Loading...
PC Staff Report 08-16-2011PC DATE: August 16, 2011 l CC DATE: September 12, 2011 1 REVIEW DEADLINE: September 13, 2011 CASE #: 2011 -08 BY: RG, TJ, ML, JM, JS, JS PROPOSED MOTION: "The Chanhassen Planning Commission recommends that City Council approve the Site Plan for a parking lot expansion located at 950 Lake Drive, plans prepared by Alliant Engineering, Inc., dated July 19, 2011, subject to the conditions of the staff report; and adoption of the Findings of Fact and Recommendation." SUMMARY OF REQUEST: The applicant is requesting Site Plan Review for a 155 -stall parking lot expansion for the Lake Drive Business Center building. LOCATION: 950 Lake Drive Lot 1, Block 1, Empak Addition (PID 25- 2710010) APPLICANT: CSM Corporation Attn: John Ferrier 500 Washington Avenue South, Suite 3000 Q Minneapolis, MN 55415 (612) 395 -7000 jferrier e ,csmcorp.net PRESENT ZONING: Industrial Office Park (IOP) 2020 LAND USE PLAN: Office Industrial ACREAGE: 12.6 acres DENSITY: 0.35 F.A.R. LEVEL OF CITY DISCRETION IN DECISION - MAKING: The City's discretion in approving or denying a site plan is limited to whether or not the proposed project complies with Zoning Ordinance requirements. If it meets those standards, the City must then approve the site plan. This is a quasi-judicial decision. PROPOSAL /SUMMARY The applicant is proposing a 155 -space expansion of the site parking. The applicant believes that this parking expansion makes the building more marketable to office and warehouse tenants. They have been in contact with potential tenants who have expressed a concern about the lack of parking near the office portion of the building, which is located on the west end of the building. Additionally, the parking expansion permits greater flexibility for additional office space within the building. The parking will be installed in phases with the parking immediately southwest of the CITY OF CHANHASSEN Planning Commission Lake Drive Business Center Site Plan — Planning Case 2011 -08 August 16, 2011 Page 2 of 10 building being installed first. The parking in the southeast portion of the building will be installed second, and the parking on the east end and the truck loading/maneuvering area will be installed third. However, should a large user be found all the parking could be installed in one phase. Some of this parking (located east of the building) was previously shown as part of a building expansion approved in 2000, but was held in proof of parking status. However, the proposed parking lot expansion and the resulting grading operation exceeded the amount that could be approved by staff administratively (1,000 cubic yards). The City may approve site grading through the site plan review process, the interim use process or as part of a subdivision. Since the proposal includes both landscaping, sign relocation and site lighting review in addition to the grading and parking lot expansion, the site plan review process is appropriate. With this site plan, they will have all their approvals in place for construction of the parking lot expansion. The property to the east is Roberts Automatic Products, another industrial user. Lake Susan Park is located south across Lake Drive. To the west across Powers Boulevard is a vacant office /industrial site. To the north are the railroad tracks at the top of a steep slope (elevation 946), 35 feet above the finished floor elevation of the building (elevation 911). To the southwest, the proposed parking expansion will be approximately seven feet above the corner of Powers Boulevard and Lake Drive. The site is served by City sewer and water service. Access is via Lake Drive with two driveways. Truck access is limited to the easterly driveway. The building is currently estimated to have the following breakdown of space usage: Office — 16,500 square feet, manufacturing area — 78,760 square feet and warehouse — 96,925 square feet. When the site plan was originally approved in 1989, the parking requirements for an office use were 3 spaces per 1,000 square feet of building area. At the time of the building expansion in 2000, City of Chanhassen's standards were 4.5 spaces per 1,000 square feet. Based on the parking requirements, the site needed the following parking: Office — 74 spaces, largest shift — 65 spaces, warehouse — 54 spaces. The total spaces needed were 193 spaces. There were ample locations to incorporate additional parking on site. At that time, staff visited the site on two different occasions and noticed that approximately one -half of the parking was occupied. The City permitted 30 percent of the parking (58 stalls) in proof of parking pursuant to section 20- 1124 (1) of the City Code. These spaces are located along the east side of the building. If parking had become a problem, the City could have required the installation of the additional parking spaces. Staff is recommending approval of the site plan subject to the conditions of this staff report. APPLICABLE REGUATIONS Section 20 -106 — 20 -116, Site Plan Review Section 20 -811— 20 -816, IOP District Regulations Section 20 -1116 — 20 -1124, Parking and Loading Section 20 -1176 — 20 -1183, Landscaping and Tree Removal Planning Commission Lake Drive Business Center Site Plan — Planning Case 2011 -08 August 16, 2011 Page 3 of 10 BACKGROUND On November 14, 2000, the Chanhassen Planning Commission as the Board of Appeals and Adjustments approved a six (6) foot variance from the 50 -foot height limitation for the construction of storage silos. On August 28, 2000, the Chanhassen City Council