installation 4,000.00 00.00
Track Ride 00.00
Meadow Green Park
Installation of Trees 400.00 400.00
Minnewashta Heights
Play Area Expansion 3,000.00 3,cro.00
North Lotus Lake Park
*This project will require additional funding, with planning/construction spanning both 1992 and
e 1993.
Pheasant Hills Park
Engineering, Surveying, Staking, .Grading e
Surfacing and Site Preparation Associated
With Initial Phase of Construction 20,000.00 10,000.00
Power Hill Park
Prairie Knoll Park
Rice Marsh Lake Park
Play Area Expansion 6,000.00 4,(XX>.00
South Lotus Lake Park
South Ridge Park
Installation of trees 800.00 800.00
Sunset Ridge Park
Installation of trees 800.00 800.00
Park Rules Sign
50 Signs 3,500.00 3,500.00
Picnic Tables, Benches, Spectator Seating, Signage 5,500.00 3,cm.00 e
Boy Scout Project 1,000.00 00.00
Tree Farm 200.00 200.00
Contingency 4.500.00 l.cm.oo
TOTAL $145,000.00 $80,750.00
DIFFERENCE $64,250.00
e
e
CHANHASSEN PARK AND RECREATION DEPARTMENT
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
1992 1993 1994 1995 1996
e
e
e
Five Year Capital Improvement proaram
Park: Bandimere Youth Parkland
Location: South Highway 101
Acreage: 35
Park Type: Community Park
Improvements 1988 1989 1990 1991
Master Park Plan 1,500
Rough Grading
General Improvements
Total -0- 1,500 -0- -0-
e
e
e
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Bandimere Community Park
Address:
9405 Great Plains Blvd (TH 101)
Acres:
30
Class:
Community
Improvements 1992 1993 1994 1995 1996
Complete a needs assessment
study in 1992. Proceed with
development of park based on
results of study.
Notes:
Concept Master Park Plan prepared in 1989.
e
Five Year Capital Improvement Proaram
Parle
Location:
Acreage:
Park Type:
Bandimere Heights Park
Kiowa Trail
3
Neighborhood Park
Improvements 1988 1989 1990 1991
Off-street Parking Asphalt 500
Sand Volleyball Court 500
Basketball
Totlot Expansion 3,500
Total -0- -0- -0- 4,500
e
e
e
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name:
Bandimere Heights Park
Address:
9290 Kiowa Trail
Acres:
3
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Wood Park ID Sign 200.
P lay Area 00. 00. 00. 8,000.
Refurbishment
TOTALS: 200. 00. 00. 00. 8,000.
Notes: Extensive regrading and site work was initiated in the fall of 1991. Work to be
completed in 1992.
1991 Improvements
Play Area Expansion
Sand Volleyball Court
Paving of Offstreet Parking
$3,500.00
$200.00
$400.00
e
Five Year Capital Improvement Proaram
Park:
Location:
Acreage:
Park Type:
Bluff Creek Park
South of Bluff Creek Golf Course
21
Community Park
Improvements 1988 1989 1990 1991
Trail Improvements
Access Road
Land Acquisition
Total -0- -0- -0- -0-
e
e
.
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name:
Address:
Acres:
Class:
Bluff Creek Park
Hesse Farm Road
21
Open Space
Improvements 1992 1993 1994 1995 1996
.00 .00 .00 .00 .00
TOTALS: 00. 00. 00. 00. 00.
Notes: To be incorporated into the Bluff Creek Preservation zone.
e
Five Year Caoitallmorovement Proaram
Parle
Location:
Acreage:
Park Type:
Carver Beach Linear Park
Lotus Trail
8
Neighborhood Park
Imorovements 1988 1989 1990 1991
General Improvements .. 3,000
Seating
Fishing Dock 1,500
Landscaping
Total -0- 3,000 -0- 1,500
.. Retaining wall, raft replacement, canoe racks, etc.
e
e
e
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Carver Beach Park
Address: 6891 Lotus Trail
Acres: 8
Class: Neighborhood
Improvements 1992 1993 1994 1995 1996
P lay Area 2,200.
Refurbishment
Grills(2) 400.
Picnic Tables(2) 1,300.
Swimming Bouy's 1,500.
& Signage
(Mini Beach)
Swimming Bouy's
& Signage 1,500.
(Main Beach)
Park Benches 2,000.
