Specifications July 2014Project No. 0004181 Specification Book SPECIFICATIONS FOR: Erosion Control, Sanitary Sewer, Water Main, Storm Sewer & Street Construction The Preserve at Bluff Creek 6th Addition Single Family Residential Chanhassen, MN July 2014 Prepared for: Chanhassen Residential Development Partners, LLC One Corporate Center III, Suite 300 7300 Metro Blvd. Edina, MN 55439-2302 Contact: Todd Baumgartner Prepared by: Westwood Professional Services, Inc. 7699 Anagram Drive Eden Prairie, MN 55344 (952) 937-5150 Contact: Fran Hagen, PE Planning Traffic Engineering Landscape Architecture Civil Engineering Land Surveying Environmental Studies Offices: Minneapolis St. Cloud Specification Index Section Signature Page 1.0 Proposal Form 2.0 Agreement 3.0 Instructions to Bidders 4.0 Supplementary Conditions to the Standard General Conditions of the Construction Contract 5.0 General Conditions 6.0 Special Provisions 7.0 Soil Report & Borings 8.0 CEAM Specifications Section 1.0 Proposal Form Section 2.0 Agreement A-1 AGREEMENT BETWEEN OWNER AND CONTRACTOR ON THE BASIS OF A STIPULATED PRICE THIS AGREEMENT is dated as of the day of in the year 2014 by and between Chanhassen Residential Development Partners, LLC (hereinafter called OWNER) and ___________________. (hereinafter called CONTRACTOR). OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows: ARTICLE 1. WORK. 1.01 CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: Sanitary Sewer, Water Main, Storm Sewer & Street Construction for The Preserve at Bluff Creek 6th Addition in Chanhassen, MN. ARTICLE 2. THE PROJECT 2.01 The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows: Sanitary Sewer, Water Main, Storm Sewer & Street Construction for The Preserve at Bluff Creek 6th Addition in Chanhassen, MN. ARTICLE 3. ENGINEER 3.01 The Project has been designed by Westwood Professional Services, Inc., 7699 Anagram Drive, Eden Prairie, MN 55344, who is hereinafter called ENGINEER and who is to act as OWNER's representative, assume all duties and responsibilities, and have the rights and authority assigne d to ENGINEER in the Contract Documents in connection with completion of the Work in accordance with the Contract Documents. ARTICLE 4. CONTRACT TIMES. 4.01 Time of the Essence A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as state in the Contract Documents are of the essence of the Contract. 4.02 Days to Achieve Substantial Completion and Final Payment A. The Work will be substantially completed on or before the date stated in the Bid Proposal and completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions and the Supplementary Conditions on or before the date stated in the Bid Proposal. 4.03 Liquidated Damages A-2 A. CONTRACTOR and OWNER recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph 4.02 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions and the Supplementary Conditions . The parties also recognize the delays, expense and difficulties involved in proving the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay OWNER One Thousand Dollars ($1000.00) for each day that expires after the time specified in paragraph 4.02 for Substantial Completion until the work is substantially complete. After Substantial Completion, if CONTRACTOR shall neglect, refuse or fail to complete the remaining work within the time specified in the Bid Proposal for completion and readiness for final payment or any proper extension thereof granted by OWNER, CONTRACTOR shall pay OWNER One Thousand Dollars ($1000.00) for each day that expires after the time specified in paragraph 4.02 for completion and readiness for final payment. ARTICLE 5. CONTRACT PRICE. 5.01 OWNER shall pay CONTRACTOR for completion of the Work in accordance with the Contract Documents an amount in current funds as detailed in the attached CONTRACTOR's Bid. As provided in paragraph 11.03 of the General Conditions and the Supplementary Conditions , estimated quantities are not guaranteed, and determination of actual quantities and classifications are to be made by ENGINEER as proved in paragraph 9.07 of the General Conditions and the Supplementary Conditions . Unit prices have been computed as provide in paragraph 11.03 of the General Conditions and the Supplementary Conditions . ARTICLE 6. PAYMENT PROCEDURES 6.01 Submittal and Processing of Payments A. CONTRACTOR shall submit Applications for Payment in accordance with Article 14 of the General Conditions and the Supplementary Conditions . Applications for Payment will be processed by ENGINEER as provided in the General Conditions and the Supplementary Conditions . 6.02 Progress Payments; Retainage. A. OWNER shall make progress payments on account of the Contract Price on the basis of CONTRACTOR's Applications for Payment as recommended by ENGINEER upon completion of construction, required testing & acceptance by the City of each of the following 2 Phases of Construction: 1. Sanitary Sewer, Water Main & Storm Sewer Construction 2. Street Construction through the installation of the Bituminous Base Course and the backfilling of the Concrete Curb The estimates will be prepared based on the Contract Unit Pricing Proposal for work completed and accepted by the City, less 5% to be retained until final completion and acceptance of the work and less previous payments. Progress estimates will be prepared by the ENGINEER as A-3 accurately as the available information will permit but the only estimate that is binding is the final estimate. Copies of progress estimates will be furnished to the CONTRACTOR within 5 days of City acceptance of each phase of construction for his review and approval. Progress estimates approved by the CONTRACTOR shall be counter-signed by the ENGINEER and forwarded to the OWNER for payment. The CONTRACTOR will be required to keep accurate records of said construction, but will not be required to apply said quantities for payment until final payment has been requested. Estimates prepared by the ENGINEER that vary considerably from what the CONTRACTOR claims shall be brought to the attention of the ENGINEER in writing prior to the next pay period. Payment will be made within 30 days of receipt of the estimate by the OWNER except as otherwise agreed between the CONTRACTOR and OWNER. The OWNER may withhold payment in whole or in part on an approved estimate to the extent necessary to protect himself from loss on account of any of the following causes discovered subsequent to approval of the estimate by the ENGINEER, as follows: 1. Defective work not remedied. 2. Claims for labor or materials furnished the CONTRACTOR or Subcontractor, or reasonable evidence indicating probable filing of such claims. 3. Failure of CONTRACTOR to make payments properly to Subcontractors or for work or labor. 4. Amounts necessary to insure that an overpayment on the total contract amount will not occur. 5. Evidence of damage to another CONTRACTOR or private property. 6.03 Final Payment A. Upon final completion and acceptance of the Work in accordance with paragraph 14.07 of the General Conditions and the Supplementary Conditions , OWNER shall pay the remainder of the Contract Price as recommended by ENGINEER as provided in said paragraph 14.07. ARTICLE 7. INTEREST 7.01 All money not paid when due as provided in Article 14 of the General Conditions and the Supplementary Conditions , unless otherwise noted, shall bear interest at a rate of 8.0% per annum. ARTICLE 8. CONTRACTOR'S REPRESENTATIONS. 8.01 In order to induce OWNER to enter into this Agreement, CONTRACTOR makes the following representations: A. CONTRACTOR has examined and carefully studied the Contract Documents (including the Addenda listed in Article 9) and the other related data identified in the Bidding Documents including “technical data." A-4 B. CONTRACTOR has visited the Site and become familiar with and is satisfied as to the general, local and Site conditions that may affect cost, progress, performance or furnishing of the Work. C. CONTRACTOR is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may affect cost, progress, performance and furnishing of the Work. D. CONTRACTOR has carefully studied all (1) reports of explorations and tests of subsurface conditions at or contiguous to the site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except Underground Facilities) which have been identified in the Supplementary Conditions as provided in Paragraph 4.02 of the General Conditions and the Supplementary Conditions and (2) reports and drawings of a hazardous Environmental Condition, if any, at the Site which has been identified in the Supplementary Conditions as provided in paragraph 4.06 of the General Conditions and the Supplementary Conditions . CONTRACTOR acknowledges that such reports and drawings are not Contract documents and may not be complete for CONTRACTOR's purposes. CONTRACTOR acknowledges that OWNER and ENGINEER do not assume responsibility for the accuracy or completeness of information and data shown or indicated in the Contract documents with respect to Underground Facilities at or contiguous to the site. E. CONTRACTOR has obtained and carefully studied (or assumes responsibility for having done so) all such additional supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress, performance or furnishing of the Work or which relate to any aspect of the means, methods, techniques, sequences and procedures of construction to be employed by CONTRACTOR, including applying the specific means, methods, techniques, sequences, and procedures of construction, if any, expressly required by the Contract Documents to be employed by CONTRACTOR, and safety precautions and programs incident thereto. F. CONTRACTOR does not consider that any additional examinations, investigations, explorations, tests, studies or data are necessary for the performance and furnishing of the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the Contract Documents. G. CONTRACTOR is aware of the general nature of work to be performed by OWNER and others at the site that relates to the Work as indicated in the Contract Documents. H. CONTRACTOR has correlated the information known to CONTRACTOR, information and observations obtained from visits to the site, reports and drawings identified in t he Contract Documents and all additional examinations, investigations, explorations, tests, studies and data with the Contract Documents. I. CONTRACTOR has given ENGINEER written notice of all conflicts, errors, ambiguities or discrepancies that CONTRACTOR has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to CONTRACTOR. J. The Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work. ARTICLE 9. CONTRACT DOCUMENTS. A-5 9.01 Contents A. The Contract Documents which comprise the entire agreement between OWNER and CONTRACTOR concerning the work consist of the following: 1. This Agreement 2. Performance, Payment Bonds, and Insurance Certificates 3. Notice to Proceed. 4. General Conditions (pages 1 to 62, inclusive). 5. Supplementary Conditions 6. Specifications bearing the title Sanitary Sewer, Water Main, Storm Sewer & Street Construction for The Preserve at Bluff Creek 6th Addition in Chanhassen, MN. 7. Drawings consisting of sheets with each sheet bearing the following general title: Sanitary Sewer, Water Main, Storm Sewer & Street Construction for The Preserve at Bluff Creek 6th Addition in Chanhassen, MN. 8. Addenda 9. CONTRACTOR's Bid 10. Documentation submitted by CONTRACTOR prior to Notice of Award 11. The following which may be delivered or issued after the Effective Date of the Agreement and are not attached hereto: All Written Amendments and other documents amending, modifying or supplementing the Contract Documents pursuant to paragraphs 3.04 of the General Conditions and the Supplementary Conditions . 12. There are no Contract Documents other than those listed above in Article 9. 13. The Contract Documents may only be amended, modified or supplemented as provided in Paragraphs 3.04 of the General Conditions and the Supplementary Conditions . ARTICLE 10. MISCELLANEOUS 10.01 Terms A. Terms used in this Agreement which are defined in Article 1 of the General Conditions and the Supplementary Conditions will have the meanings indicated in the General Conditions and the Supplementary Conditions . 10.02 Assignment of Contract A-6 A. No assignment by a party hereto of any rights under or interests in the Contract Documents wil l be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents. 10.03 Successors and Assigns A. OWNER and CONTRACTOR each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, its partners, successors, assigns and legal representatives in respect to all covenants, agreements and obligations contained in the Contract documents. 10.04 Severability A. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall conti nue to be valid and binding upon OWNER and CONTRACTOR, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision. 10.05 CONTRACTOR’S Certifications A. CONTRACTOR certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for or in executing the Contract. For the purposes of this Paragraph 10.05: 1. “corrupt practice” means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process or in the Contract execution; 2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process or the execution of the Contract to the detriment of OWNER, (b) to establish Bid or Contract prices at artificial non-competitive levels, or (c) to deprive OWNER of the benefits of free and open completion; 3. “collusive practice” means a scheme or arrangement between two or more Bidders, with or without the knowledge of OWNER, a purpose of which is to establish Bid prices at artificial, non-competive levels; and 4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract. IN WITNESS WHEREOF, OWNER and CONTRACTOR have signed this Agreement in triplicate. One counterpart each has been delivered to OWNER, CONTRACTOR and ENGINEER. All portions of the Contract Documents have been signed, initialed or identified by OWNER and CONTRACTOR or identified by ENGINEER on their behalf. This Agreement will be effective on ______________________________, 2014 (which is the Effective Date of the Agreement). A-7 OWNER: CONTRACTOR: Chanhassen Residential Development Partners, LLC ______________________________.________ By:____________________________ By: Title:____________________________ Title: Attest__________________________ Attest__________________________________ Title ___________________________ Title __________________________________ Address for giving notices: Address for giving notices: ________________________________ ____________________________________________ ________________________________ ____________________________________________ ________________________________ ____________________________________________ Section 3.0 Instructions to Bidders IB-1 INSTRUCTIONS TO BIDDERS 1. PROPOSALS. A separate copy of the Contractor’s Proposal or bidding blank is included in loose form with this manual. All proposals must be on these official blanks. Any alteration of the Proposal form may be cause for rejection of the Proposal. Additional copies may be obtained at the office of the Engineer. 2. DELIVERY OF PROPOSALS. Each proposal and all papers bound and attached thereto shall be placed in an envelope and securely sealed therein. Envelopes shall be so marked as to indicate the following: A. Bid for The Preserve at Bluff Creek 6th Addition B. Name of Bidder C. To be Opened The envelopes shall be addressed to the designated officials of the Owner. They may either be mailed, delivered by messenger, or submitted in person. A faxed bid will be accepted for this project. All proposals shall be at the office of the designated recipient before the time set for opening proposals. Proposals arriving after the time designated for opening proposals will be returned unopened, or unread should a faxed bid be allowed. Proposals arriving by mail after the designated opening time will be returned to the sender unopened. All bids will be opened and read privately, by the Owners, who will advise the Contractors as soon as possible, of the decisions made. 3. CONDITIONS IN BIDDER'S PROPOSAL. The bidder shall stipulate in his proposal any conditions for which provisions have not been provided on the proposal form. 4. WITHDRAWAL AND MODIFICATION OF PROPOSAL. A Bidder may, without prejudice to himself, withdraw, modify, or correct a proposal after it has been deposited with the Owner. Any request for such withdrawal, modification, or correction must be filed with the Owner in writing or by telegram, before the time set for opening proposals. The original proposal, as modified by such written or telegraphic communication, will be considered to be the proposal submitted by the Bidder. No proposal can be withdrawn, modified or corrected after the time set for opening proposals. 5. PREPARATION OF PROPOSAL. The blank spaces in the proposal shall be filled in ink or typewritten and any alterations or interlineations shall be initialed by the Bidder. For each and every item for which a quantity is given, the bidder must state the prices for which he proposes to do each item of work contemplated. IB-2 The Bidder's Proposal must be signed in ink by the individual, by one or more members of the partnership, or by one or more officers of the corporation submitting it. If the proposal is made by an individual, his name and post office address must be shown; if made by a partnership, the name and post office address of each member of the partnership must be shown; if made by a corporation, the corporate seal must be affixed and the name and title of the individual signing the proposal and the corporation’s business address must be shown. Anyone signing a proposal as agent may be required to submit satisfactory evidence of his authority to do so. A proposal may be considered irregular and may be rejected if it shows any omissions, alterations of form, additions not called for, conditional or alternate bids not called for, or irregularities of any kind which may tend to make the proposal incomplete, indefinite or ambiguous as to its meaning. 6. EXAMINATION OF THE PROPOSED WORK AND PROJECT MANUAL REQUIREMENTS. Bidders shall inform themselves concerning the conditions under which the work is to be performed, determine the availability of materials and labor, examine to their satisfaction the quantities of work to be performed as determined from the drawings and project manual, thoroughly review the drawings, project manual and other contract documents to make sure all requirements are fully understood. Failure on the part of the Bidder to ascertain all the requirements of the Drawings, Project Manual, other Contract Documents, and conditions at the site of work shall not constitute a basis for extra compensation nor relieve the Bidder from any obligations. No bidder may rely upon any statements or representations of any officer, agent, or employee of the Owner with reference to the conditions of the work on the character of the soil or other hazards which may be encountered during the course of construction. The submission of a bid will constitute an incontrovertible representation by the Bidder that he has A. Examined the Contract Documents thoroughly, B. visited the site to familiarize himself with local conditions affecting the Work and performed all subsurface investigations which he has deemed necessary, C. familiarized himself with federal, state, county, and local laws, ordinances, rules and regulations that may in any manner affect cost, progress or performance of the Work, and D. studied and carefully correlated his observations with the Contract Documents. The Bidder shall base his proposal on materials and equipment complying fully with the Drawings and Project Manual, and should his bid have been based on materials or equipment which do not conform, or which in the judgment of the engineer does not meet the requirements of the "Or Equal" determination, the Bidder shall furnish materials and equipment as specified, at no change in contract price. 7. BID SECURITY. No bid security is required for this project. IB-3 8. INTERPRETATIONS OF PROPOSAL ESTIMATES. The quantities as shown in the Proposal are estimated and are furnished only as a basis to prepare a bid and to determine the low Bidder. The quantities shown in the Proposal are not guaranteed to be exact. The Contractor agrees that he will make no claim for anticipated profits, or for losses because of any difference between the work actually done or materials furnished and the estimated quantities stated in the agreement. 9. INTERPRETATION OF CONTRACT DOCUMENTS. If any person contemplating submitting a bid for the proposed Contract is in doubt as to the true meaning of any part of the drawings, project manual or other Contract documents he may submit to the engineer a written request for an interpretation thereof. An interpretation of the documents will be made only by an Addendum duly issued. The addendum will be mailed, sent by telecopy, or delivered to each person receiving a copy of said documents (planholders) and become a legal and binding part thereof. 10. COMPETENCY OF BIDDERS. If so requested by the Owner, the Bidder shall furnish a complete statement of his experience as well as the amount of capital and equipment available for the proposed work. No contract will be awarded except to a responsible Bidder, capable of performing the class of work contemplated. Failure on the part of any Bidder to satisfactorily complete previous projects within the specified time, or his lack of experience, equipment or capital necessary for the satisfactory completion of the work, may be deemed sufficient cause for disqualification. 11. DISQUALIFICATION OF BIDDERS. Evidence that any Bidder is interested in more than one proposal for the same project will cause rejection of all such proposals. Collusion between the Bidders will be considered sufficient cause for the rejection of all bids. 12. AWARD OF CONTRACT. The Owner reserves the right to reject any or all bids, or to accept such bid or bids as, in the opinion of the Owner, will be to the best of his interests. No Bidder may withdraw his bid for at least ten (10) days after the scheduled closing time for the receipt of bids. Comparison of bids will be based on the total bid after the addition of the amount of the correct multiplication of each unit price applied to the number of units or the total bid lump sum. 13. TIME OF PERFORMING CONTRACT. The Notice to Proceed with the work will be issued at the pre- construction conference. The dates that work shall commence and be substantially complete are stated in the Bid Proposal. 14. UNIT PRICES CONTROL. The total amount of the contract shall be based on the unit prices. The total amount of the contract shall be the correct addition of the extended prices which in turn shall be the correct product of the number of the units times the unit price. 15. TAXES. Each Bidder shall include and shall be deemed to have included in the prices quoted in the Contractor's Proposal the amounts which it is estimated will be payable by the successful Bidder on account of taxes imposed by any taxing authority upon the sale, purchase or use of materials, supplies, or equipment incorporated in the project. All taxes, shall be payable by the Bidder awarded the contract for the construction of the project. Successful Bidder is subject to payment of Minnesota income tax in amount prescribed by law. If successful Bidder is a non-Minnesota partnership, individual or association, he shall furnish evidence, prior to execution of contract, that bond or securities have been posted with the Minnesota Department of Revenue in the amount required by law. IB-4 17. O.S.H.A. PROVISIONS. This contract, including all materials, equipment and workmanship, is subject to the provisions of the Williams-Steiger Occupational Safety and Health Act of 1970. The Contractor shall have Right-to-Know and AWAIR Programs approved by O.S.H.A. in place. If so requested, the Contractor shall show evidence of these programs. 18. COST OF CHANGES. In all contracts where equipment is furnished, due to lack of standardization of equipment as produced by the various manufacturers, it may become necessary to make minor modifications in the structures, buildings, piping, mechanical work, electrical work, accessories, controls, etc., to accommodate the particular equipment use. The Contract price shall include the cost of making all of the aforementioned necessary changes as well as the cost of preparing detailed drawings showing such changes subject to the approval of the Engineer. 19. SUBCONTRACTING. The Contractor may subcontract portions of the work; however, if the subcontract exceeds $500.00, the Contractor must name such intended subcontractor and amount of subcontract on a sheet to be attached to and included with the Proposal. The Contractor shall not subcontract more than fifty percent (50%) of the value of the work. 20. PROJECT RECORDS. The payroll records and all other project records of the Contractor and each subcontractor shall be maintained during the course of the work and retained for a period of 3 years after completion and acceptance of the work. These records shall be made available during the 3-year period to authorized representatives of the local, county, state and Federal governments. Section 4.0 Supplementary Conditions to the Standard General Conditions of the Construction Contract SC - 1 SUPPLEMENTARY CONDITIONS TO THE STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT The Standard General Conditions of the Construction Contract, EJCDC Document C-700 (2007 Edition), Articles 1 through 17 are hereby incorporated as the General Conditions of this Contract. The articles contained in these following Supplementary Conditions may modify, delete or add to the provisions of the General Conditions and shall take precedence over the General Conditions. Where a portion of the General Conditions is modified or voided by these articles, the unaltered portion shall remain in effect. SCOPE OF PROJECT This Contract shall consist of the furnishing of all labor, equipment and all else necessary to complete the project in accordance with the plans and specifications. The work shall include, but not be limited to: Sanitary Sewer, Water Main, Storm Sewer & Street Construction together with all appurtenant items in the proposed The Preserve at Bluff Creek 6th Addition, Chanhassen, MN. SC-1 DEFINITIONS AND GENERAL TERMINOLOGY SC-1.01 Defined Terms : The terms used in these Supplementary Conditions or in the other Contract Documents and Sections, have the meanings assigned to them in the General Conditions except as modified as follows: 19. ENGINEER - The ENGINEER on this project shall be Westwood Professional Services, Inc., 7699 Anagram Drive, Eden Prairie, MN 55344. Contact: Francis Hagen, II, P.E. (952) 937-7483 29. OWNER - The OWNER of this project will be Chanhassen Residential Development Partners, LLC. Contact: Todd Baumgartner (952) 897-1707 43. Subcontractor - An individual, firm or corporation having a direct contract with CONTRACTOR or with any other subcontractor for performance of a part of the work whether at or away from the site. SC-1.02 Terminology: Whenever used in these Supplementary Conditions or in the other Contract Documents and Sections, the following additional terms have the meanings indicated which are applicable to both the singular and plural thereof: 52. Access Road - That roadway used for egress and ingress to the construction site. 53. Easement - A right acquired to use or control property for a designated purpose. 