approved Site Plan #2000 -10 for a 96,925 square -foot expansion to a 95,260 square -foot building. On April 24, 1989, the Chanhassen City Council approved the plat of Lot 1, Block 1, Empak Addition, replatting Lots 1 and 2, Block 2, Chanhassen Lakes Business Park 2 nd Addition. On April 10, 1989, the Chanhassen City Council approved site plan #89 -1 for a 77,690 square - foot office and production facility. GENERAL SITE PLAN The applicant is proposing a three- phase, 155 -space expansion of the site parking. The parking expansion southwest of the building is proposed to be installed first; the parking in the southeast portion of the building installed second; and the parking on the east end and the truck loading/maneuvering area installed third. Parking lot landscaping, parking area lighting and extensive retaining walls are included as part of the plan. The sign in the southwest corner of the building will be relocated further north on Powers Boulevard. ACCESS Access to the site is provided from Lake Drive via two existing driveways. No additional street access is being proposed. GRADING AND DRAINAGE This 12.6 -acre site is located in Empak Addition which is on the northeast corner of Powers Boulevard and Lake Drive. A 188,900 square foot building with parking is currently on the site. Beyond the parking and building areas is grass. This development is located in the Bluff Creek Watershed District. Grading will take place on the site to prepare the parking areas. The grass area maximum slope must not exceed 3:1. Runoff from this site will be treated using an underground treatment system. The drainage and storm sewer system within the site is privately owned and must be maintained by the owner. Existing runoff rates must be maintained for the 2 -, 10- and 100 -year rain events. The drainage 4 ' I o t LOT BLOCK 1 t � y l /. ACCESS Access to the site is provided from Lake Drive via two existing driveways. No additional street access is being proposed. GRADING AND DRAINAGE This 12.6 -acre site is located in Empak Addition which is on the northeast corner of Powers Boulevard and Lake Drive. A 188,900 square foot building with parking is currently on the site. Beyond the parking and building areas is grass. This development is located in the Bluff Creek Watershed District. Grading will take place on the site to prepare the parking areas. The grass area maximum slope must not exceed 3:1. Runoff from this site will be treated using an underground treatment system. The drainage and storm sewer system within the site is privately owned and must be maintained by the owner. Existing runoff rates must be maintained for the 2 -, 10- and 100 -year rain events. The drainage Planning Commission Lake Drive Business Center Site Plan — Planning Case 2011 -08 August 16, 2011 Page 4 of 10 calculations do not match the plans. The applicant must submit revised plans and calculations meeting City requirements. An easement is required from the appropriate property owner for any off -site grading. If importing or exporting material for development of the site is necessary, the applicant will be required to supply the City with detailed haul routes. Erosion and Sediment Control The applicant has prepared an erosion control plan for all phases of this project. The first phase of this project will result in 3:1 slopes with a positive grade towards Lake Drive. This disturbed area will need to be covered with erosion control blanket or sod within 14 days of cessation of work. This should be indicated in the plan. Other than the need for blanket or sod on all 3:1 slopes, the plan appears adequate for existing conditions. However, a note must be added to the plan that additional best management practices may be necessary as site and climatic conditions change throughout construction. To assure that erosion and sediment control best management practices are installed and maintained, an escrow or letter of credit in the amount of $2,450 will be required with the first phase. This number was calculated based upon 450 feet of silt fence, three (3) inlet protection devices, and 370 yards of blanket and seed. Storm Water Management The applicant is proposing to construct 155 new parking stalls in three areas. These parking areas are to be phased in with only the most southwesterly parking area being constructed with the first phase. The applicant is proposing to utilize perforated storm sewer and embedded within a rock trench to achieve rate control and some pre- treatment of the runoff. Water from this site is directed to Lake Susan pond (LS- P3.34). Approximately 150 acres of commercial and industrial land use is also directed to the Lake Susan Pond. This water is routed through three primary storm sewer conveyance routes. Powers Boulevard from MN T.H. 5 to Lake Drive is routed through a 30 -inch RCP along Powers Boulevard. Chanhassen Retail Addition is routed through a 36 -inch RCP immediately east of the subject property. The third area drains through a 30 -inch RCP along Lake Drive and accepts drainage from Lake Drive as well as the intersection of T.H. 5 and MN T.H. 101. Because of the size of the drainage area being conveyed through these pipes, the applicant must either model the entire watershed to Mk 1- 5 � LOT 1 N BLOCK 1 t w� r To assure that erosion and sediment control best management practices are installed and maintained, an escrow or letter of credit in the amount of $2,450 will be required with the first phase. This number was calculated based upon 450 feet of silt fence, three (3) inlet protection