TOTALS: 2,200. 3,200. 1,500 00. 2,000.
Notes:
e
Five Year Capital Improvement Proaram
Park:
Location:
Acreage:
Park Type:
Carver Beach Playground
Carver Beach Road
3
Neighborhood Park
Improvements 1988 1989 1990 1991
Basketball Court 3,000
Park 10 Sign
Landscaping
Totlot Upgrading 5,000
Total 3,000 -0- -0- 5,000
e
e
e
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name:
Carver Beach Playground
900 Carver Beach Road
Address:
Acres:
3
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Wood Park I D Sign 200.
Replacement of Swing 950.
Add'n of Two Spring 1,000.
Animals
Board Wood & Pea 1 ,400.
Gravel
Bleacher 1 ,400.
Skating Rink Electrical 6,000.
Sevice with Light
New Backstop 1,200.
TOTALS: 3,550. 7,400. 00. 00. 1,200.
Notes:
1991 Improvements
Play area expansion 5,000.00
e
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Chanhassen Estates Mini Park
Address: 55 Lake Drive East
Acres: 1
Class: Neighborhood
Improvements 1992 1993 1994 1995 1996
Wood Park ID Sign 200.
Picnic Tables(3) 2,000.
Basketball Court 2,500.
Play Area 00.
TOTALS: 200. 2,000. 2,500. 00.
Notes:
Park:
Location:
Acreage:
Park Type:
Five Year Capital Improvement Proaram
Chanhassen Hills Park
Chanhassen Hills Drive South
8
Neighborhood Park
Improvements 1988 1989 1990 1991
Master Park Plan 2,000
General Development 10,000
Tennis Courts
Total -0- 2,000 10,000 -0-
e
e
e
.
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Chanhassen Hills Park
Address:
8579 Chanhassen Hills Drive South
Acres:
8
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Wood Park 10 Sign 250.
Construction of a 1,500.
Ballfield
Installation of Trees
Double Tennis Court 30,000.
with Basketball
Hoops
Trees 1,000.
Play Area Expansion 00. 00. 10,000.
TOTALS: 1,750. 31,000. 00. 00. 10,000.
Notes:
e
Five Year Capital Improvement Proaram
Parle Chanhassen Pond Park
Location: Kerber Boulevard
Acreage: 16
Park Type: Neighborhood Park, Open Space
Improvements 1988 1989 1990 1991
Wood Duck Houses 100
Off-Street Parking
Benches
Correction of Erosion Problems
Grade Trail
Total -0- 100 -0- -0-
e
e
.
e
.
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Chanhassen Pond Park
Address:
7500 Laredo Drive
Acres:
16
Class:
Open Space
Improvements 1992 1993 1994 1995 1996
Wood Park 10 Sign 200.
Wheel Chair 500.
Accessable Picnic
Table
Picnic Table 450.
Wood Park 10 Sign 250.
Replace Stairs 00. 00. 4,000.
TOTALS: 1,150. 250. 00. 00. 4,000.
Notes:
1991 Improvements
Correction of erosion areas
3,000.00
.
Five Year Capital Improvement Program
Park:
Location:
Acreage:
Park Type:
City Center Park
Coulter Drive
10
Community Park
Improvements 1988 1989 1990 1991
Warming House 500
Tennis Windscreen 500
Play Surface
Totlot 40,000
Master Park Plan 2,000
Park Reconfiguration 60,000 *
Total 500 500 -0- 102,000
e
* 30,000 of this 60,000 was in the form of a Community Development Block Grant for purchase of Handicapped Accessible
Play Equipment.
.
.
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: City Center Park
Address:
710 Coulter Drive
Acres:
10
Class:
Community
Improvements 1992 1993 1994 I 1995 1996
Play Area Expansion
(50% share)
New Basketball
Poles and Standards
Play Area Expansion 12,000.
(50% Share)
Tennis Courts
Maintenance 4,000.
TOTALS: 00. 00. 16,000. 00. 00.
Notes: Configuration of park is subject to change dependent on the outcome of Central
Park Master plans.
1991 Improvements
Play area expansions
Tennis Court Refurbishment
Master Plan Development
Warming House
70,000.00
25,000.00
2,000.00
1 ,000.00
e
Five Year Capital Improvement Proaram
Park:
Location:
Acreage:
Park Type:
Curry Farms Park
Devonshire Drive
6
Neighborhood Park
Improvements 1988 1989 1990 1991
Totlot 2,500
Master Park Plan 2,000
General Development 10,000
Tennis Courts
Total 2,500 2,000 -0- 10,000
e
e
.
