Loading...
Engineer's EstimateENGINEER'S ESTIMATE WYNSONG Chanhassen, Minnesota GALPIN BLVD PARTNERS, LLC Otto Project No. 2 -12 -0191 December 19, 2012 CITY OF CHANHASSEN RECEIVED DEC 2 1 ZU17 CHANHASSEN PLANNING DEP? SCHEDULE A - SANITARY SEWER CONTRACT ITEM UNITS EST QUANT UNIT PRICE TOTAL 8" PVC Pipe Sewer SDR 35 with Granular Bedding LF 272 $ 26.00 $ 7,072.00 Standard Sanitary Sewer MH 0' -12' , 48" Dia. EACH 2 $ 3,500.00 $ 7,000.00 Connect to Existing MH Core Drill EACH 1 $ 1,200.00 $ 1.200.00 8" x 6" PVC WYE EACH 4 $ 200.00 $ 800.00 6" PVC Pipe Sewer SDR 26 Service Pipe with Granular Bedding LF 110 $ 18.00 $ 1.980.00 6" Cleanout EACH 1 $ 300.00 $ 300.00 Televising Inspection LF 1 272 $ 2.00 $ 544.00 Connect New Services to Existing Home Services LS 1 $ 600.00 $ 600.00 Remove Existing 6" Pipe and Cleanouts (Plug End LF 1 $ 500.00 $ 500.00 TOTAL $ 19,996.00 SCHEDULE B - WATERMAIN CONTRACT ITEM UNITS EST QUANT UNIT PRICE TOTAL 6" C -900 DR -18 Watermain with Tracer Wire and Granular Bedding LF 550 $ 25.00 $ 13.750.00 Fire Hydrant w /6" Gate Valve and Box EACH 1 $ 4,000.00 $ 4,000.00 1" Corporation Stop EACH 4 $ 135.00 $ 540.00 1" Curb Stop and Box (Including Extensions EACH 4 $ 210.00 $ 840.00 1" Type K Copper Pie LF 105 $ 23.00 $ 2,415.00 Shut Off Existing 2" Water Service at Corp. EACH 1 $ 500.00 $ 500.00 18" x 6" Wet Tap (Incl. 6" GV) LS 1 $ 5,000.00 $ 5,000.00 TOTAL $ 27,045.00 ENGINEER'S ESTIMATE WYNSONG Chanhassen, Minnesota GALPIN BLVD PARTNERS, LLC Otto Project No. 2 -12 -0191 December 19, 2012 SCHEDULE C - STORM SEWER CONTRACT ITEM UNITS EST QUANT UNIT PRICE TOTAL 12" CMP Culvert 30 LF (Inc]. FES) LS 1 $ 650.00 $ 650.00 12" RCP Culvert 77 LF (Incl. FES ) LS 1 $ 2,500.00 $ 2,500.00 12" RCP Culvert 52 LF (Incl. FES) LS 1 $ 2,000.00 $ 2,000.00 Remove Existing CMP Culverts EACH 2 $ 300.00 $ 600.00 4" Perforated PE Draintile with Geotextile Fabric & Filter Aggregate LF 216 $ 8.00 $ 1,728.00 TOTAL $ 7,478.00 SCHEDULE D - GRADING AND STREET CONSTRUCTION CONTRACT ITEM UNITS EST QUANT UNIT PRICE TOTAL Clearing and Grubbing LS 1 $ 2,500.00 $ 2,500.00 Grading LS 1 $ 10,000.00 $ 10,000.00 Sub grade Preparation (I' Depth) RS 6.4 $ 300.00 $ 1,920.00 Agg. Base Cl. 5, In Place 10" Inc. P Beyond Edge of Bituminous, 100% Crushed SY 1560 $ 9.00 $ 14,040.00 1 1/2" MnDOT LVWE35030B SY 1421 $ 8.00 $ 11,368.00 2" MnDOT LVNW35030B SY 1421 $ 12.00 $ 17,052.00 Geotextile Fabric (If Needed) SY 800 $ 1.00 $ 800.00 Tack Coat GAL 85 $ 5.00 $ 425.00 Utility Conduit Crossing EACH 1 $ 300.00 $ 300.00 Remove and Dispose of Existing Bituminous SY 775 $ 3.50 $ 2,712.50 Bituminous Trail/Driveway SY 30 $ 35.00 $ 1,050.00 F &I No Parking Fire Lane Signs EACH 5 $ 150.00 $ 750.00 F &I Stop Sin EACH 1 $ 300.00 $ 300.00 F &I Street Sin EACH 1 $ 300.00 $ 300.00 F &1 Development Sin EACH 1 $ 500.00 $ 500.00 TOTAL $ 64,017.50 ENGINEER'S ESTIMATE WYNSONG Chanhassen, Minnesota GALPIN BLVD PARTNERS, LLC Otto Project No. 2 -12 -0191 December 19, 2012 SCHEDULE E - EROSION AND SEDIMENT CONTROL CONTRACT ITEM UNITS EST QUANT UNIT PRICE TOTAL Rock Construction Entrance (Install and Maintain ) EACH 1 $ 1,200.00 $ 1,200.00 Restoration Seed, Fertilizer & Mulch, MnDOT 270 GR ACRE 0.5 $ 2,750.00 $ 1,375.00 Wetland Buffer Restoration MnDOT 310 SF 1700 $ 0.40 $ 680.00 Silt Fence (Including Maintenance LF 560 $ 2.00 $ 1,120.00 Tree Protection Fence with Metal T -Posts LF 665 $ 1.50 $ 997.50 Erosion Control Blanket SY 1000 $ 1.00 $ 1,000.00 Retaining Wall Modular Block SF 73 $ 16.00 $ 1,168.00 CL. III RipRap with Filter CY 16 $ 75.00 $ 1,200.00 Flared End Sediment Trap Install and Maintain EACH 2 $ 200.00 $ 400.00 TOTAL $ 9,140.50 CONTRACT ITEMS SCHEDULE A - SANITARY SEWER $ 19,996.00 SCHEDULE B - WATERMAIN $ 27,045.00 SCHEDULE C - STORM SEWER $ 7,478.00 SCHEDULE D - GRADING AND STREET CONSTRUCTION $ 64,017.50 SCHEDULE E - EROSION & SEDIMENT CONTROL $ 9,140.50 SUBTOTAL $ 127,677.00 ENGINEERING, SURVEYING, AND INSPECTION (15 %) $ 19,151.55 TOTAL $ 146,828.55