March 18, 1998
Kerber Pond Park:
Stone Creek Park:
Trail Improvements
Park Trail with Bridge
Sunset Ridge Park: Half-Court Basketball
Paul Page of Hoisington Koegler Group will present sketch plans for the Kerber
Pond Park trail connection, Stone Creek Park bridge, and Sunset Ridge Park half-
court basketball on Tuesday night. The bridge project will prove to be
challenging. Access to the site by heavy equipment, a concrete truck, crane, semi-
trailer will be required to install a pre-fabricated bridge. If this cannot be
accomplished, then the bridge would need to be constructed on-site.
Action Required by the Commission:
Confirmation of the sketch plans.