54. Item - A unit of work for which a price is provided in the Agreement. SC - 2 55. Right-of-way - The whole area which is secured and reserved for street purposes, highway purposes, or through which the improvement is located. 56. Special Provisions - Additions and revisions to the standard and supplemental specifications covering conditions peculiar to the project. These may also be termed General Requirements. 57. Standard Drawings - Drawings which show standard construction details which have been prepared and/or approved by the ENGINEER and are usually bound with the specifications. SC-3 CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE SC-3.01 Intent: Replace section 3.01.A. with the following: A. These Supplementary Conditions, the Standard General Conditions of the Construction Contract, the project Specifications & Drawings, and all other items designated as Contract Documents in the Agreement, are essential parts of the Contract, and a requirement occurring in one is as binding as though occurring in all. The Contract Documents are intented to be complementary and to describe and provide for a complete work. In case of discrepancy: a. Calculated dimensions will govern over scaled dimensions b. Standard Details will govern over Drawings c. Drawings will govern over Special Provisions to the Standard Specifications d. Special Provisions to the Standard Specifications will govern over Standard Specifications SC-4 AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS; HAZARDOUS ENVIRONMENTAL CONDITIONS; HAZARDOUS ENVIRONMENTAL CONDITIONS; REFERENCE POINTS SC-4.05 Reference Points: Replace section 4.05.A with the following: ENGINEER will provide engineering surveys for construction including alignment, grade and other necessary points as noted in the standard specifications with proper notes thereon, accompanied when necessary by detailed instructions. The CONTRACTOR will be responsible for the preservation of all survey stakes and marks, and if, in the opinion of the ENGINEER, any of the survey stakes or marks have been carelessly or willfully destroyed or disturbed by the CONTRACTOR, the cost to the OWNER for replacing them shall be deducted from the payments due to the CONTRACTOR for the Work. CONTRACTOR shall provide ENGINEER sufficient notice of need for construction stakes to allow ENGINEER 48 hours for SC - 3 scheduling surveys and sufficient time to accomplish survey. CONTRACTOR shall provide a clear line of site for staking as required and shall immediately notify the ENGINEER if any points or stakes set are not true to line or grade or if the staking appears to deviate from the plan. SC-4.06 Hazardous Environmental Conditions at Site Delete Paragraphs 4.06.A and 4.06.B in their entirety and insert the following: A. No reports on drawings related to Hazardous Environmental Conditions are known to Owner or Engineer. B. Not Used. SC-5 BONDS AND INSURANCE SC-5.01 Performance, Payment, and Other Bonds: Add the following to section 5.01.A in THE STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT as follows: Bond forms used shall meet statutory requirements. The Contractor will be required to provide a maintenance bond and lien waivers as required by the City at the time of final acceptance of the project. Final payment will not be made until this bond is secured. SC-5.03 Certificates of Insurance: Add the following new paragraphs immediately after Paragraph 5.03.E: F. The Contractor is required to name as additional insured: Owner, Westwood Professional Services, Inc., and the City the work is being performed in. SC-5.04 CONTRACTOR's Liability Insurance: The limits of liability for the insurance required by paragraph 5.04 of THE STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT shall provide coverage for not less than the following amount or greater where required by Law and Regulations: Worker's compensation, etc. under paragraphs 5.04.A.1 and 5.04.A.2. in THE STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT: 1. State: Statutory 2. Applicable Federal (e.g. Longshoreman's): Statutory 3. Employer's Liability: $1,000,000 Per Accident SC - 4 CONTRACTOR's Liability Insurance under paragraphs 5.04.A.3 through 5.04.A.6 in THE STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT which shall also include completed operations and product liability coverages and eliminate the exclusion with respect to property under the care, custody and control of the CONTRACTOR: 1. General Aggregate (Except Products - Completed Operations) $1,000,000 2. Products - Completed Operations Aggregate $1,000,000 3. Personal and Advertising Injury (Per Person/Organization) $1,000,000 4. Each Occurrence (Bodily Injury and Property Damage) $1,000,000 5. Property Damage liability insurance will provide Explosion, Collapse and Underground coverages where applicable. 6. Excess or Umbrella Liability General Aggregate $1,000,000 Each Occurrence $1,000,000 Automobile Liability under paragraph 5.04.A.6 of the General Conditions a. Bodily Injury: $1,000,000 Each Person $1,000,000 Each Accident b. Property Damages $1,000,000 Each Accident c. Combined Single Limit of $1,000,000 Each Accident Add the following to section 5.04.B of THE STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT: CONTRACTOR shall include as additional insured the City, the owner as defined in section SC-1.01.A.29, their officers and employees, Westwood Professional Services, Inc., and their officers and employees. : Other reasons or entities to be included on policy as additional insured shall include the City, OWNER as d efined above in section SC-1.01.A.30 , The Contractual Liability required by paragraph 5.0.4.B of THE STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT shall provide coverage for not less than the following amounts: 1. General Aggregate $1,000,000 2. Each Occurrence (Bodily Injury and Property Damage) $1,000,000 Umbrella Policy to cover excess liability, Employer's liability, comprehensive general and automobile liability and contractors SC - 5 liability combined: $4,000,000 If statutory limit in any case is higher than that specified, then the statutory limit shall be adhered to. SC-9 ENGINEER'S STATUS DURING CONSTRUCTION SC-9.03 Project Representative Add the following to section 9.03.A in THE STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT: Resident Project Representative (RPR) is ENGINEER's Agent, will act as directed by and under the supervision of ENGINEER, and will confer with ENGINEER regarding his actions. Resident Project Representative's dealings in matters pertaining to the on- site Work shall in general be only with ENGINEER and CONTRACTOR, and dealings with subcontractors shall only be through or with the full knowledge of CONTRACTOR. Written communication with OWNER will be only through or as directed by ENGINEER. RPR duties and responsibilities will be as follows: 1. Review progress and shop-drawing submittal schedules, and schedule of values prepared by the CONTRACTOR. The RPR should consult with the ENGINEER about acceptability of the work. 2. Attend conferences and meetings with the CONTRACTOR and prepare and circulate minutes. 3. Serve as the ENGINEER's liaison with the CONTRACTOR and report to the ENGINEER concerning the adherence to the progress schedule. 4. Log shop drawings and samples. The shop-drawing schedule should indicate any work requiring a shop drawing or sample. The RPR should log interpretations and clarifications as well as substitute proposals and field orders. 5. Review work performed, disapprove defective work, and verify that tests and start-up procedures, as required by the contract documents, are accomplished. Accompany the OWNER'S personnel and inspectors, or representatives of agencies having jurisdictional interest, during site visits. 6. Receive requests for information from the CONTRACTOR and transmit the ENGINEER'S interpretations of the contract documents back to the CONTRACTOR. 7. Consider and evaluate the CONTRACTOR'S suggested modifications to the contract drawings or specifications and report to the ENGINEER. 8. Maintain at the site orderly files of all job records. Keep a diary or log book of weather conditions with names, addresses and telephone numbers of all CONTRACTORS, subcontractors, and major suppliers. 9. Measure and record quantities of Work completed in accordance wit h the Units and Method of Measurement specified in the Contract Documents, or contractor breakdown in the case of lump sum bids. 10. Submit to the ENGINEER periodic progress reports, and advice concerning major inspections and tests, draft change orders, field orders, and work directive changes. 11. Report immediately to ENGINEER upon the occurrence of any accident. SC - 6 12. Review payment requests with the CONTRACTOR before sending them to the ENGINEER. 13. Submit to the CONTRACTOR before a certificate of substantial completion is issued, a list of items that remain to be completed or corrected, and conduct a final inspection with the ENGINEER, OWNER AND CONTRACTOR. Verify that all items on the final list have been completed or corrected. 14. Determine if certificates, operating and maintenance manuals, and other required data have been assembled by the CONTRACTOR and forwarded to the ENGINEER. 15. In coordination with the ENGINEER, prepare record plans and specifications as required. The RPR operates under a number of limitations of authority. The RPR has no power or right to: 1. Authorize any deviation from the contract documents or substitutions of materials and equipment, except as specifically authorized by the OWNER. 2. Exceed the limitations of the ENGINEER'S authority outlined in the contract documents and the service agreement. 3. Assume any of the responsibilities of the CONTRACTOR, subcontractors, or their superintendents. 4. Advise on or issue instructions concerning the CONTRACTOR'S techniques, sequences, or other procedures or construction unless specifically required by the contract documents. 5. Advise, issue directions concerning, or take control over safety precautions and programs. 6. Accept shop drawings or samples from anyone other than the CONTRACTOR. 7. Authorize the OWNER to occupy the project in whole or in part, except as specified in the construction contract. 8. Participate in specialized field or laboratory tests or inspections conducted by others, unless specifically authorized by the ENGINEER. SC-10 CHANGES IN THE WORK; CLAIMS SC-10.05 Claims and Disputes Amend the first sentence of section 10.05.B in THE STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT to read as follows: Notice: Written notice stating the general nature of each claim, dispute, or other matter shall be delivered by the claimant to ENGINEER and the other party to the Contract promptly (but in no such event later than 10 days) after the start of the event giving rise thereto. SC-11 COST OF THE WORK; ALLOWANCES; UNIT PRICE WORK SC-11.03 Unit Price Work SC - 7 SC-11.03.D Delete Paragraph 11.03.D in its entirety and insert the following in its place: D. The unit price of an item of Unit Price Work shall be subject to reevaluation and adjustment under the following conditions: 1. if the Bid price of a particular item of Unit Price Work amounts to 10 percent or more of the Contract Price and the variation in the quantity of that particular item of Unit Price Work performed by Contractor differs by more than 20 percent from the estimated quantity of such item indicated in the Agreement; and 2. if there is no corresponding adjustment with respect to any other item of Work; and 3. if Contractor believes that Contractor has incurred additional expense as a result thereof or if Owner believes that the quantity variation entitles Owner to an adjustment in the unit price, either Owner or Contractor may make a Claim for an adjustment in the Contract Price in accordance with Article 10 if the parties are unable to agree as to the effect of any such variations in the quantity of Unit Price Work performed. SC-12 CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIMES SC-12.01 Change of Contract Price Replace sections 12.01.C.2.a, in THE STANDARD GENERALCONDITIONS OF THE CONSTRUCTION CONTRACT with the following: a. for costs incurred under paragraphs 11.01.A.1 and 11.01.A.2, the Contractor’s fee shall be 10% SC-14 PAYMENTS TO CONTRACTOR AND COMPLETION SC-14.02 Progress Payments Replace section 14.02.A.1 in THE STANDARD GENERAL CONDITIONS OF THE CONSTRUCTION CONTRACT with the following: Estimates of work completed will be prepared by the ENGINEER upon completion of construction, required testing & acceptance by the City of each of the following 2 Phases of Construction: 1. Sanitary Sewer, Water Main & Storm Sewer Construction 2. Street Construction through the installation of the Bituminous Base Course and the backfilling of the Concrete Curb The estimates will be prepared based on the Contract Unit Pricing Proposal for work completed and accepted by the City, less 5% to be retained until final completion and SC - 8 acceptance of the work and less previous payments. Progress estimates will be prepared by the ENGINEER as accurately as the available information will permit but the only estimate that is binding is the final estimate. Copies of progress estimates will be furnished to the CONTRACTOR within 5 days of City acceptance of each phase of construction for his review and approval. Progress estimates approved by the CONTRACTOR shall be counter-signed by the ENGINEER and forwarded to the OWNER for payment. The CONTRACTOR will be required to keep accurate records of said construction, but will not be required to apply said quantities for payment until final payment has been requested. Estimates prepared by the ENGINEER that vary considerably from what the CONTRACTOR claims shall be brought to the attention of the ENGINEER in writing prior to the next pay period. Payment will be made within 30 days of receipt of the estimate by the OWNER except as otherwise agreed between the CONTRACTOR and OWNER. The OWNER may withhold payment in whole or in part on an approved estimate to the extent necessary to protect himself from loss on account of any of the following causes discovered subsequent to approval of the estimate by the ENGINEER, as follows: 1. Defective work not remedied. 2. Claims for labor or materials furnished the CONTRACTOR or Subcontractor, or reasonable evidence indicating probable filing of such claims. 3. Failure of CONTRACTOR to make payments properly to Subcontractors or for work or labor. 4. Amounts necessary to insure that an overpayment on the total contract amount will not occur. 5. Evidence of damage to another CONTRACTOR or private property. SC-16 DISPUTE RESOLUTION SC-16.01 Methods and Proceedures Delete Paragraph 16.01.C in its entirety and insert the following in its place: C. If the Claim is not resolved by mediation, Engineer’s action under Paragraph 10.05.C or a denial pursuant to Paragraphs 10.05.C.3 or 10.05.D shall become final and binding 30 days after termination of the mediation unless, within that time period, Owner or Contractor: 1. gives to the other party written notice of intent to submit the Claim to a court of competent jurisdiction, or 2. agrees with the other party to submit the Claim to another dispute resolution process. SC-16.01.D Add the following new paragraph immediately after Paragraph SC-16.01.C. SC - 9 D. Notwithstanding any applicable statute of limitations, a party giving notice under Paragraph SC-16.01.C.1 shall commence an action on the Claim within one year of giving such notice. Failure to do so shall result in the Claim being time-barred and Engineer’s action or denial shall become final and binding. Section 5.0 General Conditions of the Construction Contract Prepared by Engineers Joint Contract Documents Committee SPEC-1 WPS REVISION: JANUARY 2009 SPECIAL PROVISIONS FOR EROSION CONTROL & TURF ESTABLISHMENT SCOPE OF WORK This Contract shall consist of the furnishing, installing & maintaining erosion and sediment control devises, turf establishment and any work specified in conjunction therewith as well as removing temporary sediment control devices when no longer necessary, to complete and maintain the project in accordance with the plans and specifications. The work shall include, but not be limited to: 1) Managing storm water runoff and project related water discharges, in order to minimize sediment pollution during project construction and over the life of the contract; 2) Managing the discharges associated with dewatering and basin draining activities as set forth in the NPDES permit: 3) Providing temporary shaping and grading; 4) Applying temporary soil covers; 5) Establishing a perennial ground cover. Erosion and sediment control measures shall be constructed and maintained as planned and specified following Best Management Practices as outlined by the Minnesota Pollution Control Agency (MPCA) and being in conformance with the MPCA General Stormwater Permit together with all appurtenant items in the proposed The Preserve at Bluff Creek 6th Addition located in Chanhassen, Minnesota. Unless otherwise noted or modified herein, all sections of the General Conditions shall apply. 1. SPECIFICATIONS WHICH APPLY Specifications which apply to the furnishing & installing of the erosion and sediment control measures and devices & turf establishment as shown in the plans shall be Division II (Construction Details), Sections 2573 & 2575 and Division III (Materials) of the "Standard Specification for Construction", Minnesota Department of Transportation, August 31, 2005 and current revisions, and the City of Chanhassen City Specifications and City Engineering Guidelines to the extent that they are modified by these special provisions. 2. STAKING The OWNER through the ENGINEER will provide the staking for erosion and sediment control measures as follows: The ENGINEER will stake silt fence on an average of every 50’ along the proposed fencing. All other staking necessary to perform the work, including the replacement of lost, damaged or destroyed stakes, will be the responsibility of the CONTRACTOR. 3. INSPECTION Erosion & sediment control inspections shall be conducted by the project’s SITE NPDES INSPECTOR (INSPECTOR Must be a trained individual after February 2010) every seven days and within 24 hours after a rainfall event exceeding 0.5 inches in a 24 hour period. The SITE NPDES INSPECTOR will conduct the inspections as specified in the Project SWPPP. SPEC-2 WPS REVISION: JANUARY 2009 The project must be in compliance with the requirements of the Minnesota Pollution Control Agency General Storm Water Permit for Construction Activity (MN R100001). The CONTRACTOR is required to have a copy of the Stormwater Pollution Prevention Plan (SWPPP), the National Pollutant Discharge Elimination System (NPDES), and copies of the NPDES Monitoring forms present on the project site at all times. The CONTRACTOR shall provide a mailbox (SWPPP Box) with lock to maintain these documents. If a job trailer is on site, the documents should be located in an area with 24 hour access. The Permit ID #, Contact # of Contractor, and other applicable information should be posted on site. The CONTRACTOR shall schedule and phase construction in critical resource areas to minimize the potential of sediment entering into a critical resource. Critical resources include but are not limited to, protected wetlands, surface waters, trout streams, Special Waters, impaired waters, rivers, and endangered species habitat. Measures to minimize sediment potential include practices such as hand clearing and grubbing, limited bare soil exposure time, and immediate final establishment of vegetation. 4. STORM WATER MANAGEMENT (MnDOT 2573) In accordance with MnDOT 1716 the CONTRACTOR has responsibility for charge and care of the Project and shall take necessary precautions against injury or damage to the Project by action of the elements. In addition, the CONTRACTOR shall take necessary precautions to prevent off site damage resulting from work conducted on the Project or Project related storm water runoff. Extreme care shall be exercised in all phases of the Project’s construction operation to control erosion and siltation into drainage ways. The CONTRACTOR shall be required to provide silt fence dikes and weirs of approved fabric in all areas where runoff from open graded areas could cause siltation. In addition, the CONTRACTOR shall provide interim sumps of adequate size to intercept silt in areas of concentrated runoff. These dikes, weirs and sumps shall be maintained in such a manner as to prevent siltation of the natural ponding areas. All construction shall be in accordance with the requirements of the Minnesota Pollution Control Agency General Storm Water Permit for Construction Activity (MN R100001). The CONTRACTOR shall designate an Erosion Control Supervisor (ECS) as the project point of contact for erosion and sediment control issues. This person shall have valid documented training and / or certification. The certification is obtained by completing a two (2) day Erosion/Sediment Control Site Management training class and passing the required test or equivalent training / certification course. A copy of the Erosion Control Supervisor’ certification shall be forward to the ENGINEER prior to the start construction. The ECS shall also provide 24 hour emergency contact information in case of a need to contact the ECS after normal construction hours. The Erosion Control Supervisor (ECS) shall be considered incidental to the contract and no additional direct compensation shall be made therefore. All erosion and sediment control shall be in place and approved by the ENGINEER, City, Watershed, etc., prior to starting any excavation on the site. Temporary storm water basins shall be constructed concurrently with the start of soil disturbing activities. The basins must be made fully functional and have storm water runoff from the localized watershed directed to the basins. The exposed side slopes of the basins must be mulched and/or seeded within the time periods as set forth in the Minnesota Pollution Control Agency General Storm Water Permit for Construction Activity (MN R100001) & the SWPPP Narrative, or as directed by the ENGINEER. Erosion and sediment control devices shall be maintained throughout the duration of the contract. SPEC-3 WPS REVISION: JANUARY 2009 The CONTRACTOR shall comply with all conditions and completion dates relative to all permits issued by any regulatory agency. The CONTRACTOR shall provide the required signatures on the Minnesota Pollution Control Agency's permit application. A. Unsatisfactory Conditions Site soils shall not be allowed to deposit on the existing public roadways, nor on neighboring properties, nor in public waters. The CONTRACTOR will be given a notice when an unsatisfactory condition exists. The CONTRACTOR shall perform the necessary clean-up or repair work within 48 hours of notice or others will complete the work at the CONTRACTOR's expense. B. Removal of all Temporary Devices All temporary erosion & sediment control structures and devices (silt fence, temp. pond outlets, pipes, etc.) shall be removed and disposed of by the CONTRACTOR, at the end of their temporary life. Payment items are listed in the proposal. C. Workmanship & Quality Control The CONTRACTOR is responsible for maintaining quality control on the project by ensuring that all work performed and all materials furnished are in conformance with t he dimensions, installation requirements and material specifications shown on the plans or indicated in the specification. Quality workmanship shall be used in all aspects of the work and shall be uniform in character throughout the project. D. Certified Installers When erosion or sediment control practices are installed, a certified installer shall be on the Project to install the practices or direct the installation . Certified installer requirements shall be in accordance with MnDOT 2573.3P1 and according to Part III.A.2. (Post February 2010) of the Minnesota Pollution Control Agency General Storm Water Permit for Construction Activity (MN R100001). If the CONTRACTOR or subcontractor(s) fails to provide the required certified installer(s), the Erosion Control Supervisor shall notify the ENGINEER. If the ENGINEER determines that one or more required certified installers have not been provided, the CONTRACTOR shall respond to the ENGINEER’s notification within 2 days with the appropriate certified or provisionally certified person(s), or be subject to a $500.00 per required installer per calendar day deduction for noncompliance. E. Workmanship Rework Schedule Performance of the work shall be controlled by the CONTRACTOR so that the materials installed and the workmanship practices are of good quality. When the quality falls below the threshold level defined in MnDOT Table 2573-1, the CONTRACTOR shall take immediate action to correct the situation and prevent it from reoccurring. Any corrective actions required for acceptance of the work shall be performed at the CONTRACTOR’s expense. SPEC-4 WPS REVISION: JANUARY 2009 5. SILT FENCE Silt fence will be required as shown on the plans and as directed by the ENGINEER. The final configuration and placement of all erosion and sediment control structures shall be subject to the approval of the aforementioned governing agencies. The required silt fence shall conform to the standard details by the City or MnDOT 3886. 