devices, and 370 yards of blanket and seed. Storm Water Management The applicant is proposing to construct 155 new parking stalls in three areas. These parking areas are to be phased in with only the most southwesterly parking area being constructed with the first phase. The applicant is proposing to utilize perforated storm sewer and embedded within a rock trench to achieve rate control and some pre- treatment of the runoff. Water from this site is directed to Lake Susan pond (LS- P3.34). Approximately 150 acres of commercial and industrial land use is also directed to the Lake Susan Pond. This water is routed through three primary storm sewer conveyance routes. Powers Boulevard from MN T.H. 5 to Lake Drive is routed through a 30 -inch RCP along Powers Boulevard. Chanhassen Retail Addition is routed through a 36 -inch RCP immediately east of the subject property. The third area drains through a 30 -inch RCP along Lake Drive and accepts drainage from Lake Drive as well as the intersection of T.H. 5 and MN T.H. 101. Because of the size of the drainage area being conveyed through these pipes, the applicant must either model the entire watershed to Planning Commission Lake Drive Business Center Site Plan — Planning Case 2011 -08 August 16, 2011 Page 5of10 show that there is adequate capacity in the pipes or maintain, or preferably decrease discharge rates to the system. While this system is generally acceptable, it is undetermined at this time how it will be maintained. The City has required, and the consulting engineer has agreed to provide, a long- term operations and maintenance plan for this system. This system will remain private and the land owner will be responsible for the maintenance of the system. With proper lead time, staff has indicated to the applicant's engineer that the City would have an interest in working with the applicant to procure grant funds and partner or accept cash in lieu of installation of the pretreatment features being proposed. Because of the existing infrastructure and size of the contributing watershed, rate control must be achieved on site. However, the City would still have an interest in partnering with the applicant and other agencies to implement some alternative storm water BMPs. WETLANDS AND SHORELAND No wetlands appear to exist on or immediately adjacent to the proposed project area. Although the subject property is tributary to both Lake Susan and Riley Creek, it lies outside of the shoreland overlay district for both of these water bodies. RETAINING WALLS The proposed retaining walls are as follows: Location Length (approx.) Maximum Height (approx.) Southeast corner parking area 1 (Wall 1 ) 70 feet 2.5 feet North side of parking area 2 — 5' from the building (Wall 2) 430 feet 6.8 feet East side of parking area 3 (Wall 3 ) 360 feet 8.8 feet North side of parking area 4 (Wall 4) 330 feet 17.5 feet Building permits are required for all retaining walls four feet tall or higher and must be designed by a Structural Engineer registered in the State of Minnesota. The exits in front of Wall 2 may be inadequate for some uses of the building under the proposed parking scenario. Exterior exit discharge must accommodate exits served. The parking stalls in this area should be constructed at the time when a final end user is determined so that the exits will not limit the occupancy. The wall and support structure (not including soil) in Parking Area 3 must be moved outside of the City utility easement. A 36 -inch diameter storm sewer is within this easement. Moving the wall in this area will cause a reduction in the number of parking stalls. Planning Commission Lake Drive Business Center Site Plan — Planning Case 2011 -08 August 16, 2011 Page 6 of 10 UTILITIES Details must be provided for all proposed storm, sanitary, and watermain crossings. Actual elevations of existing utilities shall be verified for accuracy. All of the utility improvements are required to be constructed in accordance with the City's latest edition of Standard Specifications and Detail Plates. The applicant is also required to provide the City with the necessary financial security in the form of a letter of credit or cash escrow to guarantee the installation of the storm sewer, erosion control, and seeding. This amount will be determined prior to start of construction due to the possible phasing of the project and not knowing the amount to be installed and disturbed. The applicant must also notify the City after installation of the erosion control and 48 hours prior to the commencement of grading. Permits from the appropriate regulatory agencies will be required. LIGHTING /SIGNAGE The applicant is proposing parking lot lighting as part of the parking area expansion. The photometric plan describes the use of 25 -foot poles, which would comply with city requirements that restrict pole height to 30 feet. City code requires that all fixtures must be shielded, high - pressure sodium or light- emitting diode (LED) with a total cutoff angle equal to or less than 90 degrees. The applicant is proposing relocating the monument sign on the site. This relocation will require a separate building permit and sign permit. Such sign shall not exceed 64 square feet in display area nor be greater than eight feet in height. The proposed monument sign is shown 35.7 feet from the westerly property line. LANDSCAPING/TREE PRESERVATION Minimum requirements for landscaping include 472 square feet of landscaped area around the parking lot, two trees for the parking lot, and bufferyard plantings along