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Curry Farms Park
Address:
1300 Stratton Court
Acres:
6
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Wood Park 10 Sign 200.
Trees 500.
Trees 00. 00. 500.
TOTALS: 200. 500. 00. 00. 500.
Notes: 1991 Improvements:
Play area expansion
Ballfield construction
Trail construction
2,500.00
2,000.00
5,500.00
Park:
Location:
Acreage:
Park Type:
Improvements
Land Acquisition
Total
Greenwood Shores Park
Utica Lane
4
Neighborhood Park
1988
-0-
e
Five Year Capital Improvement Proaram
1989
-0-
1991
-0-
1990
-0-
-0-
-0-
-0-
-0-
e
e
.
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Greenwood Shores Park
Address:
7110 Utica Lane
Acres:
4
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Picnic Tables(2) 1,300.
Grills(2) 400.
TOTALS: 00. 1,700. 00. 00. 00.
Notes: Discussion included possibility of installing a sand volleyball court. Site
constrictons make this installation prohibitive.
Parle Herman Field Park
Location: Forest Avenue
Acreage: 13
Park Type: Neighborhood Park
Improvements
Access Road, Initial
Phase of Development
1988
e
Five Year Capital Improvement Proaram
1989
1990
-0-
1991
50,000
Total
-0-
-0-
-0-
50,000
e
e
.
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Herman Field Park
Address:
2591 Forest Avenue
Acres:
13
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
1 st Phase Play Area 13,000.
with Border
Wood/Pea Gravel
Superdeck 6,000.
Boardwalk
Picnic Tables & Play 1,500.
Area Bench
Single Tennis Court 20,000.
with Basketball Hoop
Play Area Expansion Beyond
1996
TOTALS: 20,500. 00. 00. 20,000.
Notes: Construction of trail loops will be completed in 1992 by park maintenance
personnel. Negotiations for a trail connection to Minnewashta Regional Park
are underway.
1991 Improvements:
Grading surfacing, installation of access road
50,000.00
e
Five Year Capital Improvement Program
Park:
Location:
Acreage:
Park Type:
Lake Ann Park
On the north side of Highway 5, 1 mile west of downtown Chanhassen
98
Community park
Improvements 1988 1989 1990 1991
Totlot 8,000
Expansion Project (300,000)*
Totlot (Ballfields) 10,000
Totlot (Ballfields Phase II) 9,000
Nature Trail (Woods)
Community Park Shelter
Street Curbing
Raft 10,000
Concession Improvements
Soccer Lights
Handicap Picnic Area
Player Benches 2,500 e
Total 8,000 10,000 9,000 12,500
* Referendum Funds: These costs were not calculated into the totals.
e
. FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
e
e
Park Name: Lake Ann Park
Address: 1456 Arboretum Blvd (Hwy 5)
Acres: 98
Class: Community
Improvements 1992 1993 1994 1995 1996
SHELTER
First Aid supplies
Lifeguard Room Equipment
Rescue Board
Cash Register 150.
Freezer
Refrigerator
Microwave
Menu Boards
Building Supplies &
Equipment
Row Boat
Canoes (2)
Paddle Boats (2)
Life Jackets (20)
Canoe Paddles (10)
Play-aks (6)
Play-ak Paddles (8)
Outboard Motor
Shelter Landscaping
Boundary Buoys
SUBTOTAL: 150.
.
e
e
GENERAL 1992 1993 1994 1995 1996
Basketball Pole
Drainage Improvements, 1,000.
Field #6
Supplies for Conversion of 500.
Field #2 to Little League
Bituminous Trail Loop
Fencing 2,200.
Picnic Shelter (Parkview) 50,000.
Ballfield Restroom & Beyond 1996
Concession Bldg.
SUBTOTAL: 3,700. 00. 00. 00. 50,000.
GRAND TOTAL: 3,850. 00. 00. 00. 50,000.
Notes: Lake Ann Park is entering a stage of final transformation to a "full service"
community park. The installation of services, Le. phone, electric, sewer, water
will allow the future construction of a group reservation picnic shelter at the
parkview area, the construction of a serviceable shelter at the ballfields, and
other improvements.