6. ROCK CONSTRUCTION ENTRANCE A rock construction entrance as shown on the plans or at the direction of the ENGINEER, shall be constructed of a minimum depth of 12” to a width that is sufficient for two-way traffic leading to and from the site. The entrance shall be a minimum length of 50 feet. The material shall be clean rock from 1” to 2” in diameter. MnDOT 3733, Type IV geotextile fabric must be placed under rock. The entrance will require maintenance and replacement throughout the life of the utility & street contract. All temporary access installed / used for project access and not shown on the plans or preapproved by the ENGINEER, shall have temporary rock entrances installed at the CONTRACTOR’s expense. 7. TURF RESTORATION All disturbed areas shall be seeded with Mn/DOT 3876 Mixture No. 150 except for pond areas below the normal water level, streets, parking areas and areas designated for immediate building construction or other areas designated for a different seed mix on the plans. Seeding shall be in accordance with Mn/DOT 2575. All slopes and other areas designated by the ENGINEER shall be mulched, in accordance with Mn/DOT 2575, with Type I mulch at the rate of 2 tons per acre and shall be disc-anchored within 48 hours after applying seed, or as directed by the ENGINEER. All areas designated to be seeded shall be seeded and mulched within seven (7) days of the re-spreading of topsoil or when directed by the ENGINEER. If the CONTRACTOR has to apply more than one seeding application to remain in conformance with the General Storm Water Permit, due to sequencing of the CONTRACTOR’s own operations, no additional payment will be made and such seeding will be considered incidental to the contract. 8. BOULEVARD RESTORATION All sod furnished to the project shall conform to the requirements of MnDOT 3878, Type A Lawn Sod, and shall be installed in conformance with MnDOT 2575.3. The CONTRACTOR shall water & maintain the sod, in a condition satisfactory to the ENGINEER, for 30 calendar days. The ENGINEER will then make the final inspection and consider acceptance of the sod. During the maintenance period, the CONTRACTOR shall promptly replace all sod that dries out to the point where it is presumed dead, or has become heavily infected with weeds. Areas replaced with new sod shall be maintained by the CONTRACTOR for at least 30 calendar days after placement. SPEC-5 WPS REVISION: JANUARY 2009 9. STORM DRAIN INLET PROTECTION (CURB INLET PROTECTION) All storm drain inlets shall be protected from the infiltration of sediments in accordance with the plans and details. Curb inlet protection (WIMCO’s or approved equal) shall be installed around all catch basin inlets in the streets within 24 hours of the curb and gutter placement, and in accordance with the plans and details. The inlet protection shall remain in place until the site has stabilized. Maintenance of the inlet protection shall be considered incidental during construction. This includes all cleaning of the inlet protection as directed by the ENGINEER. 10. STORM DRAIN INLET PROTECTION (REAR YARD INLET) All storm drain inlets shall be protected from the infiltration of sediments in accordance with the plans and details. Rear yard inlet protection shall be installed around all catch basin inlets immediately after the site has been graded and run off can enter the basin. The inlet protection shall remain in place until the site has stabilized. Maintenance of the inlet protection shall be considered incidental during construction. This includes all cleaning of the inlet protection as directed by the ENGINEER. BASIS OF PAYMENT The basis of measurement and payment shall be as noted on the proposal form. The proposal form indicates that some of the items are planned quantities (P). Planned quantities (P) in this format are an agreed upon quantity by the CONTRACTOR that are to be paid as a lump sum item unless changes to the plan are requested by the OWNER. Should there be plan changes, the payment for these changes will follow the method of measurement and payment as described below. A. Silt Fence By the Contract Unit Price per lineal foot furnished and installed, including sumps and maintenance during the term of the Contract. All silt fence that is damaged by excessive erosion or the CONTRACTOR’S equipment shall be replaced and maintained at no extra cost to the OWNER. Maintenance shall include the removal of silt material during the term of the contract as determined by the ENGINEER. This maintenance shall be performed at no extra cost to the OWNER. The original placement of the silt fence shall be coordinated with the ENGINEER to insure an adequate placement. If a double row, or extra reinforcement of silt fence is required in some areas, the areas shall be determined by the SITE NPDES INSPECTOR at the initial placement. B. Rock Construction Entrance By the Contract Unit Price per Each furnished, installed and maintained during the life of the construction contract. C. Turf Restoration By the lump sum in accordance with MN/DOT 2575. SPEC-6 WPS REVISION: JANUARY 2009 D. Boulevard Restoration By the Contract Unit Price per lineal foot of sod installed (2 rolls wide) and shall include all cost associated with the maintenance and watering for 30 days after installation. Measurement for payment shall be computed on the basis of planned dimensions. Payment will be authorized with final acceptance. E. Storm Drain Inlet Protection (Curb Inlet Protection) Storm Drain Inlet Protection (Curb Inlet Protection) will be measured by the number of individual inlets properly protected over the life of the contract without regard to the various types or number of devices used at each storm drain inlet. The unit bid costs shall include all materials and labor for the installation and the removal of the inlet protection. Maintenance of the inlet protection shall be considered incidental during construction. This includes all cleaning of the inlet protection as directed by the ENGINEER. F. Storm Drain Inlet Protection (Rear Yard Inlet) Storm Inlet Protection (Rear Yard Inlet) will be measured by the number of individual inlets properly protected over the life of the contract without regard to the various types or number of devices used at each storm drain inlet. The unit bid costs shall include all materials and labor for the installation of the inlet protection. Maintenance of the inlet protection shall be considered incidental during construction. This includes all cleaning of the inlet protection as directed by the ENGINEER. 11. OTHER AGENCIES The CONTRACTOR shall be required to conform to the demands of the regulating agencies involved with this project including, but not limited to the City of Chanhassen and the Watershed District. Section 6.0 Special Provisions SPU – 1 WPS REVISION: FEBRUARY, 2007 SPECIAL PROVISIONS to the STANDARD UTILITY SPECIFICATIONS SCOPE OF WORK This Contract shall consist of the furnishing of all labor, equipment and all else necessary to complete the project in accordance with the plans and specifications. The work shall include, but not be limited to: sanitary sewer, water main, storm sewer, and services together with all appurtenant items in the proposed The Preserve at Bluff Creek 6th Addition located in Chanhassen, Minnesota. Unless otherwise noted or modified herein, all sections of the General Conditions shall apply. 1. SPECIFICATIONS WHICH APPLY The specifications which apply to the construction of sanitary sewer storm sewer, and water main work as shown in the plans shall be ""Standard Specifications For Trench Excavation And Backfill / Surface Restoration, Water Main And Service Line Installation, Sanitary Sewer And Storm Sewer Installation, 1999 Edition" as prepared by the City Engineers Association of Minnesota, and the City of Chanhassen Specifications, to the extent that they are modified by these special provisions. Should there be a conflict between the two referenced specifications, the more stringent shall apply. 2. STAKING Staking for utilities provided by the ENGINEER shall be as follows: Sanitary and Storm Sewers (1 complete set) - Main: 50' center, offset per CONTRACTOR's request - Manholes: location and grade of invert and rim (offset w/witness stakes) - Services: Wye location noted on cut sheets, services staked to the stub with offset and witness stakes Water Main (1 complete set) - Main: 50' centers, offset per contractor - Hydrants/valves: line and grade with offset and witness - Tees & bends: as needed for construction - Services: location and grade at stub with offset and witness ENGINEER shall provide the CONTRACTOR's field foreman with copies of cut sheet indicating cuts from stakes provided the same day the survey crew places stakes. All survey work shall be scheduled through the Westwood Construction Engineer / Construction Observer by the OWNER and/or CONTRACTOR on site. Every attempt shall be made to provide the requested staking within 24 hours of said request. Under no circumstances shall the surveyor's response time be greater than 48 hours from request without notifying the OWNER. 2600.3 CONSTRUCTION REQUIREMENTS A2 Establishing Line and Grade Staking will be provided in accordance with section 2 above. SPU – 2 WPS REVISION: FEBRUARY, 2007 B3 Excavation Limitations and Requirements Excavating operations shall proceed only so far in advance of pipe-laying as will satisfy the needs for coordination of work and permit advance verification and unobstructed line and grade as planned. The amount of open or unfilled trench shall not exceed 500 feet unless ordered by the ENGINEER, and failure to comply with this requirement shall be cause for shut-down of the entire job until such back-filling is accomplished. All trench work MUST be confined to the right-of-way and easement areas as shown on the plans. Should trenches extend into side yard areas, the Contractor must be aware of the construction limits. Refer to the final plat for easements if they are not noted on the plans. Should excavations or stockpiling extend outside the project property, the CONTRACTOR must obtain written permission from adjacent land owners prior to the work being done. Where interference with existing structures is possible or in any way indicated, and where necessary to establish elevation or direction for connection to in-place structures, the excavating shall be done at those locations i n advance of the main operation so actual conditions will be exposed in sufficient time to make adjustments without resorting to extra work or unnecessary delay. The CONTRACTOR shall keep accurate records of all utility installations as to type, location, elevation, point of connection and termination, etc. Utility installations shall not be backfilled until all required information has been obtained and recorded. In addition to the usual safety equipment and procedures, the CONTRACTOR shall also make available at the job site the following: 1. An air blower with a directional chute capable of delivering 1,500 c.f.m. of fresh air at sewer manholes. 2. An approved harness or rope-sling for rescue of personnel from manholes. 3. An approved portable oxygen supply unit with face mask and goggles. 4. An approved meter to detect oxygen and hazardous gas levels. No personnel will be allowed to enter completed sanitary sewer manholes without this equipment immediately available for use by a "top man" stationed at the manhole. All safety equipment shall remain the property of the CONTRACTOR. E Pipeline Backfilling Operations The backfilling shall be accomplished with the use of suitable materials selected from the excavated materials to the extent available and practical. Should the materials available within the trench section be unsuitable or insufficient, the CONTRACTOR shall, when directed by the ENGINEER, replace unsuitable material beneath roadways with suitable materials from other parts of the project. The removal and disposal of unsuitable material and the hauling, placing, and compacting of the surplus material, shall be considered incidental to the pipeline installation and no payment will be made for this item. SPU – 3 WPS REVISION: FEBRUARY, 2007 It is the responsibility of the CONTRACTOR to review the geotechnical borings to determine if the installation of utilities will encounter ground water conditions. Adequate dewatering equipment shall be used to maintain water levels below the pipeline during installation. The cost of the dewatering shall be considered incidental to the installation of the pipe. Should the material from the pipeline excavation yield excess suitable material, the CONTRACTOR shall use the material as needed as suitable fill material on the project. If the fill requirements have been satisfied on the project, the material shall become the property of the CONTRACTOR. The material shall be removed from the site at the expense of the CONTRACTOR. The CONTRACTOR shall have sufficient equipment on site during utility installation to perform backfilling and compaction operations. If determined by the ENGINEER that insufficient equipment exist, installation of utilities shall cease until such equipment becomes available. The CONTRACTOR shall be responsible for maintaining proper site drainage. Site drainage will be reviewed at the end of each day’s activities. The CONTRACTOR shall provide all equipment and labor necessary to maintain good site drainage and shall be considered incidental. Each lift shall be compacted over the full width of the excavated area. The CONTRACTOR shall perform compaction to ensure that the material placed below 3' of the top of the excavation and 1' above the pipe shall be compacted to a minimum of 95% of standard Proctor dry density. The material placed in the top 3' of the trench as well as the aggregate base below pavements shall be compacted in the same manner to a minimum of 100% standard Proctor dry density. Service trenches must be compacted in the same manner as the main trench unless a higher compaction level is specified by the ENGINEER. In areas where curb and gutter exists, sufficient curbing shall be removed to allow the prescribed compaction over the entire disturbed area. Utility backfill placed in "green" areas (not below pavement) shall be compacted to a minimum of 95% of standard Proctor dry density. Utility backfill placed in "green" areas (not below pavement) adjacent to proposed or existing buildings or structures shall be compacted to the same requirements as under pavements. At the time of compaction, the moisture content of the embankment material shall be within 4% of the soil's optimum moisture content, as determined by standard Proctor, where a minimum of 95% of standard Proctor dry density is required, and shall be no more than 1% over the soil's optimum moisture content, where a minimum of 100% of standard Proctor dry density is required. If directed by the ENGINEER, a zero air voids specification may be allowed for wet backfill below pavements. The zero air voids specification consists generally of compacting the backfill to a minimum of 90% standard Proctor density with a dry density within 5% of the maximum dry density at the moisture content defined by the standard Proctor. The moisture requirements shall not apply to materials classified by the ENGINEER as Granular Material, nor shall the above specified moisture controls apply to SPU – 4 WPS REVISION: FEBRUARY, 2007 materials placed without specific density control. The soils report, as represented on this project, may contain additional or more stringent requirements. In all cases, the soils report shall govern the construction techniques used with respect to the compactive efforts on this project. The CONTRACTOR is responsible for understanding all requirements within the soils report, which is appended to this specification. In all cases, the CONTRACTOR shall blade and compact the roadway after the trench has been backfilled, so that it shall be passable to traffic and in a free draining condition at all times. The CONTRACTOR shall maintain the roadway in a condition acceptable to the ENGINEER at all times until final approval of the entire work by the OWNER. Water shall be used for dust control and moisture conditioning (scarifying and applying water to dry soil or scarifying and drying wet soil) shall be applied as directed by the ENGINEER. The CONTRACTOR shall remedy, at his own expense, any defects that appear in the backfill for a period of one year following the final written letter of acceptance of the project from the City and or ENGINEER. F. Turf Restoration All areas disturbed from utility construction and staging shall be seeded with MN/DOT 3876 Mixture No. 150. Seeding shall be in accordance with MN/DOT 2575. All areas disturbed from utility construction and staging shall be mulched in accordance with MN/DOT 2575 with Type I mulch at the rate of 2 tons per acre and shall be disc-anchored within 48 hours after applying seed. Existing topsoil on site prior to utility installation shall be salvaged and re-spread at a depth of 6” after the installation of the pipe line prior to being seeded. 2600.5 BASIS OF PAYMENT F. Turf Restoration Turf restoration will be paid for on a lump sum basis as indicated on the proposal form. 2611 WATERMAIN AND SERVICE LINE INSTALLATION MATERIALS A1 Ductile Iron Pipe and Ductile Iron and Gray Iron Fittings All 4", 6", 8" and 12" water main shall be Class 52, ductile iron pipe, in conformance with the requirements of ANSI A- 21.51 (Ductile Iron Pipe Centrifugally Cast in Metal Molds or Sand-line Molds). Pipe shall be tar coated, cement lined conforming to the requirements of AWWA C151; designed to operate at 150 psi plus water hammer. All ductile iron short body fittings shall be mechanical joint unless otherwise indicated and shall be in accordance with AWWA C153. All fittings shall be SPU – 5 WPS REVISION: FEBRUARY, 2007 designed for not less than 250 psi working pressure and shall have a standard thickness cement mortar lining conforming with AWWA C104. Conductive gaskets shall be those as manufactured by Amer ican Ductile Iron Pipe Company. Copper jumpers shall be a minimum of 1/16"x1/2" wide flat copper strip or annealed round copper wire conforming to ASTM B152, Type DHP. Field application of the copper jumpers shall conform to the Burndy Method as supplied by Burndy Corporation, Norwalk, Connecticut or the Cadeweld Method by Erico Products Co., Cleveland, OH. Silicon bronze nuts and bolts shall be used on all bolted connections. Welded connections shall be made on a clean metal surface, which has been grounded to remove coating and oxide. The area at the connection, including the weld shall be refinished with the original coating or other suitable protective coating. B Fire Hydrants All hydrants shall be Waterous "Pacer" No. WB-67 with the following requirements: 1. Hydrants are to have a five-inch minimum valve opening. They shall be equipped with two 2-1/2" diameter nozzles and one 4-1/2" steamer connection. Outlet threads shall be National Standard threads. 2. Hydrant barrels shall be two piece, with a 16" break-off traffic flange and flanged joint no more than two inches above the finished grade line with a mechanical joint connection at the hub end. Hydrants shall have an 8.0-foot bury. 3. All hydrants shall have a six-inch mechanical joint inlet for connecting into the six inch branch pipe from the main. There shall be a gate valve between the hydrant and the water main. 4. Hydrant operating mechanism shall be provided with "O" ring seals preventing the entrance of moisture and shall be lubricated through an opening in the operating nut or bonnet. 5. Shall open to the left (counterclockwise), and be able to drain when the hydrant is closed. 6. The size and shape of the operating nut shall be National Standard pentagon nut. 7. Hydrant must have permanent markings showing: 1) Manufacturer's name 2) Year of manufacture 3) Bury depth SPU – 6 WPS REVISION: FEBRUARY, 2007 4) The hydrant shall be furnished with a location flag. The flag will be a 60" Hydra-finder as manufactured by Rodon Corp. A3 Polyvinyl Chloride (PVC) Pressure Pipe and Fittings The pressure class shall be Class 150 with a DR rating of 18 and conforming with the outside diameter dimensions of cast iron pipe. Fittings shall be the same as required for ductile iron pipe. Tracer wire shall be no. 12 AWG gauge, single strand plastic coated copper wire and used only with the installation of PVC water main pipe. The wire shall be placed immediately below the pipe and run continuously between hydrants and gate valve boxes. The wire shall be wrapped twice around hydrants and curb stop boxes 4” below finish grade. The wire shall be attached to the traffic flange bolt on hydrants. Tracer wire connections shall be as approved by the ENGINEER. A continuity test shall be performed after construction is completed. Costs for furnishing and installing the wire shall be incidental. C2 Gate Valves Gate valves shall be resilient wedge type in accordance with AWWA 509 Specifications and have a working pressure of 200 psi. Valves shall be equipped with a mechanical joint ends in accordance with AWWA C111, shall have O-ring seals with non-rising stems a two inch (2") square nut and shall open counterclockwise. Gate valve boxes shall be vertical Buffalo type, cast iron shaft 5-1/4" in diameter. The valve box shall consist of three pieces with a box length to provide for 7.5 feet of cover and able to provide adjustment of at least twelve inches. D. Water Service Pipe and Fittings Curb Stop and Box Curb stops shall be Minneapolis pattern for copper service pipe inlet and outlet, of stop design with an inverted key and shall be Mueller H-15154 Mark II Oriseal or approved equal. The stop box shall be an extension type with stationary rod Minneapolis Pattern. Boxes shall have 12" adjustment with an 8' length when fully extended. Stop boxes shall be Mueller H-10300, Ford EM2-80-56-75R or approved equal. Curb stop lids shall be Mueller 89375 or approved equal. Taps into ductile iron water main having a 6” diameter or less and taps larger than 3/4" in diameter shall have a Smith-Blair type no. 313 saddle with two zinc plated straps or approved equal. All taps into PVC water main shall have A.Y. McDonald no. 3805 saddles or approved equal. SPU – 7 WPS REVISION: FEBRUARY, 2007 F. Restrained Joint Retainer Glands All fittings, stubs, hydrants and valves shall have restrained joint retainer glands. Water main and fitting joints shall be tied for a sufficient distance back for each plug, tee, cross or bend to allow soil friction to overcome the thrust. The pipe supplier shall furnish data on the frictional resistance to endwise movement of the pipe embedded in the earth. CONSTRUCTION REQUIREMENTS A2 Pipe Laying Operations Class C bedding shall be used to bed the pipe. The pipe shall be placed with care on an earth foundation, shaped to closely fit the width of at least 50% of the pipe breadth. The remainder of the pipe shall be backfilled to a height of 12 inches above the pipe with the material hand shovel-placed and thoroughly tamped in 6" layers to completely fill all the voids around the pipe. The pipe shall be laid at a minimum depth of 7.5’ to the top of the pipe unless otherwise indicated on the plans. The bottom of the water main and water services shall be laid at least 18 inches above the top of the sewer. Where this vertical separation cannot be obtained, the sewer shall be constructed of materials and with joints that are equivalent to water main standards of construction and shall be pressure tested to assure water tightness prior to backfilling; or shall have a ten (10) foot horizontal separation. A4 Blocking and Anchoring of Pipe All plugs, caps, tees, bends and other thrust points shall be blocked. A5 Polyethylene Encasement of Pipeline Polyethylene encasement material if indicated on the plans or City specifications shall conform to the requirements of ANSI A-21.5 (AWWA C-105) for tube type installation and a minimum 8 mil nominal film thickness. 2611.4 METHOD OF MEASUREMENT I Ductile Iron and Gray Iron Fittings The payment basis shall be as published in AWWA C-153. All ductile iron pipe fittings will be measured and paid for based on AWWA C-153 weights. Any difference between the weights published in AWWA C-153 charts and the weights of the fittings supplied to the project shall be considered incidental to the project. 2611.5 BASIS OF PAYMENT 1) Unless otherwise stated, cut-ins or connections to existing mains will be paid for at the Contract Unit Price per each cut-in or connection, and the SPU – 8 WPS REVISION: FEBRUARY, 2007 unit price will include all excavating, fittings, materials, backfilling, equipment, and labor necessary to make said installation. 2) Steel casing pipe shall be measured by the lineal foot of pipe actually jacked. This shall include all costs for equipment, materials, and labor for providing the jacking pit, de-watering, excavation, steel casing, sand fill, and backfilling the jacking pit to the specified density. 3) Items to be salvaged or salvaged and reinstalled shall be paid for by the each for each item or group of items as stated in the proposal form or as shown in the plans. 