Lake Drive, as well as neighboring property lines. The applicant's proposed as compared to the requirements for landscape area and parking lot trees is shown in the following table. Required Proposed Vehicular use landscape area 12,655 square feet >12,655 square feet Trees/ parking lot 50 overstory trees 14+ existing (not shown on p lans) Landscape islands or p eninsulas required 16 7 Bufferyard B — S. property line Adequate screening in accord with existing buffer plantings Screening needs revision Planning Commission Lake Drive Business Center Site Plan — Planning Case 2011 -08 August 16, 2011 Page 7 of 10 Applicant does not meet minimum requirements for parking lot landscape islands /peninsulas or required trees. The applicant shall submit a revised landscape plan showing the minimum number of landscape islands /peninsulas and trees. Additionally, screening for parking along Lake Drive is not adequate. The applicant can match the existing screening or revise the selected shrubs to a species with greater height. _ Extend Islaurl The landscape island on the north end of the parking proposed adjacent to the east side of the building shall be extended further out to provide full protection of the parking space immediately adjacent to the island. MISCELLANEOUS Building The propose number of accessible parking spaces (7) with adjacent access aisles and their locations are in accordance with Minnesota State Building Code (Chap. 1341, Accessibility). The plans and drainage calculations must be signed by a professional engineer licensed in the State of Minnesota. OTHER AGENCY APPROVALS The applicant will be responsible for applying for and procuring any additional permits that may be required for this project. It appears that all phases of this project exceed one acre of disturbance. If this is the case a National Pollution Discharge Elimination System construction stormwater permit will be required. COMPLIANCE REVIEW Required Parking Setback: North — 0', East — 0', South — 25', West — 30' Proposed Parking Setback: North — 60', East — 20', South — 25', West — 35' Parking Standards: Manufacturing or processing plant — One off - street parking space for each employee on the major shift and one off - street parking space for each motor vehicle when customarily kept on the premises. Office buildings (administrative, business or professional) — Buildings under 49,999 square feet, five stalls per 1,000 square feet gross floor area; buildings from 50,000 to 99,999 square feet, four stalls per 1,000 square feet gross floor area; and buildings over 100,000 square feet, three stalls per 1,000 square feet gross floor area. Building area square footages shall exclude common areas such as reception areas, cafeterias, hallways, etc. in calculating the parking requirements for an office building. Storage, wholesale, or warehouse establishments — One space for each 1,000 square feet of gross floor area up to 10,000 square feet and one additional space for each additional 2,000 square feet, Planning Commission Lake Drive Business Center Site Plan — Planning Case 2011 -08 August 16, 2011 Page 8of10 plus one space for each company vehicle operating from the premises. If it can be demonstrated by the applicant that the number of employees in the warehouse or storage area will require less than the required number of spaces, and if the applicant shall submit a letter to the city assuring that if there is to be any increase in employees, the applicant agrees to provide additional parking area, then the city may approve a lesser number of parking spaces. Hard Surface Coverage: permitted - 70% proposed - 63% RECOMMENDATION Staff recommends that the Planning Commission recommend approval of the site plan subject to the conditions of the staff report and adoption of the attached findings of fact and recommendation. The recommended conditions of approval are as follows: Planning Department Conditions 1. The applicant shall enter into a site plan agreement and provide the security required by it. 2. This relocated sign shall require a separate building permit and sign permit. 3. The landscape island on the north end of the parking adjacent to the east side of the building shall be extended further out to provide full protection of the parking stall. Environmental Resource Specialist Conditions 1. The applicant shall submit a revised landscape plan showing the minimum number of landscape islands /peninsulas (16) and trees (50). 2. The applicant shall provide adequate screening for the new parking areas along Lake Drive. Shrubs shall reach a mature height of at least two feet. A revised landscape plan shall be submitted to the city for approval. Water Resources Coordinator Conditions 1. Rates of surface water runoff must not be increased from existing conditions. Where practicable to do so, rates should be decreased. 2. The applicant and city shall work together on future phases to look for potential cooperative surface water management opportunities. 3. These approvals for future phases are contingent upon City code and other jurisdictional agency rules remaining the same. In the event that any of these changes, the applicant will need to resubmit to assure that the plans meet any new rules germane to this project. 4. Include a note on the Grading and Erosion Control plan indicating that the proposed best management practices is the minimum controls anticipated, but that as unanticipated site and Planning Commission Lake Drive Business Center Site Plan — Planning Case 2011 -08 August 16, 2011 Page 9 of 10 climatic conditions present themselves, it will be to modify the best management practices to meet these new conditions. 