1991 Improvements
Swimming raft 10,000.00
Player benches 2,500.00
Five Year Capital Improvement Proaram
e
Parle
Location:
Acreage:
Park Type:
Lake Susan Park
Intersection of Lake Drive & CR 17
27
Community Park
Improvements 1988 1989 1990 1991
LAWCON Grant Project* 221,000
Totlot 10,000
Totlot Expansion 10,000
Bleacher, Player Benches 2,500
Total -0- 110,500** 10,000 12,500
* Entrance road, boat access, ballfield, archery, trail, fishing pier, tennis, basketball, etc.
** As this is a matching grant, only one-half of the project cost is paid by city.
e
e
.
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Lake Susan Park
Address:
903 Lake Drive East
Acres:
27
Class:
Community
Improvements 1992 1993 1994 1995 1996
Trail Line to 21,000.
Chanhassen Hills
Archery Range Targets 300. 500. 1,000.
Aeration system
Installation
Track Ride
Ballfield Lights 65,000.
TOTALS: 21,300. 65,500. 00. 1,000. 00.
Notes: 1991 Improvements - Completion of Lake Susan Park expansion project and
play area.
e
Five Year Caoitallmorovement Proaram
Park:
Location:
Acreage:
Park Type:
Meadow Green Park
Pontiac Drive
21
Neighborhood Park
I moroveme nts 1988 1989 1990 1991
Paved Parking 2,000
Tennis Nets 600
Bleachers 3,000
Bike Rack
Total 5,600 -0- -0- -0-
tit
e
.
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Meadow Green Park
Address:
921 Pontiac Lane
Acres:
18
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Installation of Trees 400.
Bleacher 1 ,400.
Skating Rink Electrical 6,000.
Service With Light
Play Area 20,000.
Refurbishment
TOTALS: 400. 7,400. 00. 00. 20,000.
Notes:
e
Five Year Capital Improvement Proaram
Parle
Location:
Acreage:
Park Type:
Minnewashta Heights Park
Dogwood Avenue
2
Neighborhood Park
Improvements 1988 1989 1990 1991
Park 10 Sign 400
Totlot Updating
Warming Shelter
Total 400 -0- -0- -0-
tit
e
.
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Minnewashta Heights Park
Address:
6220 Dogwood Avenue
Acres:
2
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Play Area Expansion 3,000.
Skating Rink Electrical 6,000.
Service w/Light
P lay Area 7,000. 00.
Refurbishment
TOTALS: 3,000. 6,000. 00. 7,000. 00.
Notes: 1991 Improvements - Installation of play area border and resilient surfacing
completed.
e
Five Year Capital Improvement Program
Parle
Location:
Acreage:
Park Type:
North Lotus Park
Pleasant View Road
18
Neighborhood Park
Improvements 1988 1989 1990 1991
T otlot 5,000
Ballfield 15,000
Volleyball Courts 300
Paved Parking 2,000
Totlot Expansion
Tennis Courts Natural Windscreen
Swings 1,000
Total 20,300 2,000 -0- 1,000
e
e
.
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: North Lotus Lake Park
Address:
295 Pleasant View Road
Acres:
18
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Skating Rink Electrical 8,000.
Service w/Lights
Hockey Rink with 25,000.
Lights
Play Area Expansion 12,000.
TOTALS: 00. 8,000. 12,000. 25,000. 00.
Notes: Additional wind screen plantings for the tennis courts will occur in 1992.
Parle
Location:
Acreage:
Park Type:
Improvements
Pheasant Hill Parkland
Lake Lucy Lane
10
Neighborhood
1988
Master Plan
General Development
e
Five Year Capital Improvement Proaram
1989
1990
1991
2,500
2,500
e
e
.
-
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Pheasant Hill Park
Address:
1720 Lake Lucy Lane
Acres:
11
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Engineering, surveying, 10,000.
Staking, Grading,
Surfacing, & Site
Preparation Associated
with Initial Phase of
Construction
Play Area 20,000.
Picnic Tables 3,000.
Park Benches 1,600.
Double Tennis Court Beyond
with Basketball Hoops 1996
Play Area Expansion Beyond
1996
TOTALS: 10,000. 00. 24,600. 00. 00.