4) The cost of all material and labor required to complete this project as specified and shown on the plans, but not specifically included as a pay item, shall be merged with the various Contract Unit Prices bid. 5) All ductile iron pipe fittings will be paid for based on AWWA C- 153/A21.53 weights 2621 SANITARY SEWER & STORM SEWER INSTALLATION 2621.2 MATERIALS High density polyethylene (HDPE) corrugated pipe with an integrally-formed smooth interior shall conform to the following specifications: The specification is applicable to nominal sizes 12 - 36 inches in diameter. Requirements for test methods, dimensions and marking are those found in AASHTO Designations M252, MP7-97 and M-294. Pipe and fitting shall be made of polyethylene compounds which conform to the physical requirements of Type III, Category 3, 4 or 5, p23, p33 or p34, Class 3 per ASTM D-1248 with the applicable requirements defined in ASTM D-1248. Clean reworked material may be used. Minimum Pipe Stiffness values shall be as follows: Diameter Pipe Stiffness* 12 50 psi 15 42 psi 18 40 psi 24 34 psi 30 28 psi 36 22 psi *per ASTM Test Method D-2412 The pipe and fittings shall be free of foreign inclusions and visible defects. The ends of the pipe shall be cut squarely and cleanly so as not to adversely affect joining. SPU – 9 WPS REVISION: FEBRUARY, 2007 The nominal size for the pipe and fittings is based on the nominal inside diameter of the pipe. Inside diameter tolerances shall be plus 3.0% minus 1.5%. Corrugated fittings may be either molded or fabricated by the manufacturer. Fittings produced by manufacturers other than the supplier of the pipe lengths shall not be permitted without the approval of the ENGINEER. Couplings shall be corrugated to match the pipe corrugations and the width of shall not be less than 1/2 the nominal diameter of the pipe. Split couplings shall be manufactured to engage an equal number of corrugations on each side of the pipe joint. A neoprene-type gasket shall be utilized with the coupling to provide a soil-tight and water-tight joint. Connections to storm sewer structures with HDPE pipe shall include a rubber manhole boot per manufacturer's requirements to ensure a watertight seal. A manufacturer's certification that the product was manufactured, tested and supplied in accordance with this specification shall be furnished upon request to the ENGINEER. Installation shall be in accordance with ASTM recommended practice D-2321 or as specified by the ENGINEER. A2 Ductile Iron Pipe Ductile iron sanitary sewer pipe shall be used at depths over 30 feet and shall be Class 52, in conformance with the requirements of AWWA Standard C151 (Ductile Iron Pipe Centrifugally Cast in Metal Molds or Sand-line Molds). Pipe shall be tar coated, cement lined conforming to the requirements of AWWA C104. All ductile iron pipe shall be mechanical or push-on type joints. Bedding shall be Class C. A3 Reinforced Concrete Pipe Reinforced concrete pipe shall conform to the requirements of the Standard Specifications for Reinforced Concrete Sewer Pipe, A.S.T.M. Designation C-76, Wall B with circular reinforcing for the class of pipe specified. All reinforced concrete pipe joints shall be water tight. All R.C. pipe shall be Class 5 unless otherwise indicated on the plans or proposal. Bedding shall be class C. A5 PVC Pipe Polyvinyl chloride pipe and fittings shall have minimum wall thickness as covered by S.D.R. - 35 (heavy wall). PVC pipe laid at depths of 17 to 30 feet shall have minimum wall thickness as covered by S.D.R. - 26. Sewer services shall be 6" Polyvinyl chloride pipe (PVC) S.D.R. - 26 (heavy wall). All riser pipe shall be 6" Polyvinyl chloride pipe (PVC) S.D.R. - 26 (heavy wall). Bedding shall be Class B. SPU – 10 WPS REVISION: FEBRUARY, 2007 2621.4 METHOD OF MEASUREMENT A. Sewer Pipe All sewer pipe will be measured based on horizontal distance unless the slope of the pipe exceeds 15%. The depth of cut for payment shall be defined as the distance between the invert of the pipe at a particular point and the intersection of the vertical or plumb line, extended from the set point to the point of intersection of the line with the ground surface as it exists at the time of construction. B. Manholes According to the unit listed on the proposal form. Depths will be measured from the rim elevation to the invert. C. Catch Basins According to the unit listed on the proposal form. Depths will be measured from the rim elevation to the invert. 2621.5 BASIS OF PAYMENT 1. Connect to Existing Sanitary Sewer Manhole In cases where a short sanitary pipe stub out of a manhole exists, the CONTRACTOR will be required to remove the existing stub and connect the new pipe to the connection provided as directed by the ENGINEER. Connect to Existing Manhole shall be paid for at the Contract Unit Price bid per each. A removable plug shall be installed when connecting to any existing sanitary sewer MH. The plug shall be inflated to the manufactures recommended PSI to prevent discharge into the existing sanitary sewer. The plug shall remain in place until directed by the engineer for removal. 2. Connect to Existing Sanitary Sewer Where a connection to an existing sanitary sewer line is required, the CONTRACTOR shall remove the existing plug, verify the invert elevation and alignment of the existing pipe and connect the new pipe as directed by the ENGINEER. Removal of plugs and verification shall be considered to be incidental to the connection. Connect to Existing Sanitary Sewer shall be paid for at the Contract Unit Price bid for each. 3 Connect to Existing Storm Sewer Manhole Where a connection to an existing storm sewer manhole is required, the CONTRACTOR shall knock out the wall of the manhole and connect the new pipe to the existing manhole. Also, the CONTRACTOR shall grout the new connection and reconstruct and grout the invert to provide for smooth flow. Any grouting and reconstructing shall be considered to be incidental to the connection. Connect to Existing Storm Sewer Manhole shall be paid for at the Contract Unit Price bid per each. SPU – 11 WPS REVISION: FEBRUARY, 2007 4 Connect to Existing Storm Sewer Where a connection to an existing storm sewer line is required, the CONTRACTOR shall remove the existing plug or bulkhead, verify the invert elevation and alignment of the existing pipe and connect the new pipe as directed by the ENGINEER. Removal of plugs/bulkheads and verification shall be considered to be incidental to the connection. Connect to Existing Storm Sewer shall be paid for at the Contract Unit Price bid per each. 5 Drop Section For Manholes Type A: The drop section with the tee for drop manholes shall consist of a DIP tee, concrete base, pipe supports and concrete collar and will be paid for at the Contract Unit Price for each unit. Type B: The drop section without the tee for drop manholes shall consist of a DIP elbow, DIP plug, concrete base and pipe support and will be paid for at the Contract Unit Price bid per each unit. 6 Risers for Drop Manholes The risers for drop manholes consist of DIP including pipe support and will be paid for at the Contract Unit Price per lineal foot. The length of riser shall be computed as distance from the tee invert to the spring line of the lowest pipe entering the manhole less one foot (1.0'). 7 Connection to Existing Drop Sections A connection to an existing drop section shall consist of completing a Type B drop section, as covered under section 5 above, by coring into the existing manhole and furnishing a tee completely installed and will be paid for at the Contract Unit Price per each unit. 8 Core Existing Sanitary Sewer Manhole In cases where an additional invert/pipe is to be installed in an existing sanitary manhole, the CONTRACTOR will be required to core the existing manhole with the correct size and install a rubber "O" ring or profile joint with a gasketed, flexible, watertight connection or approved equal. Also, the CONTRACTOR will be required to reconstruct and re-grout the invert to provide for smooth flow. Payment for Core Existing Sanitary Sewer Manhole shall be incidental to the Contract Unit price per "Connect to Existing Sanitary Sewer Manhole". 9 Trench stabilization material shall be measured and paid for by the Contract Unit Price per ton based upon scale receipts furnished to the ENGINEER. Payment for trench stabilization material shall include the extra depth of excavation and all materials, labor and equipment required to place the material. Payment for trench stabilization materials shall not SPU – 12 WPS REVISION: FEBRUARY, 2007 be made when it is used for the CONTRACTOR's convenience or for de- watering purposes. Only material authorized by the ENGINEER shall be paid for. 10 The cost of all materials and labor required to complete this project, as specified and shown on the plans, but not specifically included as a paid item, shall be merged with the various unit prices bid. 11 Sanitary service riser pipe will be paid for based upon vertical length from the invert of the PVC main to the invert of the 45 degree bend at the point where a 2% grade starts. Additional bends required for riser construction will not be paid for and are considered incidental. SPH-1 WPS REVISION: FEBRUARY, 2007 SPECIAL PROVISIONS TO THE STANDARD HIGHWAY SPECIFICATIONS SCOPE OF WORK This Contract shall consist of the furnishing of all labor, equipment and all else necessary to complete the project in accordance with the plans and specifications. The work shall include, but not be limited to: subgrade preparation, aggregate base, curb and gutter, paving, and restoration, together with all appurtenant items in the proposed The Preserve at Bluff Creek 6th Addition, located in Chanhassen, Minnesota. Unless otherwise noted or modified herein, all sections of the General Conditions shall apply. 1. SPECIFICATIONS WHICH APPLY Specifications which apply to construction of street work as shown in the plans shall be Division II (Construction Details) and Division III (Materials) of the "Standard Specification for Construction", Minnesota Department of Transportation, August 31, 2005 and current revisions, and the City of Chanhassen Specifications to the extent that they are modified by these special provisions. 2. STAKING Staking for parking areas and streets provided by the ENGINEER shall be as follows: Street Centerline (1 set) - 50' centers (after utility construction) for subgrade verification - Staking will occur just prior to the placement of select granular Curb and Gutter (1 set) - Alignment and grade stakes 3' offset (or as appropriate) - Every 50’ on tangent and 25’ on curve, plus additional stakes at curb returns - Driveway cuts as needed for construction - WPS will require the CONTRACTOR to have a minimum of 1 days work available on all survey requests. 3. PROTECTION AND ADJUSTMENT OF EXISTING UTILITY CASTINGS The CONTRACTOR shall be responsible for the protection of and damage to all utilities including, but not limited to public gas mains, telephone lines, electric power lines, cable television, water valve boxes, manholes and catch basins. He shall also be responsible for cleaning, repairing or replacement of same if damaged in this phase of construction. 4. BARRIERS The CONTRACTOR shall furnish and place sufficient barricades and warning lights at the terminals of all construction to prevent use of the right-of-way during construction operations, except that access to private development shall be maintained. SPH-2 WPS REVISION: FEBRUARY, 2007 5. MAINTENANCE OF TRAFFIC Sufficient flag men and warning signs shall be employed on streets which abut the project area to warn and control traffic during all hauling and construction activity. The CONTRACTOR shall maintain all roadways either on or off the project area which are used for haul roads. Such maintenance shall consist of blading and dust control determined necessary by the ENGINEER in order to keep the roads suitable for automobile traffic and to control dust. Beginning on a date as established by written notification to the CONTRACTOR from the ENGINEER, said date to be on or after the formal execution of the contract, the CONTRACTOR shall be responsible for all maintenance of streets and roads that are a part of this contract. This maintenance responsibility shall include whatever work is necessary to keep the streets in a condition suitable for local access traffic, and shall generally consist of periodic blading, sweeping, and dust control procedures until surfacing has been completed. All traffic control shall be in accordance with the Minnesota Temporary Traffic Control Zone Layouts Field Manual, the Minnesota Flagging Handbook, and the Minnesota Manual on Uniform Traffic Control Devices for Streets and Highways. 6. MISCELLANEOUS REMOVALS AND REPLACEMENT The temporary removal, storage and replacement of street signs, traffic control signs, mailboxes, fences, and miscellaneous items shall be performed by the CONTRACTOR and they shall be considered incidental to the project as a whole, with no direct payment therefore. 7. EXCAVATION AND EMBANKMENT (2105) All rough grading will be completed under a separate contract and will not be a part of this work. Excavation for the installation of pipe and the preparation of curb and gutter is considered incidental to the unit item as bid. 8. SUBGRADE PREPARATION (P) Subgrade preparation shall include the work necessary to prepare the subgrade material for the laying of base material and grading for curb and gutter construction. This work will include grade variation corrections of up to 4 inches plus or minus. It shall also include scarifying the upper 12 inches, disc drying, or applying water to obtain a subgrade compacted to a minimum of 100% of standard proctor dry density. The basis of payment for this work shall be by the Contract Unit Price per square yard and shall be computed on the basis of planned dimensions using base area measured to 3.5 feet behind the back of curb. Should the only work performed include getting the street to grade without any drying effort, (scarifying and disk drying), payment for this item will be based on 50% of the Contract Unit Price per square yard as listed earlier in this section. The subgrade shall be rolled with a smooth drum roller prior to the placement of any base material. Equipment at hourly rate items as shown in the bid proposal shall be paid only as authorized by the ENGINEER for subgrade correction and grading work required beyond the scope of subgrade preparation as specified above. The CONTRACTOR shall notify the ENGINEER and receive notice to proceed prior to making any claim for such work. SPH-3 WPS REVISION: FEBRUARY, 2007 9. TEST ROLLING Prior to placement of the aggregate base, the OWNER will require the completion of a test roll on the street subgrade. The CONTRACTOR shall provide a loaded tandem axle truck with a minimum gross weight of 25 tons. The CONTRACTOR shall provide a weight ticket for the test roll vehicle to the ENGINEER during the test roll. The test rolling shall be at the direction of the ENGINEER and in the presence of the Soils ENGINEER. The OWNER may require test rolling of the aggregate base, once the base section has been constructed. Test rolling will be considered to be incidental work and no direct compensation will be made therefore. Additional test rolling required as a result of repairs to unstable sections and retesting will be considered to be incidental work and no direct compensation will be made therefore. The CONTRACTOR will be required to use every means available to provide a stable subgrade prior to the placement of Class 5 aggregate. The CONTRACTOR may be required to work material with a blade and disc below the upper 12" of subgrade material (as required under Subgrade Preparation) to a point 3'-0" below subgrade elevation to ensure a stable subgrade. This work shall be paid for at the equipment hourly rates as provided in the contract, but in no means shall be used unless specifically directed by the ENGINEER. 10. 3" MINUS CRUSHED QUARRY ROCK STABILIZING AGGREGATE When authorized by the ENGINEER, the CONTRACTOR shall complete subgrade correction with the placement of 3" minus crushed quarry rock stabilizing aggregate. 3" minus crushed quarry rock stabilizing aggregate will be used to stabilize subgrade areas which fail the test rolling procedure, but only after the CONTRACTOR has completed subgrade preparation work, inclusive of scarifying, disc drying and recompacting of the upper 12 inches of the subgrade to a minimum of 100% of standard proctor dry density to the satisfaction of the engineer. The basis of measurement and payment for this work shall be by the Contract Unit Price per ton, based upon scale receipts furnished to the ENGINEER. Payment for 3" minus crushed quarry rock stabilizing aggregate shall include the excavation and proper disposal of the failing subgrade material and all materials, labor and equipment required to place the stabilizing aggregate. Only material authorized by the ENGINEER shall be paid for and the CONTRACTOR must agree in writing with the ENGINEER or his representative prior to the work being performed. 11 SAND SUBBASE (3149 Select Granular) (P) Sand subbase shall be constructed to the depth shown on the plans and in accordance with Section 3149. Compaction shall be to a minimum of 100% of standard proctor dry density. Measurement and payment shall be by the Contract Unit Price per square yard at a compacted volume and shall be computed on the basis of planned dimensions. Shaping and compacting the sand sub base shall be incidental to the cost of the sand sub base. 12. AGGREGATE BASE (2211) (P) Class 5 (100% crushed stone) aggregate base shall be constructed to the depth shown on the plans and in accordance with Section 2211. SPH-4 WPS REVISION: FEBRUARY, 2007 Compaction shall be by the Specified Density Method and shall conform to the requirements of Section 2211. Measurement and Payment shall be by the Contract Unit Price per square yard of the minimum depth specified and shall be computed on the basis of planned dimensions using base area measured to 1.5 feet behind the back of curb. Any requests by the ENGINEER for different lift thickness not included in the proposal shall be prorated using 110 pounds per square yard of area per inch of thickness from the thinnest lift described in the Contract. Shaping and compacting the aggregate base shall be incidental to the cost of the aggregate. 13. PLANT MIXED BITUMINOUS PAVEMENT (2360) (P) Base Course 2350 Type LVNW35030B Wear Course 2350 Type LVWE35030B The plant-mixed bituminous pavement shall be constructed in accordance with the provisions of Mn/DOT Specifications 2360, except as modified: The CONTRACTOR shall submit to the ENGINEER an approved mix design for all types a Minimum of 7 days prior to placement of bituminous pavement. No additional compensation shall be made for bituminous material. Recycled mixtures will not be allowed to be used in the wear course. Recycled mixtures used in the base course shall be in accordance with the provisions of Mn/DOT specifications 2360. Compaction shall be in accordance with Mn/DOT 2360.6 Maximum Density Method. Required minimum density as determined by Nuclear Density Testing shall be 91.0% on base courses and 92.0% on wear courses of the design Marshall. Mn/DOT Specification 2360.6-B4 Payment Schedule for Maximum Density shall be deleted. Failure of the CONTRACTOR to attain minimum density shall result in the removal and replacement of the pavement as determined by the ENGINEER. No additional compensation shall be made for pavement removed and replaced due to density failures. Measurement and payment shall be by the Contract Unit Price per square yard of the minimum compacted thickness specified for each course and shall be computed on the basis of planned dimensions. Payment shall include compensation for the bituminous material for mixture, for which no separate payment will be made. No additional compensation will be granted for additional bituminous due to deficiencies in base thickness. 14. BITUMINOUS TACK COAT (2357) (P) Bituminous Tack Coat shall be used between all courses of bituminous pavement constructed by the CONTRACTOR. Tack material shall be RC 250 or RC 70. Payment for bituminous tack coat shall be by the Contract Unit Price per gallon applied at a rate of 0.05 gallons per yard of pavement. SPH-5 WPS REVISION: FEBRUARY, 2007 15. ADJUST MANHOLES, CATCH BASINS, and GATE VALVES Manholes and gate valves adjustments shall be in accordance with the provisions of MN/DOT 2506 except as modified below: The CONTRACTOR shall adjust all manhole and gate valve castings to 0.5 inches below bituminous base grade to provide interim access to all structures for the first season. Final adjustment shall be made to 0.5 inches below finished pavement grade prior to paving the final wear course. Measurement and payment of adjustments shall by the Contract Unit Price per each manhole or gate valve casting in a paved area adjusted, as provided on the proposal, only after the final adjustment. Upon request, the ENGINEER may pay 1/2 the contract amount after the first raising. The turning of Mexican hats, cones or slabs to align with curb and gutter, if necessary, shall be incidental to the contract. 16. CONCRETE SIDEWALK (2521) This work shall be done in accordance with Mn/DOT 2521 Concrete Mix No.3A32 for hand placed formed walk and Concrete Mix No. 3A22 for slip machine placed walk with a 28 day design strength of 3900 PSI. The sidewalk shall be of the dimensions and at the location shown on the plans. This shall include all labor, material and equipment necessary to rough grade; place the granular base; place, finish and cure the concrete and backfill along the edges of the sidewalk. The material excavated to place the base section and sidewalk shall become the property of the CONTRACTOR. If the material can not be used on site it will be hauled off the site by the CONTRACTOR at no cost to the OWNER. Edges of the sidewalk are to be backfilled within five (5) working days of the sidewalk placement. Winter protection shall be required and maintained for a minimum of 72 hours if temperatures are at or below freezing or as defined by the ENGINEER. Payment will be at the Contract Unit Price per linear foot of width specified in the plans. 17. BITUMINOUS TRAIL (2360) Bituminous trail shall be constructed at the location shown on the plans or as directed by the ENGINEER. Work under this pay item will include grading; aggregate base (conforming to Mn/DOT 2211); bituminous pavement (conforming to Mn/DOT 2360) and backfilling of the trail edges. The bituminous mixture shall be 2360 SPWEB340B. Edges of the trail are to be backfilled within five (5) working days of the trail placement. Payment will be at the contract unit price for Bituminous Trail as measured by the lineal foot that includes a 6” Class 5 aggregate base. 18. PEDESTRIAN RAMPS (2531) Pedestrian ramps shall placed at the location and be of the dimensions shown on the plan. Pedestrian ramps shall be constructed in accordance with Mn/Dot Standard Plate No.7036F and compliant with the ADDAG (Americans with Disabilities Act Accessibility Guidelines). Payment for pedestrian ramps shall be by the each and shall include all labor, material and equipment necessary to rough grade; place the granular base; install Truncated Domes; place, finish and cure the concrete. The material excavated to place the base section and pedestrian ramp(s) shall become the property of the CONTRACTOR. If the material can not be used on site it will be hauled off the site by the CONTRACTOR at no cost to the OWNER. SPH-6 WPS REVISION: FEBRUARY, 2007 19. CONCRETE CURB AND GUTTER (2531) Concrete curb and gutter shall be constructed in accordance with the provisions of 2531 Concrete Mix No. 3A22 with 28 day design strength of 3900 PSI except as modified herein: Concrete curb and gutter type shall be as noted on the plans. Place the expansion joints at intervals of 120 feet and at the ends of all street returns. Joint sealing as specified in Mn/DOT 2531.3H will not be required. The City of Chanhassen requires rebar reinforcement as defined in the plan details. All reinforcement shall be considered as incidental to the Contract Unit Price. Cure concrete using the membrane method. Apply membrane to all exposed surfaces, including formed surfaces. Apply membrane in two lateral directions at the rate of one gallon per 150 square feet. Apply membrane to the back of curb and face of gutter as soon as forms are stripped, or after final brushing. The compound must contain a fugitive dye. A double layer of polyethylene (with insulation between the layers) shall be required and maintained for a minimum of 72 hours if temperatures are at or below freezing or as defined by the ENGINEER. The Contract Unit Price will include complete installation, removal, clean up, and disposal of the double layer of polyethylene (with insulation). Excavation and grading for curb construction shall be incidental to curb and gutter. Project cleanup shall include backfill to back of curb and fine grading of all disturbed areas. The cost of this work is to be incidental to the price bid per foot of curb and gutter. Partial payment will not be made on curb and gutter until backfilling is completed. Measurement and payment shall be by the Contract Unit Price per lineal foot of each type of curb and gutter constructed and shall include the B618 used as radii and dropping back of the curb for pedestrian ramps. The CONTRACTOR shall submit a current test from an approved testing laboratory indicating that the materials of the concrete supplier meet the requirement of the Mn/DOT Specifications. 20. REMOVE/REPLACE BROKEN CONCRETE CURB AND GUTTER This is a budget item and shall only be used with the approval of the Engineer. It shall include the cost of saw cutting, removing of the curb and gutter, and the off site disposal of the broken or damaged curb and gutter. Compensation will only be granted for curb and gutter damaged due to home builder traffic. This item shall also include patching of the bituminous base course to match back into the replaced curb and gutter as well as turf restoration if required. No compensation will be made due to settlement or defects in construction materials or process. Payment will be by the contract unit per linear foot. 21. REMOVE/REPLACE BROKEN CONCRETE SIDEWALK This is a budget item and shall only be used with the approval of the Engineer. It shall include the cost of removing the sidewalk, and the offsite disposal of the broken or damaged sidewalk. Compensation will only be granted for sidewalk damaged due to home builder traffic. This item shall also include turf restoration if required. No compensation will be made due to settlement or defects in construction materials or process. Payment will be by the contract unit per linear foot. SPH-7 WPS REVISION: FEBRUARY, 2007 21. INSTALL TRAFFIC BARRICADES Traffic Barricades shall be at the location shown on the plans and be in conformance with Mn/DOT Detail M8002G (Totally Closed Roadway- No Turns Permitted). Payment will be at the Contract Unit Price for each installation and will include all labor, equipment and material necessary for a complete installation. The barricade shall be reflectorized on both sides for safety. 22. STREET CLEANING FOR WEAR COURSE INSTALLATION On all streets where binder and/or wearing courses are to be placed over existing bituminous surface, the existing surface shall be properly swept to the satisfaction of the ENGINEER, immediately prior to the placement of the tack coat and bituminous course(s). All sweeping operations and disposals of the sweepings shall be the responsibility of the CONTRACTOR. The sweeping shall be performed with a self-propelled pickup sweeper (w/water). A side-throw sweeper will not be allowed. Payment for street cleaning shall be paid for at the Contract Unit Price per lump sum and shall include all equipment, labor and material costs incurred to properly clean the base course prior to the installation of binder and/or wear course, including the proper disposal of the sweepings. 