5. All 3:1 slopes shall be covered with erosion control blanket or sod. This needs to be indicated within the plan set on sheet C -2: Grading and Erosion Control. 6. An escrow or letter of credit in the amount of $2,450.00 shall be provided to the City before commencement of the first phase. This escrow is only for the first phase. Subsequent phases will require additional assurance funds. 7. Applicant must apply for and receive approvals from other jurisdictional agencies as necessary. 8. The applicant must show that the total disturbed area for all phases is less than one acre or they must apply for and receive an NPDES Construction Stormwater Permit from the MPCA. If this is the case, a full Surface Water Pollution Prevention Plan must be prepared and submitted to the City for review and comment. 9. All exposed soils must be stabilized within 14 days of cessation of earth work activities. 10. Lake Drive must be swept clean of soils and debris tracked onto it from the site as needed but no less than once per week until final stabilization is achieved. 11. The applicant or their designee must maintain the best management practices in good working order until final stabilization is achieved. Engineering Department Conditions 1. Grass area maximum slope must not exceed 3:1. 2. The applicant must submit revised plans (redlines) which meet the requirements of the City. 3. Drainage plans must be revised so that the plans match the drainage calculations. The applicant must also follow City standards for water quality volume. Also, the proposed drainage rates must be maintained for the 2 -, 10 -, and 100 -year rain events. 4. The storm sewer provided for treatment will be privately owned and maintained. 5. If importing or exporting material for development of the site is necessary, the applicant will be required to supply the City with detailed haul routes. 6. Building permits are required for all retaining walls four feet tall or higher and must be designed by a Structural Engineer registered in the State of Minnesota. A fence must be placed at the top of the wall for safety. Planning Commission Lake Drive Business Center Site Plan — Planning Case 2011 -08 August 16, 2011 Page 10 of 10 7. The exits in front of Wall 2 may be inadequate for some uses of the building under the proposed parking scenario. Exterior exit discharge must accommodate exits served. The parking stalls in this area should be constructed at the time when a final end user is determined so that the exits will not limit the occupancy. 8. The wall and wall supports (not including soil) in drainage area three on the east side of the site must be removed from the drainage and utility easement. 9. Details must be provided for all proposed storm sewer, sanitary sewer, and watermain crossings. Actual elevations of existing utilities shall be verified for accuracy. A minimum vertical separation of 18" is required at all storm, sanitary, and watermain crossings. 10. All of the utility improvements are required to be constructed in accordance with the City's latest edition of Standard Specifications and Detail Plates. The applicant is also required to provide the City with the necessary financial security in the form of a letter of credit or cash escrow to guarantee the installation of the storm sewer, erosion control, and seeding. This amount will be determined prior to start of construction due to the possible phasing of the project and not knowing the amount to be installed and disturbed. 11. The applicant must also notify the City after installation of the erosion control and 48 hours prior to the commencement of grading. Permits from the appropriate regulatory agencies will be required. 12. The plans and drainage calculations must be signed by a professional engineer registered in the State of Minnesota. ATTACHMENTS 1. Findings of Fact and Recommendation 2. Reduced Copy Cover Sheet. 3. Reduced Copy Alta Survey Sheet 1. 4. Reduced Copy Alta Survey Sheet 2. 5. Reduced Copy Site Plan. 6. Reduced Copy Grading and Erosion Control Plan. 7. Reduced Copy Stormwater Management Plan. 8. Reduced Copy Details. 9. Reduced Copy Landscaping Plan. 10. Reduced Copy Photometric Plan 11. Public Hearing Notice and Mailing List. gAplan\2011 planning cases \11 -08 lake drive business center parking site plan\staff report lake drive business center pkg exp.doc CITY OF CHANHASSEN CARVER AND HENNEPIN COUNTIES, MINNESOTA FINDINGS OF FACT AND RECOMMENDATION IN RE: Application of CSM Corporation for Site Plan Review for a 155 -stall parking lot expansion in the Industrial Office Park District (IOP). On August 16, 2011, the Chanhassen Planning Commission met at its regularly scheduled meeting to consider the application of CSM Corporation for Site Plan Review for a 155 -stall parking lot expansion for property located at 950 Lake Drive. The Planning Commission conducted a public hearing on the site plan which was preceded by published and mailed notice. The Planning Commission heard testimony from all interested persons wishing to speak and now makes the following: FINDINGS OF FACT 1. The property is currently zoned Industrial Office Park District (IOP). 2. The property is guided by the Land Use Plan for Office Industrial use. 3. The legal description of the property is: Lot 1, Block 1, Empak Addition. 