Referral ResponsesGenerous, Bob
From: Julie Klima Oklima @edenprairie.org]
Sent: Friday, October 25, 2013 10:43 AM
To: Generous, Bob
Subject: Lakeside PUD Variance Request
Bob,
The City of Eden Prairie does not have any comment on the proposed variance for JAH Homes.
Thank you for the opportunity to review the request.
j4lf�- k6a
Senior Planner
City of Eden Prairie
ER 8080 Mitchell Road I Eden Prairie, MN 55344 -4485
W 952.949.8489 1 ® jklima @edenprairie.org 1't edenprairie.org
`] Please consider the environment before printing
Generous, Bob
From:
Sinclair, Jill
Sent:
Tuesday, October 22, 2013 2:36 PM
To:
Generous, Bob
Subject:
Lakeside 2nd
Hi Bob,
I have only one comment for the setback variance on Lots 1 -3, lakeside 2nd: Each home will be required to install
foundation plantings and one tree in each yard consistent with the overall landscape plan.
Jill Sinclair
Environmental Resources Specialist
City of Chanhassen
952- 227 -1133
Date: October 8, 2013
City of Chanhassen
7700 Market Boulevard
P.O. Box 147 P v`
Chanhassen, MN 55317
(952) 227 -1100
I`
Review Response Deadline: October 24, 2013 \P
To: Development Plan Referral Agencies
From: Planning Department
By: Robert Generous, Senior Planner
952- 227 -1131 beenerousna,ci.chanhassen.mn.us
Subject: Request for a variance from the Lakeside Planned Unit Development perimeter setback standards to
construct a three -unit townhome on property zoned Planned Unit Development - Residential (PUD -R)
and located on Lots 1, 2 and 3, Block 1, Lakeside Second Addition. Applicant: John Arthur Homes.
Owner: Land Hold Co., Inc.
Planning Case: 2013 -21 PID: 25- 4250010,25- 4250020 & 25- 4250030
The above described application for approval of a land development proposal was filed with the Chanhassen Planning
Department on October 4, 2013. The 60 -day review period ends December 3, 2013.
In order for us to provide a complete analysis of issues for Planning Commission and City Council review, we would
appreciate your comments and recommendations concerning the impact of this proposal on traffic circulation, existing and
proposed future utility services, storm water drainage, and the need for acquiring public lands or easements for park sites,
street extensions or improvements, and utilities. Where specific needs or problems exist, we would like to have a written
report to this effect from the agency concerned so that we can make a recommendation to the Planning Commission and City
Council.
This application is scheduled for consideration by the Chanhassen Planning Commission on November 5, 2013 at 7:00 p.m.
in the Council Chambers at Chanhassen City Hall. We would appreciate receiving your comments by no later than October
24, 2013. You may also appear at the Planning Commission meeting if you so desire. Your cooperation and assistance is
greatly appreciated.
1. City Departments:
a.
City Engineer
b.
City Attorney
c.
City Park Director
d.
Fire Marshal
e.
Building Official
f.
Water Resources Coordinator
g.
Forester
2. Carver Soil & Water Conservation District
3. MN Dept. of Transportation
4. MN Dept. of Natural Resources
5. U.S. Army Corps of Engineers
6. U.S. Fish & Wildlife
7. Carver County
a. Engineer
b. Environmental Services
8. Watershed District Engineer
a. Riley-Purgatory-Bluff Creek
b. Lower Minnesota River
c. Minnehaha Creek
9. Telephone Company (Qwest or Sprint/United)
10. Electric Company (Xcel Energy or MN Valley)
11. Mediacom
12. CenterPoint Energy Minnegasco
13. City of Eden Prairie — Janet Jeremiah
Generous, Bob
From:
Bartels, Stephanie
Sent:
Friday, October 11, 2013 11:51 AM
To:
Generous, Bob
Subject:
#2013 -21 Lakeside PUD Variance
Attachments:
Permit Survey- Blk 13 and Blk 1.pdf
:..
After reviewing the request for variance, the engineering department has no comments.
I had a few questions about the grading shown in the plan sheet submitted in the request, but I spoke with Art, the
builder, and he sent me a plan sheet with the revised grading. I have no comments on the updated grading. See
attached.
Thank you,
Stephanie
Stephanie Bartels, EIT
Project Engineer
City of Chanhassen
sbartels@ci.chanhassen.mn.us
P: 952.227.1165 / F: 952.227.1170
7700 Market Blvd P.O. Box 147 Chanhassen, MN 55317
MEMORANDUM
TO: Robert generous, Senior Planner
FROM: Jerritt Mohn, Building Official
DATE: October 10, 2013
SUBJ: Request for a variance from the Lakeside Planned Unit Development
perimeter setback standards to construct a three -unit townhome on
property zoned Planned Unit Development - Residential (PUD -R) and
located on Lots 1, 2 and 3, Block 1, Lakeside Second Addition.
Planning Case: 2013 -21
There are no building official comments.
G:\PLAN\2013 Planning Cases\2013 -21 Highlands at Lakeside Variance \buildingofficcialcomments.doc