23. PATCHING PRIOR TO INSTALLATION OF BITUMINOUS WEAR COURSE Prior to the installation of Bituminous Wear Course all areas of failed bituminous base, aggregate base and settlements shall be repaired by the CONTRACTOR. Settlements (if they do not show bituminous or aggregate base failure) shall be repaired by the addition of a leveling patch of bituminous base material or by removing bituminous base, adding compacted aggregate base and reinstalling the required bituminous base. Patching of settlements shall be the responsibility of the CONTRACTOR and no extra compensation will be allowed therefore. Areas which show evidence of bituminous base failure or bituminous base and aggregate base failure shall be repaired by the removal of the failed bituminous base or bituminous base and aggregate base. All such patch areas shall have square cut edges in the bituminous base. The removed materials shall be disposed of off site at a disposal site of the CONTRACTOR’S choice. The cost of bituminous base or bituminous base and aggregate base repair shall be borne by the CONTRACTOR except in those areas as designated by the ENGINEER to have been caused by use exceeding normal wear and tear and use beyond the control of the CONTRACTOR. Payment for such ENGINEER authorized exceptional bituminous base or bituminous base and aggregate base repair shall be by the Contract Unit Price per square yard and shall be payment in full for all costs of labor, materials, equipment and all else necessary to remove, dispose of removed materials off site, and replace and compact the required thickness of bituminous base or bituminous and aggregate base including any necessary edge tacking material. 24. UTILITY CROSSINGS Payment will be based on a per trench basis and not a per conduit basis. The Contract Unit Price for each crossing shall include the excavation for conduit placement and the backfilling of the trench after conduit placement. Trench compaction shall meet the requirements of the Subgrade Preparation specifications in this document. It will be the responsibility of the CONTRACTOR to coordinate the SPH-8 WPS REVISION: FEBRUARY, 2007 conduit installation with the utility company. Coordination should be performed in a timely manner as not to cause delay in the street construction. Conduit will be provided by the utility companies. 25. TOLERANCES Tolerances for the streets shall be plus or minus 0.05’ for the subgrade, top of the select granular, and the top of Class 5 and/or Class 7. Section 7.0 Soil Report & Borings Section 8.0 CEAM Specifications i STANDARD SPECIFICATIONS FOR TRENCH EXCAVATION AND BACKFILL/SURFACE RESTORATION WATER MAIN AND SERVICE LINE INSTALLATION SANITARY SEWER AND STORM SEWER INSTALLATION PUBLISHED BY CITY ENGINEERS ASSOCIATION OF MINNESOTA 1999 EDITION TABLE OF CONTENTS SECTION 2600 TRENCH EXCAVATION & BACKFILL/SURFACE RESTORATION 2600.1 Description......................................................................................................… 1 2600.2 Materials............................................................................................................. 1 A Granular Materials.............................................................................................. 1 A1 Granular Material Gradation Classifications.....................................................1 A2 Granular Material Use Designations................................................................. 2 B Piling....................................................................................................….......…. 2 C Insulation................................................................................................….......... 2 D Geotextile Fabric....................................................................................…..........3 2600.3 Construction Requirements..................................................................................3 A General Provisions.................................................................................... .......... 3 A1 Maintenance of Traffic................................................................................…3 A2 Establishing Line and Grade.......................................................................... 3 A3 Protection of Surface Structures................................................................…. 5 A4 Interference of Underground Structures......................................................…5 A5 Removal of Surface Improvements............................................................... 6 A6 Temporary Service Measures..............................................................…...... 7 B Excavation and Preparation of Trench..................................................................7 B1 Operational Limitations and Requirements.....................................................7 B2 Classification and Disposition of Materials....................................................8 B3 Excavation Limitations and Requirements..................................................…9 B4 Sheeting and Bracing Excavations ......................................................…...….9 B5 Preparation and Maintenance of Foundations..................................…..........10 C Non Open Cut Pipe Installation.....................................................….................. 12 C1 Jacking/Boring..........................................................................…................. 12 C2 Directional Boring.......................................................................….............. 13 ii D Placement of Insulation........................................................................…........... 13 E Pipeline Backfilling Operations.......................................................................... 14 F Restoration of Surface Improvements................................................................. 16 F1 Turf Restoration ..............................................................................…...........16 F2 Pavement Restoration................................…............................................….17 F3 Restoration of Miscellaneous Items ......................................................…....17 G Maintenance and Final Cleanup ....................................................................…..18 2600.4 Method of Measurement A Rock Excavation .................................................................................…............18 B Granular Materials ............................................................................…...….......18 C Geotextile Fabric .................................................................................…........... 19 D Piling ..................................................................................................…............ 19 D1 PileBents........................................................................................…........…19 E Insulation...............................................................................................….......…19 2600.5 Basis of Payment .......................................................................................….....19 SECTION 2611 WATERMAIN AND SERVICE LINE INSTALLATION 2611.1 Description....................................................................................................…. 20 2611.2 Materials ...............................................................................................….….....22 A Water Pipe Materials ....................................................................................…......23 A1 Ductile Iron Pipe and Ductile Iron and Gray Iron Fittings .....................…......23 A2 Prestressed Concrete Cylinder Pipe and Fittings ....................................…......23 A3 Polyvinyl Chloride (PVC) Pressure Pipe and Fittings ......................................23 A4 Polyethylene (PE) Pressure Pipe and Fittings ...................................................24 B Fire Hydrants ..............................................................................................….........24 C Valves and Valve Housings .......................................................................….........25 C1 Valve Housings ..................................................................................…...........25 C2 Gate Valves.........................................................................................…...........25 C3 Butterfly Valves ..................................................................................…..........26 D Water Service Pipe and Fittings ................................................................….........26 E Polyethylene Encasement Material ........................................................................ 27 F Restrained Joint Retainer Glands ........................................................................... 27 G Mortar .........................................................................................................…...... 27 H Concrete .....................................................................................................…........ 27 2611.3 Construction Requirements .....................................................................…........28 A Installation of Pipe and Fittings .............................................................................. 28 A1 Inspection and Handling .............................................................…...................28 A2 Pipe Laying Operations ................................................................…....….........29 A3 Aligning and Fitting of Pipe ..................................................................…........29 iii A4 Blocking and Anchoring of Pipe ...........................................................…........ 30 A5 Polyethylene Encasement of Pipeline....................................................….........31 B Connection and Assembly of Joints ..........................................................…...........32 B1 Ductile Iron Pressure Pipe and Fitting Joints ......................................…...........33 B1a Push-On Joints ..............................................................................……........33 B1b Mechanical Joints ..................................................................…...................33 B1c Flanged Joints ...........................................................................…................33 B2 Prestressed Concrete Cylinder Pipe Joints.........................................…............ 34 B3 Polyvinyl Chloride Pipe Joints ...................................................……..…..........34 B3a Push-On Joints ............................................................................……..........34 B4 Polyethylene Pipe Joints ..................................................................…..............34 C Water Service Installations ............................................................…......................34 C1 Tee Branch Service Lines ........................................................…........…..........35 C2 Tapped Service Lines ...............................................................….........….........35 D Setting Valves, Hydrants, Fittings and Specials ............................…......................36 E Disinfection of Water Mains ..........................................................…..................... 37 F Electrical Conductivity Test ...........................................................…..................... 37 G Hydrostatic Testing of Water Mains ..............................................….....................38 H Operational Inspection ....................................................................….......….........39 2611.4 Method of Measurement ..........................................................…............…........39 A Water Pipe .......................................................................................….........….......40 B Valves .............................................................................................….............…....40 C Corporation Stops ...........................................................................….…............…40 D Curb Stops .......................................................................................…...….........…40 E Hydrants ...........................................................................................…........…....…40 F Air Vents ..........................................................................................…........…....…40 G Rearrangement of Inplace Facilities .............................................................…...…40 H Polyethylene Encasement .............................................................................…...…40 I Ductile and Gray Iron Fittings .......................................................................…....…41 J Polyvinyl Chloride or Polyethylene ...............................................................…..….41 K Access Structures ........................................................................….............…....…41 2611.5 Basis of Payment ..................................................................…...............….....…41 SECTION 2621 SANITARY SEWER AND STORM SEWER INSTALLATION 2621.1 Description........................................................................................................... 43 2621.2 Materials...............................................................................................................44 A Sewer Pipe and Service Line Materials ...................................................................45 A1 Vitrified Clay Pipe and Fittings .........................................................................45 A2 Ductile Iron Pipe and Ductile Iron and Gray Iron and Fittings .........................46 A3 Reinforced Concrete Pipe and Fittings ..............................................................46 iv A4 Corrugated Steel Pipe and Fittings ................................................................... 46 A5 Polyvinyl Chloride Pipe and Fittings .................................................................47 A6 Cast Iron Soil Pipe .............................................................................................47 A7 Acrylonitrile-Butadiene-Styrene Pipe ................................................................47 A8 Dual-Wall Corrugated Polyethylene Pipe ......................................................... 47 B Metal Sewer Castings ...............................................................................................47 C Precast Concrete Manhole and Catch Basin ............................................................ 48 D Concrete ..................…............................................................................................ 49 E Mortar ....................…................................................................................................49 2621.3 Construction Requirements ..................................................................................49 A Installation of Pipe and Fittings ................................................................................49 A1 Inspection and Handling .....................................................................................49 A2 Pipe Laying Operations ......................................................................................50 A3 Connection and Assembly of Joints ...................................................................51 A4 Bulkheading Open Pipe Ends ............................................................................ 51 B Appurtenance Installations ....................................................................................... 52 C Sewer Service Installations ...................................................................................... 52 D Manhole and Catch Basin Structures .......................................................................53 E Reconnecting Existing Facilities ..............................................................................54 F Sanitary Sewer Leakage Testing .............................................................................. 54 F1 Air Test Method ................................................................................................. 55 F2 Hydrostatic Test Method .................................................................................... 57 F3 Test Failure and Remedy ....................................................................................57 G Deflection Test .........................................................................................................58 G1 Test Failure and Remedy ...................................................................................58 H Televising ................................................................................................................ 58 2621.4 Method of Measurement ......................................................................................58 A Sewer Pipe ....................................................................................................….......59 B Manholes ......................................................................................................…........59 C Catch Basins ................................................................................................….........59 D Outside Drop Connection .........................................................................................59 E Service Connection ...................................................................................................60 F Service Pipe ...............................................................................................…............60 G Special Pipe Fittings .................................................................................................60 H Appurtenant Items .....................................................................................…...........60 2621.5 Basis of Payment .......................................................................................….......60 SECTION 2600 TRENCH EXCAVATION AND BACKFILL/SURFACE RESTORATION 1 2600 STANDARD SPECIFICATIONS FOR TRENCH EXCAVATION & BACKFILL/SURFACE RESTORATION 2600.1 DESCRIPTION This work shall consist of the excavation, backfilling, and restoration of existing surface improvements for the purposes of installing new and/or relocating or adjusting existing underground utilities. Use of the term "Plans, Specifications and Special Provisions" within this specification shall be construed to mean those documents which compliment, modify, or clarify these specifications and are accepted as an enforceable component of the Contract or Contract Documents. All references to Mn/DOT Specifications shall mean the latest published edition of the Minnesota Department of Transportation Standard Specifications for Construction, as modified by any Mn/DOT Supplemental Specification edition published prior to the date of advertisement for bids. All reference to other Specifications of AASHTO, ASTM, ANSI, AWWA, etc. shall mean the latest published edition available on the date of advertisement for bids. 2600.2 MATERIALS A. Granular Materials Granular materials furnished for foundation, bedding, encasement, backfill, or other purposes as may be specified shall consist of any natural or synthetic mineral aggregate such as sand, gravel, crushed rock, crushed stone, or slag, that shall be so graded as to meet the gradation requirements specified herein for each particular use by the material manufacturer or as indicated in the Plans, Specifications, or Special Provisions.. A1. Granular Material Gradation Classifications Granular materials furnished for use in Foundation, Bedding, Encasement, or Backfill construction shall conform to the following requirements: Foundation materials shall have 100 percent by weight passing the 1-1/2 inch sieve and a maximum of 10 percent by weight passing the No. 4 sieve. Backfill materials shall consist of existing trench materials, except as otherwise specified in this specification or in the Special Provisions. Bedding and encasement materials for flexible pipe, where improved pipe foundation is not required, shall meet the requirements of Mn/DOT Specification 3149.2B1, Granular Borrow, except that 100 percent by weight shall pass the one-inch sieve. 2 A gradation report from an approved Independent Testing laboratory of the proposed granular materials shall be furnished to the Engineer before any of the granular materials are delivered to the project. A2. Granular Material Use Designations Granular materials provided for Foundation, Bedding, Encasement, or Backfill use as required by the Plans, Specifications, and Special Provisions, either as part of the pipe item work unit or as a separate contract item, shall be classified as to use in accordance with the following: Material Use Designation Zone Designation Granular Foundation ------------- Placed below the bottom of pipe grade as replacement for unsuitable or unstable soils, to achieve better foundation support. Granular Bedding ---------------- Placed below the pipe midpoint, prior to pipe installation, to facilitate proper shaping and to achieve uniform pipe support. Granular Encasement ----------- Placed below an elevation one foot above the top of pipe, after pipe installation, for protection of the pipe and to assure proper filling of voids or thorough consolidation of backfill. Granular Backfill ----------------- Placed below the surface base course, if any, as the second stage of backfill, to minimize trench settlement and provide support for surface improvements. In each case above, unless otherwise indicated, the lower limits of any particular zone shall be the top surface of the next lower course as constructed. The upper limits of each zone are established to define variable needs for material gradation and compaction or void content, taking into consideration the sequence of construction and other conditions. The material use and zone designations described above shall only serve to fulfill the objectives and shall not be construed to restrict the use of any particular material in other zones where the gradation requirements are met. B. Piling Piling shall be constructed in accordance with the provisions of Mn/DOT Specification 2452 and special plan details relating to piling. C. Insulation Main Insulation shall be extruded rigid board material having a thermal conductivity of 0.23 BTU/hour/square foot/degree Fahrenheit/per inch thickness, maximum, at 40âF mean, a comprehensive strength of 35 psi minimum, and water absorption of 0.25 percent by volume minimum. Unless otherwise specified in the Plans, specifications, or Special Provisions, board dimensions shall measure 8 feet long, 2 or 4 feet wide, and 1, 1-1/2, 2, or 3 inches thick. 3 D. Geotextile Fabric Geotextile fabric shall meet the requirements of Mn/DOT Specification 3733 and be used as required by the Plans, Specifications, and Special Provisions. 2600.3 CONSTRUCTION REQUIREMENTS A. General Provisions A1. Maintenance of Traffic Whenever work interferes with the flow of traffic along a roadway, the Contractor shall provide for traffic control and signing and public safety in accordance with the provisions of the field manual of Temporary Control Zone Layouts of the Minnesota Manual of Uniform Traffic Control Devices and Mn/DOT Specifications 1404 and 1710, and the Special Provisions. Neither road closures nor detours shall be permitted unless specified in the Special Provisions or authorized by the Engineer. Where road closures or detours are permitted by the Engineer, the Engineer shall determine the appropriate agencies, boards, or departments the Contractor must notify prior to taking the action and the proper advance notice to be provided to each body. Compliance with this requirement shall not be construed to relieve the Contractor from the responsibility of notifying agencies or institutions whose services may be predicated upon a roadway being opened to traffic or whose services would be hindered if a roadway is closed to traffic. Such agencies or institutions shall include, but not be limited to, the police department, the fire department, municipal bus service, school bus service, and ambulance service. The Contractor shall keep the required agencies informed of changing traffic patterns and detour situations. A2. Establishing Line and Grade The primary line and grade will be established by the Engineer. For trench installation, line and grade stakes will be set parallel to the proposed pipeline at an appropriate offset therefrom as will best serve the Contractor's operations wherever practical. For tunnel installation, line and grade stakes will be set directly above the proposed pipeline setting. Grade and line stakes will be set at 25-foot intervals along the pipeline; at each change in line or grade; and as needed for pipeline appurtenances and service lines. The Contractor shall arrange operations to avoid unnecessary interference with the establishment of the primary line and grade stakes; and shall render whatever assistance may be required by the Engineer in accomplishing the staking. The Contractor shall be responsible for preservation of the primary stakes and, if negligent in providing necessary protection, shall bear the full cost of any restaking. The Contractor shall be solely responsible for the correct transfer of the primary line and grade to all working points and for construction of the work to the prescribed lines and 4 grades as established by the Engineer. Following construction of a work shaft on tunnel installations, the line and grade shall be transferred down the shaft and be projected into and throughout the length of each tunnel heading. Unless otherwise specified in the Plans, Specifications, and Special Provisions, the water main shall generally be placed with the minimum specified cover. However, a greater depth may be required to clear existing storm and sanitary sewers and sewer services, and no additional compensation shall be provided for such adjustments. In locations where sewer is in direct conflict with existing water main and water services the water main and water services shall be lowered to provide at least 18 inches of vertical distance between the top of the water main or service and the bottom of the sanitary or relocated in accordance with the Plans. Water mains crossing above storm or sanitary sewers shall be laid to provide a separation of at least18 inches between the bottom of the water main and the top of the sewer. When local conditions prevent a vertical separation as described, the following construction shall be used: (1) Sewers passing over or under Water mains shall be constructed of materials equal to water main standards of construction for a distance of at least 9 feet on either side of the water main. (2) Watermain passing under sewers shall, in addition, be protected by providing: (a) a vertical separation of at least 18 inches between the bottom of the sewer and the top of the water main; (b) adequate structural support for the sewers to prevent excessive deflection of joints and settling on and breaking of the Water mains; (c) a length of water pipe shall be centered at the point of crossing so that the joints will be equidistant and as far as possible from the sewer. Water mains shall be laid at least 10 feet horizontally from any sanitary sewer or storm sewer, whenever possible. When local conditions prevent a horizontal separation of 10 feet, a water main may be laid closer to a storm or sanitary sewer provided that: (1) The bottom of the water main is at least 18 inches above the top of the sewer; (2) Where this vertical separation cannot be obtained, the sewer shall be constructed of materials and with joints that are equivalent to water main standards of construction and shall be pressure tested to assure water tightness prior to backfilling. No deviation shall be made from the required line or grade except with the consent of the Engineer. 