4. Site Plan Findings: a. The proposed development is consistent with the elements and objectives of the City's development guides, including the comprehensive plan, official road mapping, and other plans that may be adopted; Finding: The development of the site is consistent with the City's development guides and comprehensive plan. The proposed parking expansion provides greater marketability. and flexibility in the use of the site for office and industrial users. b. The proposed development is consistent with the site plan review requirements; Finding: The site is consistent with the site plan review requirements and complies with all zoning code requirements. c. The proposed development preserves the site in its natural state to the extent practicable by minimizing tree and soil removal and designing grade changes to be in keeping with the general appearance of the neighboring developed or developing or developing areas; Finding: The propose parking areas are in locations that have previously been altered with the development of the site. The proposed development is in keeping with the general appearance of the neighboring developed areas. The proposed development will incorporate surface water treatment of runoff and additional site landscaping. Retaining walls are being incorporated to reduce site grading. d. The proposed development creates a harmonious relationship of building and open space with natural site features and with existing and future buildings having a visual relationship to the development; Finding: The development will be harmonious with the existing site building and features. e. The proposed development creates a functional and harmonious design for structures and site features, with special attention to the following: 1) An internal sense of order for the buildings and use on the site and provision of a desirable environment for occupants, visitors and general community; Finding: The proposed expansion is in logical and practical locations on the site. 2) The amount and location of open space and landscaping; Finding: The proposed parking lot expansion is located around the site. The proposed site coverage is less than permitted by code. Additional landscaping is being provided around the parking areas. 3) Materials, textures, colors and details of construction as an expression of the design concept and the compatibility of the same with adjacent and neighboring structures and uses; and Finding: The proposed parking lot expansion will provide additional flexibility with the use of the existing building and is compatible with adjacent development. 4) Vehicular and pedestrian circulation, including walkways, interior drives and parking in terms of location and number of access points to the public streets, width of interior drives and access points, general interior circulation, separation of pedestrian and vehicular traffic and arrangement and amount of parking. Finding: Access to the site shall remain as exists. Parking areas and circulation comply with code requirements and are being distributed around three sides of the building. 5) Protects, adjacent and neighboring properties through reasonable provision for surface water drainage, sound and sight buffers, preservation of views, light and air and those aspects of design not adequately covered by other regulations which may have substantial effects on neighboring land uses. Finding: Surface water is being directed to an improved storm water system. The parking areas are being served by adequate drainage improvements. Landscaping is provided around the parking lot to buffer from public view. 2 5. The planning report, Planning Case #2011 -08 dated August 16, 2011, prepared by Robert Generous, et al, is incorporated herein. RECOMMENDATION The Planning Commission recommends that the City Council approve Planning Case #2011 -08 for Site Plan approval for a 155 -space parking lot expansion, plans prepared by Alliant Engineering, Inc., dated July 19, 2011, on property located at 950 Lake Drive subject to the recommended conditions of approval. ADOPTED by the Chanhassen Planning Commission this 16 day of August, 2011. CHANHASSEN PLANNING COMMISSION C Its Chairman 3 0 W Z Z Q U Fz� 133M u3AOO a �_ c ( � a� ➢x8 NW 'N355VNNVNJ '� °�� 3 / \ 1• 3Alaa 3MVl MS €j`a 3 °€ F9llB0 3ARlO �IKI € A A 3 N v W a A t h 0 w t� a w -- 0 N C7 ZW m 9 <w J UU ~ z n ¢ J N O � Q t z U Q U � C 2 U Ir Q zoz c1w� zl o l w z� zM m ¢ OMZhI� ZwW ZV11/ W W W O WWt9w I I �?> 1 1 0. > IT IL Q W K— ZI_NWN ¢ Y OQ N�EO Q (..Q NI�oO ~xNGMM V 1 Z .IY OO�n U �1Z.1Y00�1� Vl 1 1 W �J �OJQ 4 'NN W N y = 3 �zme (S ¢a Fi em z Ya io p °c�i ° mv ° aL` W c u'znx. Q Q3" o?xx J xaNVl�n1.. 0i ou i6 00. F Y 9 -a 9 — � kl � 1 1 N M V 1[1 10 i� CO W z Y n z Q J m o a O Z Z N Q U m w w p O < Z W Z p Q w M f a W W U w OL R U W � 2 �( W w S r a z a V) ti a Q W U f f y O W Q O r Q Z Q U mQ � M 0 N O : I R O i N M V i l U U U U V J d U \ o \. \ \� \ o \ "11 Y '7' -x cr,� 6 3:� o o W a -- — 1102 '61 W wp anoa090011 S— w 090011 1102 :X -=U DIO a�e..v son .w. � a .wo 4 en. 'uasso RA 13 sai 0 Ni�pol8 ® O3N1 lime— sv /SNovel3s �NOI11O0y NydW3 /S1N3W3Sy3/Aay0Nnoe w 000£ ai�r5 yinog a 36uiysoM OOS dw - }inb3 WSo xanans vry s as o ak grsb66 s —� d S d s 8 = 'P a • get d- gg �' talj i # S i a i T F1 7 f i` is. °`' sp § *ixi `u# � � s i «= a g R ! o a g 1 If. I d �I aES�dF 3� l l ,gi j A s Y 88 Y -t` 3t t l .1 .. aa { 4q s [ t If IC 1; Il r ib 9� Yp P [ s •�a iss : . M ill 1.5 � eI # d 6\ V G Itt ja I t z � a a� �� s 3d 3 4 � £I {{�s `f i i P I M $ # #$� $# t s34 ff = ¢ �£ C h a $ IBi iF s ds da i it i idn i ,3 gig i3 i gill : s 5 a §: € e 4 9 E1 :lla E"£`F a� R j �ss W Imo# ; s 53 MR Y § e q Fi€; \ \\ \ iR re'a'nacdoe'evc.cn lF }s as s�5 � �,� � �� ���• • saY J '•� �{ $ •� q A b e '\ m 1 ` 1 5 \ 38 R 8 �$¢ @tld� i$$i3 fig 3 ��s1 #il #b�8�8888 \ \ p Y W 5 \^ \•� �� 3 3 . t I si s 5 e' 1 l B o m•v •w>r .a.. •+x mo a m,. 