Notes:
Park Master Plan approved in 1991.
e
Five Year Capital Improvement Program
Park:
Location:
Acreage:
Park Type:
Lake Susan Hills West - Power Hill
18
Neighborhood Park
Improvements 1988 1989 1990 1991
Master Park Plan
Totlot
General Development
Total -0- -0- -0- -0-
e
e
e
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Power Hill Park
Address:
Flamingo Drive
Acres:
18
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Final Grading, Seeding 10,000.
Entrance Road &
Parking
Play Area 18,000.
Trees 2,500.
TOTALS: 00. 10,000. 2,500. 18,000. 00.
Notes:
Boundary of this park is being defined through the development of the 7th and 8th
addition of Lake Susan Hills West. New homes are currently being constructed on the
eastern border of the park.
Park:
Location:
Acreage:
Park Type:
Improvements
Totlot
Total
e
Five Year Capital Improvement Proaram
Lake Susan Hills West - Prarie Knoll
Dove Court
4
Neighborhood Park
1988
1989
1990
1991
-0-
-0-
-0-
-0-
-0-
e
e
e
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Prairie Knoll Park
Address:
1124 Dove Court
Acres:
4
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Site Preparation 4,000.
Play Area
TOTALS: 00. 00. 4,000. 00.
Notes: The access trail to Prairie Knoll Park from Dove Court will be installed by the
developer to the rear of the lots which it bisects. .
e
Five Year Capital Improvement Proaram
Park:
Location:
Acreage:
Park Type:
Rice Marsh Lake Park
Erie Circle
30
Neighborhood Park
Improvements 1988 1989 1990 1991
Paved Parking 1,500 -0- -0- -0-
Bleacher 1,000
Totlot Expansion
Total 1,500 -0- -0- 1,000
e
e
e
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Rice Marsh Lake Park
Address:
8119 Erie Circle
Acres:
30 (90% wetland)
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Play Area Expansion 4,000.
P lay Area 7,000.
Refurbishment
Picnic Shelter Beyond
Replacement 1996
TOTALS: 4,000. 00. 00. 00. 7,000.
Notes: 1991 Improvements - Completion of half court basketball court, installation of
swing unit and expanded border wood area.
e
Five Year Capital Improvement Proaram
Park:
Location:
Acreage:
Park Type:
South Lotus Lake Park
South Shore Drive
5
Neighborhood Park
Improvements 1988 1989 1990 1991
Fishing Dock 1,500
Ballfield
General Improvements (Trees & Bench) 1,000
T otlot 10,000
Tennis Courts
Total 1,500 -0- -0- 11,000
e
e
e
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: South Lotus Lake Park
Address:
7610 South Shore
Acres:
7
Class:
Community
Improvements 1992 1993 1994 1995 1996
Unsurmountable 10,000.
Curbing
Play Area Expansion 14,000.
TOTALS: 00. 00. 10,000. 00. 14,000.
Notes: 1991 Improvements - Grading, drainage and landscaping improvement project
completed, play area to be installed.
"',
e
Five Year Capital Improvement Proaram
Park:
Location:
Acreage:
Park Type:
Lake Susan Hills West - Sunset Ridge
Lake Susan Hills Drive West
9
Neighborhood Park
Improvements 1988 1989 1990 1991
Master Park Plan 2,000
T otlot 10,000
General Development 3,000
Tennis Courts
Total -0- 2,000 -0- 13,000
e
e
.
e
e
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM
Park Name: Sunset Ridge Park
Address:
1364 Lake Susan Hills Drive
Acres:
10
Class:
Neighborhood
Improvements 1992 1993 1994 1995 1996
Installation of Trees 800.
Single Tennis Court 20,000.
with Basketball Hoop
Trees 1,000.
Play Area Expansion 14,000.
TOTALS: 800. 21 ,000. 00. 14,000. 00.
Notes: Initial development of park will be completed in 1991, with total expenditures
of $19,000.
e
OTHER IMPROVEMENTS
Improvements 1992 1993 1994 1995 1996
Park Rules Signs 3,500.
Picnic Tables, Benches 3,000.
Spectator Seating, Signage
Boy Scout Project
Tree Farm 200.
Contingency 1,000.
TOTALS: 7,700.
e
e
.
CHANHASSEN PARK AND RECREATION DEPARTMENT
FIVE YEAR CAPITAL IMPROVEMENT PROGRAM TOTALS
4
e YEAR AMOUNT
1992 $ 80,950.00
1993 $163,950.00
1994 $ 73,100.00
1995 $ 85,000.00
1996 $116,700.00
e