5 A3. Protection of Surface Structures All surface structures and features located outside the permissible excavation limits for underground installations, together with those within the construction areas which are indicated in the Plans as being saved, shall be properly protected against damage and shall not be disturbed or removed without approval of the Engineer. Within the construction limits, as required, the removal of improvements such as paving, curbing, walks, turf, etc., shall be subject to acceptable replacement after completion of underground work, with all expense of removal and replacement being borne by the Contractor to the extent that separate compensation is not specifically provided for in the Contract. Obstructions such as street signs, guard posts, small culverts, mailboxes, and other items of prefabricated construction may be temporarily removed during construction provided that essential service is maintained in a relocated setting as approved by the Engineer and that nonessential items are properly stored for the duration of construction. Upon completion of the underground work, all such items shall be replaced in their proper setting at the sole expense of the Contractor. The Contractor shall be responsible for protection of existing overhead utilities and poles. This shall include arranging with the utility and paying the utility for holding poles that will be close to the edge of any trench. Holding of poles and repair of any damage to these facilities shall be considered incidental to the project with no additional compensation allowed. If relocation or removal of these facilities is required, the Owner will contact the concerned utility and pay for the relocation or removal at no additional expense to the Contractor. In the event of damage to any surface improvements, either privately or publicly owned, in the absence of construction necessity, the Contractor will be required to replace or repair the damaged property to the satisfaction of the Engineer and without cost to the Owner. A4. Interference of Underground Structures When any underground structure interferes with the planned placement of the pipeline or appurtenances to such an extent that alterations in the work are necessary to eliminate the conflict or avoid endangering effects on either the existing or proposed facilities, the Contractor shall immediately notify the Engineer and the Owner of the affected structure. When any existing facilities are endangered by the Contractor's operations, the Contractor shall cease work at the site and take such precautions as may be necessary to protect the inplace structures until a decision is made as to how the conflict will be resolved. Without specific authorization from the Engineer, no essential utility service shall be disrupted, nor shall any change be made in either the existing structures or the planned installations to overcome the interference. Alterations in existing facilities will be 6 allowed only to the extent that service will not be curtailed unavoidably and then only when the encroachment or relocation will satisfy all applicable regulations and conditions. Wherever alterations are required as a result of unforeseen underground interferences not due to any fault or negligence of the Contractor, the Engineer will issue a written order covering any additional or extra work involved and specifying the revised basis of payment, if any. Any alterations made strictly for the convenience of the Contractor, shall be subject to prior approval and shall be at the Contractor's expense. No extra compensation will be allowed for delays caused by the interference of underground structures. A5. Removal of Surface Improvements Removal of surface improvements in connection with trench excavation shall be limited to actual needs for installation of the pipeline and appurtenances, based on the allowable trench widths and any other controls imposed in connection with the work. Removal operations shall be coordinated effectively with the excavation and installation operations as will cause the least practical disruption of traffic or inconvenience to the public. The debris resulting from removals shall become the property of the Contractor and shall be disposed of by the Contractor in accordance with Mn/DOT Specification 2104. Removal debris shall not be deposited at locations that will block access to fire hydrants, private driveways, or other essential service areas, nor obstruct surface drainage. Removal and final disposal of debris shall be accomplished as a single operation wherever possible and, in any event, the debris shall be removed from the site before starting the excavating operations. Removal of concrete or bituminous structures shall be by methods producing clean-cut breakage to prescored lines as will preserve the remaining structure without damage. Removal equipment shall not be operated in a manner that will cause damage to the remaining structure or adjoining property. Where not removed to an existing joint, concrete structures shall be sawed along the break lines to a minimum depth of one-third of the structure depth. Any reusable materials generated during the work, such as aggregate, sod, topsoil, shall be segregated from other waste materials and be stockpiled so as to maintain suitability and permit proper reuse. The use of drop weight equipment for breaking pavement will be allowed to the extent that the Contractor shall assume full responsibility for any damages caused thereby. The pavement breaking operation shall not be allowed to become a nuisance to the public or a source of damage to underground or adjacent structures. The Engineer reserves the right to order discontinuance of drop weight breaking operations at any time. 7 A6. Temporary Service Measures While any open excavations are maintained, the Contractor shall have available a supply of steel plates suitable for temporary bridging of open trench sections where either vehicular or pedestrian traffic must be maintained. Use of the plates shall be as directed or approved by the Engineer and where installed they shall be secured against possible displacement and be replaced with the permanent structure as soon as possible. B. Excavation and Preparation of Trench B1. Operational Limitations and Requirements Excavating operations shall proceed only so far in advance of pipe laying as will satisfy the needs for coordination of work and permit advance verification of unobstructed line and grade as planned. Where interference with existing structures is possible or in any way indicated, and where necessary to establish elevation or direction for connections to inplace structures, the excavating shall be done at those locations in advance of the main operation so actual conditions will be exposed in sufficient time to make adjustments without resorting to extra work or unnecessary delay. Where possible, excavated materials shall be placed in areas that will not block existing vehicle and pedestrian traffic and drainage ways. The Contractor shall review proposed methods of operation with the Engineer prior to beginning the work. All installations shall be accomplished by open trench construction except for short tunnel sections approved by the Engineer and with the exception that boring and jacking or tunnel construction methods shall be employed where so specifically required by the Plans, Specifications, or Special Provisions. Installation of pipe through tunnel excavations will be allowed only where the surface structure can be properly supported and the backfill restored to the satisfaction of the Engineer. The excavating operations shall be conducted so as to carefully expose all inplace underground structures without damage. Wherever the excavation extends under or approaches so close to an existing structure as to endanger it in any way, precautions and protective measures shall be taken as necessary to preserve the structure and provide temporary support. Hand methods of excavating shall be utilized to probe for and expose such critical or hazardous installations as gas pipe and power or communication cables. The Engineer shall be notified of any need for blasting to remove materials which cannot be broken up mechanically, and there shall be no blasting operations conducted until the Engineer's approval has been secured. Blasting will be allowed only when proper precautions are taken to protect life and property, and then shall be restricted as the Engineer directs. The hours of blasting operations shall be set by the Owner. The Contractor shall assume full responsibility for any damages caused by blasting, regardless 8 of the requirements for notification and approval. The Contractor shall secure any required permits for blasting and shall conduct blasting operations in conformance with all applicable local, state and federal laws, regulations, and ordinances. B2. Classification and Disposition of Materials Excavated materials will be classified for payment only to the extent that the removal of materials classified by the Engineer as Rock will be paid for as provided in the Special Provisions or shown in the Proposal. All other materials encountered in the excavations, with the exception of items classified for payment as structure removals, will be considered as Unclassified Excavation and unless otherwise specified in the Plans, Specifications, and Special Provisions, no additional compensation shall be provided for their removal. Unclassified materials shall include muck, rubble, wood debris, and boulder stone, masonry or concrete fragments less than one cubic yard in volume, together with other miscellaneous matter that can be removed effectively with power operated excavators without resorting to drilling and blasting. Rock excavation shall be defined to include all hard, solid rock in ledge formation, bedded deposits and unstratified masses; all natural conglomerate deposits so firmly cemented as to present all the characteristics of solid rock; and any boulder stone, masonry or concrete fragments exceeding one cubic yard in volume. Materials such as shale, hard pan, soft or disintegrated rock which can be dislodged with a hand pick or removed with a power operated excavator will not be classified as Rock Excavation. Excavated materials will be classified for reuse as being either Suitable or Unsuitable for backfill or other specified use, subject to selective controls. All suitable materials shall be reserved for backfill to the extent needed, and any surplus remaining shall be utilized for other construction on the project as may be specified or ordered by the Engineer. To the extent practicable, granular materials and topsoil shall be segregated from other materials during the excavating and stockpiling operations so as to permit best use of the available materials at the time of backfilling. Unless otherwise specified in the Plans, Specifications, and Special Provisions, material handling as described above shall be considered incidental with no additional compensation provided. All excavated materials reserved for backfill or other use on the project shall be stored at locations approved by the Engineer that will cause a minimum of inconvenience to public travel, adjacent properties, and other special interests. The material shall not be deposited so close to the edges of the excavations as would create hazardous conditions, nor shall any material be placed so as to block the access to emergency services. All materials considered unsuitable by the Engineer, for any use on the project, shall be immediately removed from the project and be disposed of as arranged for by the Contractor at no extra cost to the Contract. 9 B3. Excavation Limitations and Requirements Trench excavating shall be to a depth that will permit preparation of the foundation as specified and installation of the pipeline and appurtenances at the prescribed line and grade, except where alterations are specifically authorized. Trench widths shall be sufficient to permit the pipe to be laid and joined properly and the backfill to be placed and compacted as specified. Extra width shall be provided as necessary to permit convenient placement of sheeting and shoring and to accommodate placement of appurtenances. Excavations shall be extended below the bottom of structure as necessary to accommodate any required Granular Foundation material. When rock or unstable foundation materials are encountered at the established grade, additional materials shall be removed as specified or ordered by the Engineer to produce an acceptable foundation. Unless otherwise indicated or directed, rock shall be removed to an elevation at least six inches below the bottom surface of the pipe barrel and below the lowest projection of joint hubs. All excavations below grade shall be to a minimum width equal to the outside pipe diameter plus two feet. Rock shall be removed to such additional horizontal dimensions as will provide a minimum clearance of six inches on all sides of appurtenant structures such as valves, housings, access structures, etc. Where no other grade controls are indicated or established for the pipeline, the excavating and foundation preparations shall be such as to provide a minimum cover over the top of the pipe as specified. Trench widths shall allow for at least six inches of clearance on each side of the joint hubs. The maximum allowable width of the trench at the top of pipe level shall be the outside diameter of the pipe plus two feet, subject to the considerations for alternate pipe loading set forth below. The width of the trench at the ground surface shall be held to a minimum to prevent unnecessary destruction of the surface structures. The maximum allowable trench width at the level of the top of pipe may be exceeded only by approval of the Engineer, after consideration of pipe strength and loading relationships. Any alternate proposals made by the Contractor shall be in writing, giving the pertinent soil weight data and proposed pipe strength alternate, at least seven days prior to the desired date of decision. Approval of alternate pipe designs shall be with the understanding that there will be no extra compensation allowed for any increase in material or construction costs. If the trench is excavated to a greater width than that authorized, the Engineer may direct the Contractor to provide a higher class of bedding and/or a higher strength pipe than that required by the Plans, Specifications, and Special Provisions in order to satisfy design requirements, without additional compensation. B4. Sheeting and Bracing Excavations All excavations shall be sheeted, shored, and braced as will meet all requirements of the applicable safety codes and regulations; comply with any specific requirements of the 10 Contract; and prevent disturbance or settlement of adjacent surfaces, foundations, structures, utilities, and other properties. Any damage to the work under contract or to adjacent structures or property caused by settlement, water or earth pressures, slides, cave-ins, or other causes due to failure or lack of sheeting, shoring, or bracing or through negligence or fault of the Contractor in any manner shall be repaired at the Contractor's expense and without delay. Where conditions warrant extreme care, the Plans, Specifications, and Special Provisions may require special precautions to protect life or property, or the Engineer may order the installation of sheet piling of the interlocking type or direct that other safety measures be taken as deemed necessary. Failure of the Engineer to order correction of improper or inadequate sheeting, shoring, or bracing shall not relieve the Contractor's responsibilities for protection of life, property, and the work. The Contractor shall assume full responsibility for proper and adequate placement of sheeting, shoring, and bracing, wherever and to such depths that soil stability may dictate the need for support to prevent displacement. Bracing shall be so arranged as to provide ample working space and so as not to place stress or strain on the inplace structures to any extent that may cause damage. Sheeting, shoring and bracing materials shall be removed only when and in such manner as will assure adequate protection of the inplace structures and prevent displacement of supported grounds. Sheeting and bracing shall be left in place only as required by the Plans, Specifications, and Special Provisions or ordered by the Engineer. Otherwise, sheeting and bracing may be removed as the backfilling reaches the level of respective support. Wherever sheeting and bracing is left in place, the upper portions shall be cut and removed to an elevation of three feet or more below the established surface grade as the Engineer may direct. All costs of furnishing, placing and removing sheeting, shoring, and bracing materials, including the value of materials left in place as required by the Contract, shall be included in the prices bid for pipe installation and will not be compensated for separately. When any sheeting, shoring, or bracing materials are left in place by written order of the Engineer, in the absence of specific requirements of the Contract to do so, payment will be made for those materials as an Extra Work item, including waste material resulting from upper cut-off requirements. B5. Preparation and Maintenance of Foundations Foundation preparations shall be conducted as necessary to produce a stable foundation and provide continuous and uniform pipe bearing between bell holes. The initial excavating or backfilling operations shall produce a subgrade level slightly above finished grade as will permit hand shaping to finished grade by trimming of high spots and without the need for filling of low spots to grade. Final subgrade preparations shall be such as to produce a finished grade at the centerline of the pipe that is within 0.03 foot 11 of a straight line between pipe joints and to provide bell hole excavation at each joint as will permit proper joining of pipe and fittings. In excavations made below grade to remove rock or unstable materials, the backfilling to grade shall be made with available suitable materials unless placement of Granular Foundation or Bedding material is specified and provided for or is ordered by the Engineer. Placement of the backfill shall be in relatively uniform layers not exceeding 8 inches in loose thickness. Each layer of backfill shall be compacted thoroughly, by means of approved mechanical compaction equipment, as will produce uniform pipe support throughout the full pipe length and facilitate proper shaping of the pipe bed. Where placement of foundation materials will not provide an adequate foundation for laying pipe due to the instability of the existing materials and where ordered by the Engineer, the Contractor shall place Geotextile Type I fabric on top of the unstable materials prior to placing foundation materials. Sufficient geotextile fabric shall be used to completely enclose the foundation materials and pipe. It shall be the Contractor's responsibility to notify the Engineer of changing soil conditions which may be of poor bearing capacity and when organic soils are encountered. Where utilities are placed on unstable soils without notification of the Engineer, the Contractor shall be responsible for all repairs and correction of the installation without further compensation. Where the foundation soil is found to consist of materials that the Engineer considers to be so unstable as to preclude removal and replacement to a reasonable depth to achieve solid support, a suitable foundation shall be constructed as the Engineer directs in the absence of special requirements in the Plans, Specifications, and Special Provisions. The Contractor may be required to furnish and drive piling and construct concrete or timber bearing supports or other work as may be ordered by the Engineer. Care shall be taken during final subgrade shaping to prevent any over-excavation. Should any low spots develop, they shall only be filled with approved material, which shall have optimum moisture content and be compacted thoroughly without additional compensation to the Contractor. The finished subgrade shall be maintained free of water and shall not be disturbed during pipe lowering operations except as necessary to remove pipe slings. The discharge of trench dewatering pumps shall be directed to natural drainage channels or storm water drains. Draining trench water into sanitary sewers or combined sewers will not be permitted. The Contractor shall install and operate a dewatering system of wells or points to maintain pipe trenches free of water wherever necessary or as directed by the Engineer to meet the intent of these specifications. Unless otherwise specified in the Plans, Specifications, and Special Provisions, such work shall be considered incidental. All costs of excavating below grade and placing foundation or bedding aggregates as required shall be included in the bid prices for pipe items to the extent that the need for 12 such work is indicated in the Contract provisions and the Proposal does not provide for payment under separate Contract Items. Any excavation below grade and any foundation or bedding aggregates required by order of the Engineer in the absence of Contract requirements will be compensated for separately. If examination by the Engineer reveals that the need for placement of foundation aggregate was caused by the Contractor's manipulation of the soils in the presence of excessive moisture or lack of proper dewatering, the cost of the corrective measures shall be borne by the Contractor. C. Non-Open Cut Pipe Installation C1. Jacking/Boring The terms "auger", "boring", "jack", "jacking", and "tunneling" in the proposal, specifications, and plans refers only to non-open cut construction. The Contractor shall inspect and verify soil conditions to his own satisfaction in order to determine the type of construction to employ. During the construction, the Contractor shall be responsible for protecting all existing utilities above the pipe invert. The minimum diameter of the casing pipe shall be four (4) inches greater than the outside diameter of the bell of the carrier pipe. For any installation beneath a railroad, the top of the casing pipe shall not be closer than the specified dimensions indicated in the permit. If the Contractor elects to install steel casing, the minimum wall thickness shall be as specified on the Plans, in the Special Provisions, or in the applicable Permit. Where required by the Engineer, two 17-pound anode packs shall be attached to the casing for corrosion protection. A 1-1/2 inch pipe shall be forced along the top of the casing pipe. The front end of this pipe shall be 18 inches behind the front end of the casing pipe. A mixture of water and bentonite clay shall be forced through this pipe at all times during the casing installation to fill any voids that may be present above the casing pipe. Upon completion of the casing installation, this pipe shall be slowly withdrawn while bentonite is forced through the pipe to fill any remaining voids. The Contractor shall prevent excavated materials from flowing back into the excavation during the non-open cut construction. This shall include the use of a shield conforming to the size and shape of the casing that will prevent materials from flowing into the leading edge of the casing. The machine used shall be capable of controlling line and grade and shall conform to the size and shape of the casing pipe. No jacking/augering of pipe will be allowed below the water table unless the water table has been lowered sufficiently to keep the water below the pipe being installed. The use of water under pressure (jetting) or puddling will not be permitted to facilitate jacking/augering operations. 