1p olosauu!W 's!I NW + 'uass0yuoy0 x m +mow 1 , Pole '1 1 nw sKw NOLLVW2JO.iN1 ta a a sss u oau oowW NOLLIOOV AV&W ttu-so °way OIHdv2100dO1 a[�.xxa 000£ 1! ^S 41^^S enuany 16,{ysoM OOS Oil sai}inb3 Wso Aamns vnv z z 2 ��fp4odaoapnEmn ��. a }9 oI � R Q om IN �� ig }�E3II���d ��38B8B88�5�8 ? I �g ahe • , "1ff o QY J 7g k's a 1 \ fit° 1`` \• t'it }; J J . =11 {° 1 t 1 11n In . q; 1 All 11 1111 s t rr 1 1 t1 E.1 • \ vJ 11 \i1 I � . �'\ 11� 1 11 1 'x1 )11 s ql 141, A\\\ 11 11 , ±'11 V % % 1 ;11 1 1111 `1 �` W \`\ s 1 1,1 , y t , 'l i Ijll s t r„ \ y c o If 1 7111, -Ir ? r,1\ � I U 111 rj V Ill111511 1 46 ��:' \ \1 $ f 1 1 j 111 i i jjr1 °s \ ` \ .`�•��, 4 1 5 x '`•(, \ \t °.,11, '\ ®E�SE3 114HO � a N1� \. � \ 1 t r \, •— �. \h1 11U;111. 11� \ \,, j`, C 11Q11 \�11,1j; F • �r+ I o =11 , II + t1\�Ibl \� 4 11 ��• O - ,,:;1 : 11 t � p l\I 111 , €$ \`;) < is 1 III 11 L 1 I �.� \„\,,,1 \ \j1gra , 4•q l:$ � �I11 ilk � � h''; I t \1 t, ,;F': � � ���a l•i I IIh Il ii�iil - 0 1 \`�I B t , _ �. _ a `.. •� % �;;n iii "�`9 � � f Q � a O R EFz NV1d 3LIS €_ : g a s p 1< l TAT a� 1 1 1 1 mncvx....r.ew Fgso �ma3a8 NX 'N3SSYNMHO 3AO10 3X" OS6 8$ a tl31N33 SS3NISt19 3AItlO 8 ~ s e 4 E�s3 g z � gulf 7 � ¢ g gg g Y Y G r N+S'N \ I li e1 e. m ( \\; AA - kv S . - s 11 �,� ,s• \ ` \ \1 \ \ ffi:� W W E sgx a4 r ; 1 �M Iii 1 .. e \ ~ 1 y0 iz M.€F.C�£O „r.F.. Zoo -FZi _________ __ _ __ -($ s 1 �• Or/b etc -O)v ;; S21 �iylOd 6 im "6[ pq' Bwai1s090 msia s —d\0 oiimioa- om—a E"a NVId IOHM03 NOISOH3 (INV `JNIOVH9 a € ` @ - m NM 'H3ssvHNyH3 3AM0 3)M 6S6 ES . -� e Q U N ` H31N3O SS3NISf19 3AIHO 3)IV I SSS y € - I a to a _ Q 3 g � s s a I It gl —n - 1102 1 61 mf UPWP 0090011 \siaa S — ld\090U11 \It02 \ -% 1— 6ulwou6 E ° a Nnd 1N3W30VNVW 831VMWdO1S ills N AINO 3Mn 096 jjks g f V al31N33 SSMisn8 3AIHO 3Ntl1 8 3 gal .e O ®90AOA l ei el cS9 0- w W - n02 '6I w O.P'tll^09001hsyaays - 4 10900II\iM- -auw W1--1 z E S- 11V13O e > a mew aeoan� a NI 3 VNNtlH� mwv°s.d.w WSJ g� 3ARNSO 10 371Y7 OS6 ^f'ce H31N33 SS3NISng3AIH03)Itl7 a W _ d gg� z w g" t � U _ w� 7 � a A x F z e, w s i U p 3 "R c F En III -I m 02� oy o- F r a r, z a ay O V "T m wLSB - 1102 1 61 rr 6.p14aM9W11 \sways 8ul 0 W d gg� w g" qg Y o 2 U � a U 02� oy o- F r a r, z a ay O V "T m wLSB - 1102 1 61 rr 6.p14aM9W11 \sways 8ul 0 IIIIIIIIIt� $se: NVId UVOSONtl7 .€ a € A A s f 51 , NN 'N355MNNtlH� ��€ 6F m 3NaO 3In �' G A H31N33 SS3NISf19 3MHO 3X" `°' g W�? € Wad x A as ag a ° o °° ymll g xggEg gg E °, § a P @s U a ,Rai 8 E 55 yggy 4 $ 4 = �I i 1. i2 $ ing °€ gk b aU REdE 7 a. a 4 a� � 6 i i 1 + IP\ \ +1, I 11u d... l ik �. \ , + \Yi, 1 i ji't 1 , w 7,P \+ll�n 1 PI ag11. 1 Id I III tF� fly nt Y� 1� 11 i u iil 1 i VI'l it r1 1 _' 4.1 At 1�I 1 1 `.I I. l •— } ;•1i id(tl+1, O Oil, 1 , 1 x 2 '}1111; n1'1 It t1 \ \ e 8 � a o ? r a db J w a� o� N1 \ \ Q 1 I \ AN \ e a� wR i!I a �6 I l �owi l� ^^BV6 - IIaZ '61 NY E.I °olosmm�aa� �ow\osoonvlozvx �+o,. d,l�e..a � elan � xxa 3 A ° W ^ k k b _ _ N # !a tai {{ 1�g a l l a s 8 � a o ? r a db J w a� o� N1 \ \ Q 1 I \ AN \ e a� wR i!I a �6 I l �owi l� ^^BV6 - IIaZ '61 NY E.I °olosmm�aa� �ow\osoonvlozvx �+o,. d,l�e..a E14 §. NV'ld DIUMMONd M i NM 'H3SSVMNYHO MIN 3)lVl 096 a E13IN33 SS3N mua min NE isn 11 Wye I C) 0 -i 02 25 x F- 0 0- j2 0 1 8 "o j -ok A vnv 4 1 At Oc/ —006 - 1102 '61 5--la CITY OF CHANHASSEN AFFIDAVIT OF MAILING NOTICE STATE OF MINNESOTA) ) ss. COUNTY OF CARVER ) I, Karen J. Engelhardt, being first duly sworn, on oath deposes that she is and was on August 4, 2011, the duly qualified and acting Deputy Clerk of the City of Chanhassen, Minnesota; that on said date she caused to be mailed a copy of the attached notice of Public Hearing for Lake Drive Business Center — Planning Case No. 2011 -08 to the persons named on attached Exhibit "A ", by enclosing a copy of said notice in an envelope addressed to such owner, and depositing the envelopes addressed to all such owners in the United States mail with postage fully prepaid thereon; that the names and addresses of such owners were those appearing as such by the records of the County Treasurer, Carver County, Minnesota, and by other appropriate records. Kare J. Enge t, Dep to Clerk Subscribed and sworn to before me this � day of , , 2011. .IV I A u otary ublic KIM T. MEUWISSEN Notary Public- Minnesota My Cornmission Expires Jan 31 , 2015 4) C . O V ._ G Rf a d N ca s C .0 V C 'i d V .Q a O d O Z w � W C O • N E O V C FL U N cc s ea s U C d V a O d 0 Z r @ "6 N O O U c r_•. L ` r--• .Q �!' c m `o ° �m m o L . c >� @ 'c L N a L in c .r O O O N O �_ O C tC to > 3 U N N o o ro n m .: T'= n a> m o 16 CC am �QD m� m O O U p •� �� O �� O � 2 wo aciNo amp m om =o nom '0> E +�� O� �L- U U N om- O O O C t O TW E. (O O d� `�� Q c°00 EmwmTY ma>m 7U mm Enomrc_ cc$ �� a) 0= mwo 0) Co cc � C i N O+ O C L QN C O O U 3 0 CO a)�� c°�ronYmom�E. �o �c0 �'maEnEyNcm M 0 e ca >' _O a) D N s C (n CC Ld C Q ' 3 • fN @ D m m m •o O 7 m o E r j 'U L .+ C @ C «. C a) a C a) L cc .0 0 C C fn C a) a) .- a > L T � N a) m Q G> U U E N O N— E U 3 .� () E � _ O ao C Cl) O p y 0t. = U U m 3 E L '@ N �• a) N> U a EB 0) g.3a 3 N- mo0 wo o ~ O Y N O C '� O} Q O `• O U L �O > y > «> nm @ E o m c O m N U c O >_ ) _ 0 C p _ N C QO 0) � O _ (B Q N y = Smm Eu @ o c �N mm Q O ci c (aO G 11) L t r+ � O (n ._ L� - ;�.. N (n N +� C QU N U Qas+ O c � cCD')) = �� �oN m O U O c O "' N O ... 