13 If any installation is augered, the head shall be approved by the Engineer and the auger shall be located six (6) inches behind the lead edge of the casing or carrier pipe. If a void develops, the jacking/augering shall be stopped immediately and the void shall be filled by pressure grouting. The grout material shall consist of a sand-cement slurry of at least two sacks of cement per cubic yard and a minimum of water to assure satisfactory placement. Skids and blocking shall be used as necessary to install the carrier pipe to the proper line and grade inside the casing pipe. Voids between carrier and casing pipes shall be filled with sand and the casing pipe sealed at both ends with a suitable material to prevent water or debris from entering the casing pipe. C2. Directional Boring Direction boring/drilling installation shall be accomplished where required on the Plans or in the Special Provisions to minimize disturbance of existing surface improvements. The installer shall have a minimum of three years of experience in this method of construction and have installed at least 1,000 feet of 8-inch or larger diameter pipe to specified grades. The field supervisor employed by the Contractor shall have at least three years of experience and shall be at the site at all times during the boring/drilling installation, and be responsible for all of the work. The Contractor shall submit boring/drilling pit locations to the Engineer before beginning construction. The drilling equipment shall be capable of placing the pipe as shown on the plans. The installation shall be by a steerable drilling tool capable of installing continuous runs of pipe, without intermediate pits, a minimum distance of 200 feet. The guidance system shall be capable of installing pipe within 1-1/2 inch of the plan vertical dimensions and 2 inches of the plan horizontal dimensions. The Contractor shall be required to remove and reinstall pipes which vary in depth and alignment from these tolerances. Pull back forces shall not exceed the allowable pulling forces for the pipe being installed. Drilling fluid shall be a mixture of water and bentonite clay. Disposal of excess fluid and spoils shall be the responsibility of the Contractor. D. Placement of Insulation Rigid insulation board shall be placed within the pipe encasement zone, 6 inches above the pipe. Prior to placement of the insulation, Granular Borrow (MnDOT 3149) shall be leveled and compacted until there is no further visual evidence of increased consolidation or the density of the compacted layer conforms to the density requirements specified in the Special Provisions, then leveled and lightly scarified to a depth of 1/2 inch. Borrow material placed above and below the insulation shall be free of rock or stone fragments measuring 1-1/2 inches or greater. 14 Insulation boards shall be placed on the scarified material with the long dimension parallel to the centerline of the pipe. Boards shall be placed in a single layer with tight joints. No continuous joints or seams shall be placed directly over the pipe. If two or more layers of insulation boards are used, each layer shall be placed to cover the joints of the layer immediately below. The Contractor shall exercise precaution to insure that all joints between boards are tight during placement and backfilling with only extruded ends placed end to end or edge to edge. The first layer of material placed over the insulation shall be 6 inches in depth, free of rock or stone fragments measuring 1-1/2 inches or greater. The material shall be placed in such a manner that construction equipment does not operate directly on the insulation and shall be compacted with equipment which exerts a contract pressure of less than 80 psi. The first layer shall be compacted to conform to the density requirements specified in the Special Provisions. E. Pipeline Backfilling Operations All pipeline excavations shall be backfilled to restore preexisting conditions as the minimum requirement, and fulfill all supplementary requirements indicated in the Plans, Specifications, and Special Provisions. The backfilling operations shall be started as soon as conditions will permit on each section of pipeline, so as to provide continuity in subsequent operations and restore normal public service as soon as practicable on a section-by-section basis. All operations shall be pursued diligently, with proper and adequate equipment, as will assure acceptable results. The backfilling shall be accomplished with the use of Suitable Materials selected from the excavated materials to the extent available and practical. Should the materials available within the trench section be unsuitable or insufficient, without loading and hauling or the employment of unreasonable measures, the required additional materials shall be furnished from outside sources as an Extra Work item in the absence of any Special Provision requirements. Suitable Material shall be defined as a mineral soil free of foreign materials (rubbish, debris, etc.), frozen clumps, oversize stone, rock, concrete or bituminous chunks, and other unsuitable materials, that may damage the pipe installation, prevent thorough compaction, or increase the risks of after settlement unnecessarily. Material selection shall be such as to make the best and fullest utilization of what is available, taking into consideration particular needs of different backfill zones. Material containing stone, rock, or chunks of any sort shall only be utilized where and to the extent there will be no detrimental effects. Within the pipe bedding and encasement zones described as that portion of the trench which is below an elevation one foot above the top of the pipe, the materials placed shall be limited in particle size to 1-1/2 inches maximum in the case of pipe of 12 inches in 15 diameter or less and to 2 inches maximum in the case of larger pipe. Above these zones, the placement of material containing stones, boulders, chunks, etc. greater than 8 inches in any dimension shall not be allowed. All flexible pipe shall be bedded in accordance with ASTM Specification D2321, "Recommended Practice for Underground Installation of Flexible Thermoplastic Sewer Pipe". This shall include placement of granular bedding and encasement materials from a point six inches below the bottom of pipe to a point twelve inches above the top of the pipe. Placement and compaction of bedding and encasement materials around the pipe shall be considered incidental to the installation of the pipe. Where existing soils do not meet the requirements of bedding and encasement materials, the Contractor shall furnish the required granular materials. Compaction of materials placed within the pipe bedding and encasement zones shall be accomplished with portable or hand equipment methods, so as to achieve thorough consolidation under and around the pipe and avoid damage to the pipe. Above the cover zone material, the use of heavy roller type compaction equipment shall be limited to safe pipe loading. Backfill materials shall be carefully placed in uniform loose thickness layers up to 12 inches thick spread over the full width and length of the trench section to provide simultaneous support on both sides of the pipeline. Granular backfill may be placed in 12 inch layers above an elevation one foot above the top of the pipe, and with the provision that, by authority and at the discretion of the Engineer in consideration of the demonstrated capability of special type vibrating compactors, the stated maximums may be increased. Each layer of backfill material shall be compacted effectively, by approved mechanical or hand methods, until there is no further visual evidence of increased consolidation or the density of the compacted layer conforms to the density requirements specified in the Special Provisions. Compaction of the inplace layer shall be completed acceptably before placing material for a succeeding layer thereon. The manner of placement, compaction equipment, or procedure effectiveness shall be subject to approval of the Engineer. All surplus or waste materials remaining after completion of the backfilling operations shall be disposed of in an acceptable manner within 24 hours after completing the backfill work on each particular pipeline section. Disposal at any location within the project limits shall be as specified, or as approved by the Engineer; otherwise, disposal shall be accomplished outside the project limits at the Contractor's discretion. The backfilling and surplus or waste disposal operations shall be a part of the work required under the pipeline installation items, not as work that may be delayed until final cleanup. Compaction of backfill within Roadbed areas shall meet the density requirements of Mn/DOT Specification 2105. Compaction of backfill in all other areas shall be as required in the Special Provisions. 16 Until expiration of the guarantee period, the Contractor shall assume full responsibility and expense for all backfill settlement and shall refill and restore the work as directed to maintain an acceptable surface condition, regardless of location. All additional materials required shall be furnished without additional cost to the Owner. Any settlement of road surfaces that are either placed under this Contract or by others under either public or private contract; that are in excess of one inch, as measured by a ten foot straight edge; and that are within the guarantee period shall be considered failure of the mechanical compaction. The Contractor shall be required to repair such settlement including all items placed by others. F. Restoration of Surface Improvements Wherever any surface improvements such as pavement, curbing, pedestrian walks, fencing, or turf have been removed, damaged or otherwise disturbed by the Contractor's operations, they shall be repaired or replaced to the Engineer's satisfaction, as will restore the improvement in kind and structure to the preexisting condition. Each item of restoration work shall be done as soon as practicable after completion of installation and backfilling operations on each section of pipeline. In the absence of specific payment provisions, as separate Contract Items, the restoration work shall be compensated for as part of the work required under those Contract Items which necessitated the destruction and replacement or repair, and there will be no separate payment. If separate pay items are provided for restoration work, only that portion of the repair or reconstruction which was necessitated by the Contract work will be measured for payment. Any improvements removed or damaged unnecessarily or undermined shall be replaced or repaired at the Contractor's expense. F1. Turf Restoration Turf restoration shall be accomplished by sod placement except where seeding is specifically allowed or required. Topsoil shall be placed to a minimum depth of four inches under all sod and in all areas seeded. The topsoil material used shall be light friable loam containing a liberal amount of humus and shall be free of heavy clay, coarse sand, stones, plants, roots, sticks and other foreign matter. Topsoil meeting these requirements shall be selected from the excavated materials to the extent available and needed. All turf establishment work shall be done in substantial compliance with the provisions of Mn/DOT Specification 2575 using seed mixtures as specified in the Special Provisions or Proposal. 17 F2. Pavement Restoration The inplace pavement structure (including base aggregates) shall be restored in kind and depth as previously existed, using base aggregates salvaged from the excavated materials to the extent available and needed, and with new materials being provided for reconstruction of the concrete or bituminous surface courses. If, through no fault of the Contractor in failing to reserve sufficient aggregate materials from the excavations, there should be insufficient quantity of suitable aggregate to reconstruct the pavement base courses, the additional materials required will be furnished by the Owner at its expense, or the Contractor will be ordered to furnish the additional materials from outside sources. Placement of any additional aggregate materials delivered to the site by the Owner or of any additional materials furnished by the Contractor shall be an incidental expense, as will also be the disposal of any excess materials resulting therefrom, unless special payment provisions are otherwise agreed upon. Reconstruction of aggregate base courses and concrete or bituminous surface courses shall be in substantial compliance with all applicable Mn/DOT Specifications pertaining to the item being restored. The materials used shall be comparable to those used in the inplace structure, and the workmanship and finished quality shall be equal to that of new construction to the fullest extent obtainable in consideration of operational restrictions. Existing concrete and bituminous surfaces at the trench wall shall be sawed or cut with a cutting wheel to form a neat edge in a straight line before surfaces are to be restored. Sawing or cutting may be accomplished as a part of the removal or prior to restoration at the option of the Contractor. However, all surface edges will be inspected prior to restoration. F3. Restoration of Miscellaneous Items Wherever any curbing, curb and gutter sections, pedestrian walks, fencing, driveway surfacing, or other improvements are removed or in any way damaged or undermined, they shall be restored to original condition by repair or replacement as the Engineer considers necessary. Replacement of old materials will be acceptable only to the extent that existing quality can be fully achieved, such as in the case of fencing. Otherwise new materials shall be provided and placed as the Engineer directs. Workmanship and finished quality shall be equal to that of new construction, where new materials are used, to the extent obtainable in consideration of operational restrictions. A proper foundation shall be prepared before reconstructing concrete or bituminous improvements. Unless otherwise directed, granular material shall be placed to a depth of at least four inches under all concrete and bituminous items. No direct compensation will be made for furnishing and placing this material even though such course was not part of the original construction. 18 G. Maintenance and Final Cleanup All subgrade surfaces shall be maintained acceptably until the start of surfacing construction or restoration work, and until the work has been finally accepted. Additional materials shall be provided and placed as needed to compensate for trench settlement and to serve as temporary construction pending completion of the final surface improvements. Final disposal of debris, waste materials, and other remains or consequences of construction, shall be accomplished intermittently as new construction items are completed and shall not be left to await final completion of all work. Cleanup operations shall be considered as being a part of the work covered under the Contract Items involved and only that work which cannot be accomplished at any early time shall be considered as final cleanup work not attributable to a specific Contract Item. If disposal operations and other cleanup work are not conducted properly as the construction progresses, the Engineer may withhold partial payments until such work is satisfactorily pursued or he may deduct the estimated cost of its performance from the partial estimate value. Maintenance of sodded and seeded areas shall include adequate watering for plant growth and the replacement of any dead or damaged sod as may be required for acceptance of the work. 2600.4 METHOD OF MEASUREMENT All items will be measured separately according to design designation as indicated in the Pay Item name and as may be detailed and defined in the Plans, Specifications, or Special Provisions. Complete-in-Place items shall include all component parts thereof as described or required to complete the unit, but excluding any excesses covered by separate Pay Items A. Rock Excavation Rock Excavation shall be measured by volume in cubic yards. Depth shall be measured from the top of the rock to a point six inches below the outside barrel of the pipe and width shall be the inside diameter of the pipe plus twenty-four inches (12" from each side). The minimum width of measurement shall be four feet. B. Granular Materials Granular materials furnished and placed as special foundation, bedding, encasement, or backfill construction will be measured by weight or volume of material furnished by the Contractor from outside sources and placed within the limits defined. Unless otherwise specified, volume will be determined by vehicular measure (loose volume) at the point of delivery. Measurements will not include any materials required to be placed as a component part of other Contract Items as may be specified. 19 C. Geotextile Fabric Where geotextile fabric is used for improving pipe foundation, it shall be measured by the square foot of material installed. D. Piling Piling shall be measured according to the provisions of Mn/DOT Specification 2452. D1. Pile Bents Pile bents shall be measured as a unit and shall include all materials and labor required, except the pile. E. Insulation Rigid board insulation shall be measured on a square foot basis installed to the specified thickness noted on the Plans, Specifications, and Special Provisions and shall include all materials, equipment, and labor required for placement. 2600.5 BASIS OF PAYMENT All costs of excavating to foundation grade, preparing the foundation, placing and compacting backfill materials, restoring surface improvements, and other work necessary for prosecution and completion of the work as specified, shall be included for payment as part of the pipe and pipe appurtenance items without any direct compensation being made. When special aggregate backfill materials are required to be furnished and placed to comply with the indicated Laying Conditions, the costs shall be included for payment as part of the pipe items without any direct compensation. Otherwise, the furnishing of aggregate materials for backfill by order of the Engineer in the absence of such requirements will be compensated for as an Extra Work item. In the absence of special payment provisions, all costs of restoring surface improvements as required, disposal of surplus or waste materials, maintenance and repair of completed work, and final cleanup operations shall be incidental to the Contract Items under which the costs are incurred. Granular materials furnished for foundation, bedding, cover, or backfill placement as specified in connection with pipe or structure items will only be paid for as separate Contract Items to the extent that the Proposal contains specific Pay Items. Otherwise the furnishing and placing of granular materials as specified shall be incidental to the pipe or structure item without any direct compensation being made. * * * END OF SECTION * * * SECTION 2611 WATERMAIN & SERVICE LINE INSTALLATION 20 2611 STANDARD SPECIFICATIONS FOR WATER MAIN AND SERVICE LINE INSTALLATION 2611.1 DESCRIPTION This work shall consist of the construction of water main and building service pipelines utilizing plant fabricated pipe and other appurtenant materials, installed for conveyance of potable water. The work includes the relocation or adjustment of existing facilities as may be specified in the Plans, Specifications and Special Provisions. Use of the term "Plans, Specifications and Special Provisions" within this specification shall be construed to mean those documents which compliment, modify, or clarify these specifications and are accepted as an enforceable component of the Contract or Contract Documents. All references to Mn/DOT Specifications shall mean the latest published edition of the Minnesota Department of Transportation Standard Specifications for Construction, as modified by any Mn/DOT Supplemental Specification edition published prior to the date of advertisement for bids. All reference to other Specifications of AASHTO, ASTM, ANSI, AWWA, etc. shall mean the latest published edition available on the date of advertisement for bids. The following American Water Works Association (AWWA) Specifications have been referenced in this Specification: C104 American National Standard for Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water C105 American National Standard for Polyethylene Encasement for Ductile-Iron Pipe Systems C110 American National Standard for Ductile-Iron and Gray-Iron Fittings, 3 In. Through 48 In. (75 mm Through 1200 mm), for Water and Other Liquids C111 American National Standard for Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings C115 American National Standard for Flanged Ductile-Iron Pipe With Ductile-Iron or Gray-Iron Threaded Flanges C150 American National Standard for Thickness Design of Ductile-Iron Pipe C151 American National Standard for Ductile-Iron Pipe, Centrifugally Case, for Water or Other Liquids 21 C153 American National Standard for Ductile-Iron Compact Fittings, 3 In. Through 24 In. (76 mm Through 610 mm) and 54 In. Through 64 In. (1,400 mm Through 1,600 mm), for Water Service C301 AWWA Standard for Prestressed Concrete Pressure Pipe, Steel-Cylinder Type, for Water and Other Liquids C304 AWWA Standard for Design of Prestressed Concrete Cylinder Pipe C500 AWWA Standard for Metal-Seated Gate Valves for Water Supply Service (Includes addendum C500a-95.) C502 AWWA Standard for Dry-Barrel Fire Hydrants (Includes addendum C502a-95.) C504 AWWA Standard for Rubber-Seated Butterfly Valves C509 AWWA Standard for Resilient-Seated Gate Valves for Water Supply Service (Includes addendum C509a-95.) C600 AWWA Standard for Installation of Ductile-Iron Water Mains and Their Appurtenances C605 AWWA Standard for Underground Installation of Polyvinyl Chloride (PVC) Pressure Pipe and Fittings for Water C651 AWWA Standard for Disinfecting Water Mains C800 AWWA Standard for Underground Service Line Valves and Fittings C900 AWWA Standard for Polyvinyl Chloride (PVC) Pressure Pipe, 4 In. Through 12 In., for Water Distribution (Includes addendum C900a-92.) C901 AWWA Standard for Polyethylene (PE) Pressure Pipe and Tubing, 1/2 In. Through 3 In., for Water Service C905 AWWA Standard for Polyvinyl Chloride (PVC) Pressure Pipe and Fabricated Fittings, 14 In. Through 48 In., (350mm Through 1,200mm), for Water Transmission and Distribution C906 AWWA Standard for Polyethylene (PE) Pressure Pipe and Fittings, 4 In. Through 63 In., for Water Distribution C907 AWWA Standard for Polyvinyl Chloride (PVC) Pressure Fittings for Water - 4 In. Through 8 In. (100mm Through 200mm) 22 Service installations shall include either Branch Service Lines or Tapped Service Lines in accordance with the standards set forth herein. Tapped Service installations shall include all water service lines less than three inches nominal inside diameter pipe. The component parts of a tap service installation shall include a corporation stop coupling complete with water main tap and saddle where required; a curb stop coupling complete with service box; and copper piping extending from the corporation stop to the curb stop coupling and beyond to the property line or to the limits as established by the Engineer. Tapped Service lines shall be installed at the size specified in the Plans, Specifications, and Special Provisions. Branch Service installations shall include all water service lines of three inches nominal inside diameter pipe and larger. The component parts of a branch service installation shall include a tapping sleeve and valve or a tee connection and valve complete with valve box, and piping extending from the water main connection, to the property line or to the limits as specified by the Engineer. All references to Gray Iron material shall be construed to include both Gray Iron and Ductile Iron products, except where one or the other is specified, and all references to Polyvinyl Chloride pipe shall be construed to include only pressure pipe complying with AWWA C-900 or C-905. All references to "structure" shall include any man-made object that is not otherwise exempted by special terminology or definition. 2611.2 MATERIALS All materials required for this work shall be new material conforming to requirements of the reference specifications for the class, kind, type, size, grade, and other details indicated in the Contract. Unless otherwise indicated, all required materials shall be furnished by the Contractor. If any options are provided for, as to type, grade, or design of the material, the choice shall be limited as may be stipulated in the Plans, Specifications, or Special Provisions. All manufactured products shall conform in detail to such standard design drawings as may be referenced or furnished in the Plans. Otherwise, the Owner may require advance approval of material suppliers, product design, or other unspecified details as it deems desirable for maintaining adopted standards. At the request of the Engineer, the Contractor shall submit, in writing, a list of materials and suppliers for approval. A Certificate of Compliance shall be furnished stating that the materials furnished have been tested and are in compliance with the specification requirements. 