'V . CD C) ''C O �� N C � (C6 C " E O U C. -_ Q N O �(Da) da �Emv� m� o70 O w c O L d. �_ O °- O U O w +• O N O .N.. w «. G E Z a a w a> m L a) @ m " ° a)cc 7 m aN .� I� O C �- O` v> (0 O C (a, + (0 N Co N O O 3 N �'.� E mm NT'- oa)o 0On (6 a m @ >Q �a> n 'u c N c : (A L >> O N N N= a) C C O O O '.'' U p> cu O N N C2 N N Q 0) U) C v, '� oE mc)��<n 0E- °o c) r a c o= N L . d n U m m 'E r-. @> O".r L C C a) � i > N = O c= a) L '� O C -C d M :3 cn O y 0 ..L. .L... -p -T' O O 3Q O Q. N .Q E O C d' N O N 'p'C > aL 7 U U C1 Q � �— 3 c� . T a °aL T U d .0 w @ate 0 O. Nr 0) CL > 0 c n m - 'Eo a) a (B U C a> O a. p) = O NQ C !n � C ��' N N �L +P-W V O �� T. �r mon c_rnm me cc °� 0c. �U ° ° "'co o "rj � cU +.• C) U d Q(D L c � U LO � � � � O c fl N d - � U N Q'� ) O O d'p c w (6 L C N ° ma :3 ca N cm ac ="� -a oac ci�mo> = c U c- 7> U O C N L C O O +-• O U L C (B C � 7 - > (D C N +' L E s N U U N N Q. cc U m@ -- c o c o dY m e o a = yU m m no o: N� 7 3 0 -a)' - a n � a) :3 D- U) U C N H >• U . O O �� V C m N to O O� C O > = da m30� -E a- 6' w E m �m E mo Yom U Q 0) O U >_ C) O U p` Co QE N Q . 0 = 0 per . U �? O O c0 E C (1) ,«- C r 4) Qf0 0) c w E c '— - - U maw -@ L m a> c 3L-7NCLUco aM- c >+•-- V , r- C >` O. fn ' O O c Y U • U >_ Q C � N`� �� d L U , C (0 U O 7'' C N_c O� Nm n a> Q m (D o a m o rn c m L n EEc 3^ ooa�i� 2_ (D N (6 fn0 U O cU} p cu+. �� O N °•`—' 'fn� > . U �._+ O N U O a cmav�NC�a �UL o m m U �°= a) > 1 7 (CO N o J v �.`- O �(� ° N C i O C E> � > m��' w� ° �'m° � a)a: - U o� N cr_ U@ N = QY O X m ,,^^ O O LO QO C QM 7 Y O _O OL O D O c L AEU °NO?ma O f 7U U w a) V J U 0) < m ca o- c) t ,� � co - co QU (6 O Q - '�wcUc cZ ° om� n3m omo CV M� c �c QomEFmmo �tn3°N m o)Ua E 7 O a) 4 N L C 0 > O Y o) a) m m O) CL m O C L4r y mo �2a>P0o'i�coian)Uao� yoc ccc - 0 E .. �„j d V) N r ioa00E3 u ° 0(D a r (D d u U E p � c 0 o O N c � M (D H O R N = O !4 C � = C _ O 0) c o C N U C m ° m C. _N r n N 0 3 C d N LP 0 a) L> p C m N a 0 .L.. 3 m 06 V CL Q R s L a)� 7 a N G U n y N= E E U c O � rn a) N m U N E d O O O O .0 •N r..) O O T « 7 m n m r L L N°- C m a) .2 C N o a) C O Uof amCnf UU23nNQmncmccN o -i a Q n. - m Cd L) . If ;a N O C O — G) C C J' o m o w c 3 cL a N 0 �' O U O C _� V m o ° m n @ 7- C& (D @ O o ++ L 7 O N > N O O l0 N 9 ( 6 .-. m d U Q C c L C 2 : L- -Z aa a3 a a)No > m +� a O� L— U N 7Q U O p C� Qm mom Lo naia`m �� N p aoo E -mm rn a> 7U �@ O O -0 (6 �. a N c a) C L Q��� m o m O a 0 0 m t n m m m m w O c �Y 0 O CJ Q - U �� =t la . O �cO �mnEnEu Ncm O d_ @@ Y � La >' Q O _� !n W+ O Q 3 N m a) co m m a O 7 a) O E L 7 'U r coo L m U) a> > Q N d - C �� O U N Q !n C C fn - O p£> C .�. a)a)'N a>L' —a.3Nm .Um O U E L E � N +-' O D N> °- U t ~ m - y U_ � 2 _O E N U V M to O p d Oa+ (] c a E �� o3a°a =3 N�m o C i; 0_ cc cu O `1 V- fn 0 C C O Q O c Q E C O C U 0 T m 4) a) n N -- m Y L a m E o m ° m N U m � L I N.� O''••' O .�.. O (�� > r („) Q N �N_N0O -�� cm E• - m "'O Y cpmC a) O mc a) N 0 E C U N L C o �w o - nN E w ca`> � '- a ''C : � - - UQ CQ � O O N .� C QU O U Qa+ C moo Ec p� °`a, OLO .� p ON p).= O C (n r- O - .' N O N= L N O ' ' - LO p C 0 ma 3a)t Din crm c a )m._ m . one O. 1� c o O f� L p O C N a C C (B .0 E p (II (B O O QO C \ tn L N U O 3 d N N �'-' a+. (0 O O =3 N a) c _EmaY 0 42 c o r E a a N m L a y a c m ca (C �> = UL'�a va)o coon a)co >° wm + c to N N r _ L O S O O w CO `� C >- _ O> O N N Q N >+ (B O. ai a o f r) E a 'w m � � E p o) 0 0 E c Y i ° o U L c c `� w 'c ° o. �a >_ N O O CO i ..0 p U N� O O m U C 0) n U CALU) d� E N L Q U m m m T m m e C N E m > n• mo o c o s O �� N N / N ; O O C L 3 V Q� 0) L) a Q> o > n m co o a c c 7 ir N N U U (D =3 > QO Q C p= U (BQ _�M N N (6 r ++ r �"� >a) , Z6 � U c.o m c o Eo corn m ° n m C m m 7 E m C C U ( 7 C (D C ... QUO O r C) ca O ) L .. to r- � C O O c6 3 N ?� C O _� QN U d = . O d O C °w.�onC5Nm OWN 0 v La) c @ a)c Ew._ 0m 9� m�°�ym�wo7o° m a)N U c- Q d N O C C c O U _C . >_ O +-• N U N 'J O U tq 0 (Of� p U N N� E•r- C cn N U L m o) c � 0 � a@m'> ca= NUca °� 0 > C _� Q U � N y O CS � > (CB N ' , N N C N U (1) ') — —c ( 0 m m m m n a) co o ° c m Um'vT Q 7fnCm�.�O O L O O NN���'UCNUOOLCO>,Nr_,L�ta (J) Q..L — Q(D (� id d aEi0U°Nmo7 E . @� : + N .. C QQ ^' C O N w V Q L Q E .� p _fin � (� Q. O ,_ a--• Q c� p r- , C (n y O _ U N 4a 3 L 7 u N U- C N Q@ �-: a) C c a a) C m 0 (Q O .> UQ U N C C2 N N .�? 7 03 +-' N (� U p+ C U O N U'� E U m L 0 N c .� 7 o N �^ r nr - :: O 7 C m«, J as Q,U U L O 7 N _ 'V a) dr O N C E L oQcNHv .Nc a a) L > . anicc of a> c._ 7 E 7 c n co o U@ N = CSC N QY ,,^^ v O O O Qp -0 cnF -Ua . pU �C C O > �' O >> •L p a')aoZ> "EUc'o0cL i U cam` NrnL 7 U d) X cu W N J V J U LO� 0') Q Q-0 � I— M Co Q-, a)� O_0 p = 4= �"' � U Q U N U o a) T C ..L., a) C U .T. m m W (D, C L N. n E "� C 'c - E ~ E 3 CV M� ' n U c c -° a) m U= In m - o n aai c Q o m E m m N d U 3:,2 N m; U m r@E O,)Ym a L... Em'5 m � d _ = d m n _N N N O O N fn - O 7 r O C c C .0 E .. �„j C L Q N i ca0E3 @mm0000�'X w c ' 0 . Q a N U C N C °- m N N L@ m O O ~ O ff) OS O =� O d C: 6 ° C Cn L a) ;O c> U o nn o my� ~OL3�00073 mdc d N � 2 06 Q m L 0 N L C U' 0 d 4. Q. O Q. OL t+r N `) L O E _T C> tl .7.. a) m a) 16 N C c m : m O O O in�aM �'UU� 3n"u l O J G. Q a J R C1 U U • CARVER COUNTY JOHN FERRIER ISTAR MINNESOTA LLC CSM PROPERTIES INC 600 4TH ST E PO BOX 4900 CHASKA MN 55318 -2102 500 WASHINGTON AVE S #3000 SCOTTSDALE AZ 85261 -4900 MINNEAPOLIS MN 55415 -1151 PAULS FAMILY TRUST ROBERTS AUTOMATIC PRODUCTS ROSEMOUNT INC 7676 HIGHWAY 145 INC 12001 TECHNOLOGY DR TELLURIDE CO 81435 -4100 880 LAKE DR EDEN PRAIRIE MN 55344 -3695 CHANHASSEN MN 55317 -9325