23 A. Water Pipe Materials All pipe furnished for water main and branch line installations shall be of the type, kind, size, and class indicated for each particular line segment as shown in the Plan and designated in the Contract Items. Wherever connection of dissimilar materials or designs is required, the method of joining and any special fittings employed shall be subject to approval of the Engineer. Al. Ductile Iron Pipe and Ductile Iron and Gray Iron Fittings The pipe furnished shall be Ductile Iron pipe fittings furnished shall be of the Ductile Iron or Gray Iron type as specified for each particular use of installation. When Gray Iron is specified, either type may be furnished. Gray Iron may not be substituted for Ductile Iron unless specifically authorized in the Special Provisions. Ductile iron pipe shall conform to the requirements of AWWA C115 or C151 for water and thickness design shall conform to AWWA C 150. In addition, the pipe shall comply with the following supplementary provisions: (1) Fittings shall conform to the requirements of AWWA C110 OR 153 (Gray Iron and Ductile Iron Fittings) (Ductile Iron Compact Fittings) for the joint type specified. (2) Unless otherwise specified all pipe and fittings shall be furnished with cement mortar lining meeting the requirements of AWWA C104 for standard thickness lining. All exterior surfaces of the pipe and fittings shall have an asphaltic coating at least one mil thick. Spotty or thin seal coating, or poor coating adhesion, shall be cause for rejection. (3) Rubber gasket joints for Ductile Iron Pressure Pipe and fittings shall conform to AWWA C111. A2. Prestressed Concrete Cylinder Pipe and Fittings Prestressed Concrete Cylinder pipe, fittings and specials shall conform to the requirements of AWWA C-301 and C-304 (Prestressed Concrete Pressure Pipe, Steel Cylinder Type) for the size, working pressure, external loading, laying condition, and other design considerations indicated in the Plans, Specifications, and Special Provisions. The Contractor shall furnish plans and specifications to the pipe manufacturer giving such special details and other information as are necessary for manufacture of the pipe, fittings, and specials in accordance with the specific requirements of the project. A3. Polyvinyl Chloride (PVC) Pressure Pipe and Fittings Polyvinyl chloride (PVC) pressure pipe, produced by a continuous extrusion process employing a prime grade of unplasticized polyvinyl chloride, shall conform to the requirements of AWWA C-900 for the size, grade, and pressure class indicated on the 24 Plans, Specifications, and Special Provisions. Fittings shall conform to AWWA C907 and C908. The grade used shall be resistant to aggressive soils or corrosive substances in accordance with the requirements of ASTM D-543. Unless otherwise specified, the dimensions and tolerances of the pipe barrel should conform to ductile iron or cast iron pipe equivalent outside diameters. A4. Polyethylene (PE) Pressure Pipe and Fittings Polyethylene pressure pipe and fittings shall conform to the requirements of AWWA C906 for the size and pressure class indicated on the Plans, Specifications and Special Provisions. Unless otherwise specified, the dimensions and tolerances of the pipe barrel should conform to Ductile Iron pipe equivalent outside diameters. The method of joining material shall be by the Thermal Butt- Fusion Method. The standard HDPE fittings shall be standard commercial products manufactured by injection molding or by extrusion and machining, or, shall be fabricated from PE pipe conforming to this specification. The fittings shall be fully pressure rated by the manufacturer to provide a working pressure equal to the pipe, for 50 years service at 73.4 degrees Fahrenheit with an included 2:1 safety factor. The fittings shall be manufactured from the same resin type, grade, and cell classification as the pipe itself. The manufacture of the fittings shall be in accordance with good commercial practice to provide fittings homogeneous throughout and free from crack, holes, foreign inclusions, voids, or other injurious defects. The fittings shall be as uniform as commercially practicable in color, opacity, density and other physical properties. The minimum "quick-burst" strength of the fittings shall not be less than that of the pipe with which the fitting is to be used. B. Fire Hydrants Fire hydrants shall be of the type, size, and construction specified in the Plans and shall conform to the applicable requirements of AWWA C-502. Unless otherwise specified in the Plans, Specifications, and Special Provisions, hydrants shall be furnished in conformance with the following supplementary requirements: (1) Hydrants shall have a five-inch (nominal diameter) main valve opening of the type that opens against water pressure. (2) Hydrant barrels shall be two piece, non-jacket type, with flanged joint above finished grade line and with mechanical joint connection at the hub end for joining a six-inch ductile iron branch pipe. (3) Hydrant bury length, measured from the bottom of the branch pipe connection to the finished ground line at the hydrant, shall be 7'-6". 25 (4) Hydrants shall have two outlet nozzles for 2-1/2 inch (I.D.) hose connection and one outlet nozzle for 4 inch (I.D.) steamer connection. All outlet nozzle threads shall be National Standard Fire-Hose Coupling Screw Threads (NFPA 1963). (5) Hydrant operating mechanisms shall be provided with "O" ring seals preventing entrance of moisture and shall be lubricated through an opening in the operating nut or bonnet. (6) Hydrants shall be provided with outlets for drainage in the base or barrel, or between the base and barrel, unless the Special Provisions require that drain outlets be omitted or plugged. (7) The hydrant operating nut shall be rotated counterclockwise to open. (8) Detailed drawings, catalog information, and maintenance data shall be furnished as requested by the Engineer. C. Valves and Valve Housing Cl. Valve Housings Valve housings shall be of ductile or cast iron, High Density Polyethylene or masonry construction as specified in the Plans, Specifications, and Special Provisions for the particular valve size or installation. Masonry manhole or vault type units shall be constructed in accordance with the provisions of Mn/DOT Specification 2506. Precast Concrete Manholes shall conform to ASTM Specification C-478 suitable for HS 20 traffic loading for all units located in driving areas. Ductile or cast iron valve boxes and all castings for manhole or vault type units shall conform to the requirements of Mn/DOT Specification 3321. C2. Gate Valves Gate Valves shall be manufactured and furnished in accordance with an approved pattern and shall conform to all applicable requirements of AWWA C-500 or AWWA C-509, together with such supplementary requirements as may be covered in the Plans, Specifications, and Special Provisions or the provisions hereof. Unless otherwise specified, the gate valves furnished shall comply with the following supplementary requirements: (1) Gate valves meeting the requirements of AWWA C-500 shall be two-faced, double disc type, with parallel seats. Gate valves meeting the requirements of AWWA C-509 shall be single disc type with resilient seat bonded or mechanically attached to either the gate or valve body. All valves shall be provided with a two-inch square operating nut opening counterclockwise and mechanical joint ends. (2) All gate valves shall be non-rising stem type furnished with O-Ring stem seals. 26 (3) All gate valves 16 inches or larger in size shall be arranged for operation in the horizontal position and shall be equipped with bypass valves. (4) All gate valves 12 inches or larger in size shall be equipped with approved barrel type rugged gate position. (5) All gears on gate valves shall be cut tooth steel gears, housed in heavy ductile or cast iron extended type grease cases of approved design. (6) All gate valves shall have an open indicating arrow, the manufacturer's name, pressure rating and year of manufacture cast on the valve bodies. C3. Butterfly Valves Butterfly valves shall be manufactured in conformance with all applicable requirements of AWWA C-504 for 150 p.s.i. working pressure minimum, together with such supplementary requirements as may be covered in the Plans, Specifications, and Special Provision or the provisions hereof. Unless otherwise specified, the butterfly valves furnished shall comply with the following supplementary requirements. (1) The butterfly valves shall be short body of ductile or cast iron with mechanical joint ends. (2) The butterfly valves shall be rubber seated with ductile or cast disc, non-rising stem type furnished with O-ring stem seals. (3) The butterfly valves shall be equipped with a two-inch square operating nut opening counterclockwise. (4) The butterfly valves shall be designed for direct burial installation. (5) All butterfly valves shall have an open indicating arrow, the manufacturer's name, pressure rating and year of manufacture on the valve bodies. D. Water Service Pipe and Fittings Water service pipe of 3 inches or larger inside diameter shall conform to the requirements for Ductile Iron Pipe and Ductile Iron and Gray Iron Fittings as set forth under the provisions of 2611.2A1, and Polyvinyl Chloride Pressure Pipe as set forth under the provisions of 2611.2A3, and Polyethylene pipe as set forth under the provision of 2611.2A4. Water service pipe of less than 3 inches in inside diameter shall conform to the requirements of ASTM B 88 for Seamless Copper Water Tube, Type K, Soft Annealed temper, Polyethylene Pipe as per AWWA C901 or Polyvinyl Chloride Pipe and fittings as 27 per a ASTM D1785, D2241, D2466, D2467 and D2740 as specified on the Proposal or in the Special Provisions. Corporation stops, saddles, curb stops, and curb stop service boxes shall conform to the requirements of AWWA C800 be as detailed in the Plans, Specifications, and Special Provisions or approved designations. All fittings for copper tubing shall be cast brass, having uniformity in wall thickness and strength, and shall be free of defects affecting serviceability. All copper pipe fittings shall be flared or compression type. All threads for underground service line fittings shall conform to the requirements of AWWA C-800. Each fitting shall be permanently and plainly marked with the name or trademark of the manufacturer. Curb stop service boxes shall be gray iron castings conforming to the requirements of ASTM A 48 for Class 20 or higher tensile strength and shall have 18 inches of vertical adjustment for the cover depth specified in the Plans, Specifications, and Special Provisions. E. Polyethylene Encasement Material Polyethylene encasement material shall conform to the requirements of AWWA C-105 for tube type installation and 8 mil nominal film thickness. F. Restrained Joint Retainer Glands Where water main joint restraint is required by the use of retainer glands, the retainer glands shall be American, US Pipe or Mega-Lug type, ductile iron, and be designed to withstand the design pressures indicated in the Plans, Specifications, and Special Provisions. All nuts, bolts, and tie rod type restraints shall be stainless steel or coated with an approved rustproofing material. G. Mortar Mortar for use in masonry construction shall be an air-entrained mixture of one part Masonry Cement (Type I) and two parts mortar sand, with sufficient water added to produce proper consistency, and with sufficient air-entraining agent added to maintain an air content within the range of 7 to 10 percent. Mortar shall meet the requirements of ASTM C270. H. Concrete Concrete for cast-in-place masonry construction shall be produced and furnished in accordance with the provisions of Mn/DOT Specification 2461 for the mix design indicated in the Plans, Specifications, or Special Provisions. The requirements for Grade 28 B concrete shall be met where a higher grade is not specified. Type 3, air-entrained, concrete shall be furnished and used in all structures having weather exposure. 2611.3 CONSTRUCTION REQUIREMENTS A. Installation of Pipe and Fittings Installation of ductile iron water mains and their appurtenances shall conform to the requirements of AWWA C-600 Specifications, the Plans, Specifications and Special Provisions. Prestressed concrete cylinder pipe and their appurtenances shall conform to the requirements of AWWA C301 and C304. The installation shall be to the bedding and backfill conditions specified in the Plans, Specifications, or Special Provisions. Installation of Polyvinyl Chloride (PVC) pipe and their appurtenances shall conform to the requirements of AWWA C900. The installation shall be to the bedding and backfill conditions specified by the Manufacturer, Plans, Specifications, or Special Provisions. Installation of Polyethylene Pipe and their appurtenances shall conform to the requirements of AWWA C906. The installation shall be to the bedding and backfill conditions specified by the Manufacturer, Plans, Specifications, or Special Provisions. Installation of pipe and fittings shall also conform to the following general guidelines: Al. Inspection and Handling Proper and adequate implements, tools, and facilities satisfactory to the Engineer shall be provided and used by the Contractor for the safe and convenient prosecution of the work. During the process of unloading, all pipe and accessories shall be inspected by the Contractor for damage. The Contractor shall notify the Engineer of all material found to have cracks, flaws or other defects. The Engineer shall inspect the damaged material and have the right to reject any materials found to be unsatisfactory. The Contractor shall promptly remove all rejected material from the site. All materials shall be handled carefully, as will prevent damage to protective coatings, linings, and joint fittings; preclude contamination of interior areas; and avoid jolting contact, dropping, or dumping. While suspended and before being lowered into laying position, each pipe section and appurtenant unit shall be inspected by the Contractor to detect damage or unsound conditions that may need corrective action or be cause for rejection. The Contractor shall inform the Engineer of any defects discovered and the Engineer will prescribe the required corrective actions or order rejection. 29 Immediately before placement, the joint surfaces of each pipe section and fitting shall be inspected for the presence of foreign matter, coating blisters, rough edges or projections, and any imperfections so detected shall be corrected by cleaning, trimming, or repair as needed. A2. Pipe Laying Operations Trench excavation and bedding preparations shall proceed ahead of pipe placement as will permit proper placement and joining of the pipe and fittings at the prescribed grade and alignment without unnecessary hindrance. All foreign matter or dirt shall be removed from the inside of the pipe and fittings before they are lowered into position in the trench, and they shall be kept clean by approved means during and after laying. The water main materials shall be carefully lowered into laying position by the use of suitable restraining devices. Under no circumstances shall the pipe be dropped or dumped into the trench. At the time of pipe placement, the bedding conditions shall be such as to provide uniform and continuous support for the pipe between bell holes. Bell holes shall be excavated as necessary to make the joint connections, but they shall be no larger than would be adequate to support the pipe throughout its length. No pipe material shall be laid in water nor when the trench or bedding conditions are otherwise unsuitable or improper. When placement or handling precautions prove inadequate, in the Engineer's opinion, the Contractor shall provide and install suitable plugs or caps effectively closing the open ends of each pipe section before it is lowered into laying position, and they shall remain so covered until removal is necessary for connection of an adjoining unit. As each length of bell and spigot pipe is placed in laying position, the spigot end shall be centered in the bell and the pipe forced home and brought to correct line and grade. The pipe shall be secured in place with approved backfill material, which shall be thoroughly compacted by tamping around the pipe to a height of at least 12 inches above its top. Acceptable tamping techniques include hand tamping and use of hand operated mechanical tamping devices. At all times when pipe laying is not in progress, including noon hour and overnight periods, all open ends of the pipe line shall be closed by watertight plugs or other means approved by the Engineer. If water is present in the trench, the seals shall remain inplace until the trench is pumped completely dry. When connecting to existing stubs, the Contractor shall take every precaution necessary to prevent dirt or debris from entering the existing lines. All necessary work to make the connection shall be done at no additional compensation, except where noted otherwise. A3. Aligning and Fitting of Pipe The cutting of pipe for inserting valves, fittings, or closure pieces shall be done in a neat and workmanlike manner without damage to the pipe and so as to leave a smooth square- 30 cut end. Pipe shall be cut with approved mechanical cutters. The electric-arc cutting method, using carbon or steel rod, will be approved for use on larger size ductile or gray pipe where mechanical cutters are not available. Flame cutting will not be allowed under any conditions. All rough edges shall be removed from the cut ends of pipe and, where rubber gasket joints are used, the outer edge shall be rounded or beveled by grinding or filing to produce a smooth fit. Wherever it is necessary to deflect ductile iron pipe from a straight line either in the vertical or horizontal plane, to avoid obstructions, plumb stems, or produce a long radius curve when permitted, the amount of deflection allowed at each joint shall not exceed the allowable limits for maintaining a satisfactory joint seal as given in AWWA C-600 for mechanical joints and push-on joints. The maximum angular deflection at any joint for other pipe materials and joints shall not exceed the manufacturer's recommendations. If the specified alignment requires angular deflections greater than recommended or allowed, the Contractor shall provide appropriate bends or shorter pipes such that the maximum angular deflection is not exceeded. Connection and assembly of joints shall be accomplished during the setting, aligning, and fitting operations, in accordance with the provisions of Section 2611.2D, to the extent that the jointing requirements will permit. A4. Blocking and Anchoring of Pipe All plugs, caps, tees, bends, and other thrust points shall be provided with reaction backing, or movement shall be prevented by attachment of suitable restraining devices or tie rods, in accordance with the requirements of the Plans, Specifications, and Special Provisions. In the absence of other specified requirements for reaction backing or restraining devices, the following provisions shall apply: (l) All horizontal bends exceeding 20 degrees deflection, and all caps, plugs, and branch tees shall be provided with concrete buttress blocking. (2) All vertical bends exceeding 20 degrees deflection shall be provided with concrete buttress blocking at the low points and with metal tie rod or strapping restraints at the high points. (3) Offset bends made with standard offset fittings need not be strapped or buttressed. Hardwood blocking shall only be used as temporary reaction backing until acceptable permanent reaction blocking or restraining devices have been installed. Blocking shall be nominal 2-inch timber having an area equivalent to at least four times the area of the surface of the cap or plug it restrains. 31 Concrete buttresses shall be poured against firm, undisturbed ground and shall be formed in such a way that the joints will be kept free of concrete and remain accessible for repairs. The concrete mix used in buttress construction shall meet the requirements for Grade B concrete in conformance with Mn/DOT Specification Section 2461. Buttress dimensions shall be a minimum of 12 inches in thickness, and the minimum area, in square feet shall be as follows. PIPE SIZE TEE OR PLUG 1/4 BEND 1/8 BEND 1/32 & 1/16 BENDS 6" 2.9 3.1 1.6 0.8 8" 3.7 5.3 2.9 1.4 10" 5.7 8.1 4.4 2.2 12" 8.1 13.4 6.6 3.2 16" 15.1 21.4 11.6 5.9 20" 23.2 30.2 18.1 9.3 24" 33.6 48.5 26.1 13.3 Contractors are instructed to size concrete buttress blocking on fittings and dead ends where the blocking must withstand the pressure of larger main line fittings equipped with reducers, for the larger sized main line thrust and not for smaller fitting size only. This is of particular importance on tees and crosses where the main size is reduced on the run from large to small size by use of reducers. All metal parts of tie rod or strap type restraints shall be galvanized or coated with other approved asphaltic type rustproofing. All necessary fittings, bands, tie rods, nuts, and washers, and all labor and excavation required for installation of reaction restraints shall be furnished at the Contractor's expense with no direct compensation provided therefore. A5. Polyethylene Encasement of Pipeline Wherever so required by the Plans, Specifications, or Special Provisions, the pipeline, including valves, fittings, and appurtenances, shall be fully encased in polyethylene film meeting the requirements of these Specifications. The film shall be furnished in tube form for installation on pipe and all pipe-shaped appurtenances such as bends, reducers, off- sets, etc. Sheet film shall be provided and used for encasing all odd-shaped appurtenances such as valves, tees, crosses, etc. 32 The polyethylene tubing shall be installed on the pipe prior to being lowered into the trench. Tubing length shall be sufficient to provide a minimum overlap at all joints of one foot or more. Overlap may be accomplished with a separate sleeve tube placed over one end of the pipe prior to connecting another section of pipe, or by bunching extra overlap material at the pipe ends in accordion fashion. After completing the pipe jointing and positioning the overlap material, the overlap shall be secured in place with plastic adhesive tape wrapped circumferentially around the pipe not less than three turns. After encasement, the circumferential slack in the tubing film shall be folded over at the top of the pipe to provide a snug fit along the barrel of the pipe. The fold shall be held in place with plastic adhesive tape applied at intervals of approximately three feet along the pipe length. Also, any rips, punctures, or other damage to the tubing shall be repaired as they are detected. These repairs shall be made with adhesive tape and overlapping patches cut from sheet or tubing material. At odd-shaped appurtenances such as gate valves, the tubing shall overlap the joint and be secured with tape, after which the appurtenant piece shall be wrapped with a flat film sheet or split length of tubing by passing the sheet under the appurtenance and bringing it up around the body. Seams shall be made by bringing the edges together, folding over twice, and taping down. Wherever encasement is terminated, it shall extend for at least two feet beyond the joint area. Openings in the tubing for branches, service taps, air valves and similar appurtenances shall be made by cutting an X-shaped slit and temporarily folding back the film. After installing the appurtenance, the cut tabs shall be secured with tape and the encasement shall be completed as necessary for an odd-shaped appurtenance. Unless otherwise specified in the Plans, Specifications, and Special Provisions, hydrants encased in polyethylene tubing shall have plugged drain outlets. B. Connection and Assembly of Joints Where rubber gasketed joints are specified, care shall be taken during the laying and setting of piping materials to insure that the units being joined have the same nominal dimension of the spigot outside diameter and the socket inside diameter. A special adaptor shall be provided to make the connection when variations in nominal dimension might cause unsatisfactory joint sealing. Immediately before making the connection, the inside of the bell or socket and the outer surface of the spigot ends shall be thoroughly cleaned to remove oil, grit, excess coating, and other foreign matter. Insertion of spigot ends into the socket or bell ends shall be accomplished in a manner that will assure proper centering and insertion to full depth. The joint seal and securing requirements shall be as prescribed below for the applicable pipe and joint type. 33 B1. Ductile Iron Pressure Pipe and Fitting Joints Ductile iron pressure pipe and fitting joints shall conform to AWWA C-111. B1a. Push-On Joints The circular rubber gasket shall be kept in a warm, flexible condition at all times, and for purposes of placement shall be flexed inward and inserted in the gasket recess of the bell socket. A thin film of approved gasket lubricant shall be applied to either the inside surface of the gasket or the outside surface of the spigot end, or to both. Care shall be taken while inserting the spigot end to prevent introduction of contaminants. The joint shall be completed by forcing the spigot end to the bottom of the socket by the use of suitable pry-bar or jack type equipment. Spigot ends which do not have depth marks shall be marked before assembly to insure full insertion. Field cut pipe shall be filed or ground at the spigot edge to resemble the manufacturer's fabricated detailing. The use of the bucket on the excavation equipment to force the pipe into the socket shall not be permitted. B1b. Mechanical Joints The last eight inches of the outside spigot surface and the inside bell surface of each pipe and appurtenance joint shall be painted with a soap solution, after being thoroughly cleaned. The gland shall then be slipped on the spigot end with the lip extension toward the socket or bell end. The rubber gasket shall be kept in a warm, flexible condition at all times, and for purposes of placement shall be painted with soap solution and be placed on the spigot end with the thick edge toward the gland. An approved lubricant provided by the pipe manufacturer may be used in lieu of the soap solution. After the spigot end is inserted into the socket to full depth and centered, the gasket shall be pressed into place within the bell evenly around the entire joint. After the gland is positioned behind the gasket, all bolts shall be installed and the nuts tightened alternately to the specified torque, such as to produce equal pressure on all parts of the gland. Unless otherwise specified, the bolts shall be tightened by means of a suitable torque- limiting wrench to within a foot-pound range of: 45 to 60 for 5/8 inch bolts; 75 to 90 for 3/4 inch bolts; 85 to 100 for 1 inch bolts; and 105 to 120 for 1-1/4 inch bolts. After tightening, all exposed parts of the bolts and nuts shall be completely coated with an approved asphaltic type rust preventive material. B1c. Flanged Joints Flanged joints shall be installed only in above grade or exposed locations and shall conform to the requirements of AWWA C115 Specifications, the Plans, Specifications and Special Provisions. Flanged joints shall have full face gaskets. 34 B2. Prestressed Concrete Cylinder Pipe Joints Unless otherwise indicated, all pipe and appurtenances shall be joined by means of the rubber gasketed bell and spigot connection in accordance with AWWA C301 or C304 and with the recommendations of the pipe manufacturer and the provisions hereof. All contact surfaces of the steel bell and spigot assembly shall be thoroughly lubricated with approved material before the connection is made. After the joint has been set in the home position, the outside joint recess shall be filled with cement grout, poured into place by means of a paper or cloth diaper. The grout shall contain at least one part Portland cement for each two parts of sand. Care shall be taken in pouring the grout to assure complete filling of the recess around the entire pipe circumference. B3. Polyvinyl Chloride Pipe Joints B3a. Push-On Joints The circular rubber gasket shall be bonded to the inner wall of the gasket recess of the bell socket. Installation of pipe spigot into the bell socket shall conform to the requirements for Ductile Iron Push-On Joints as set forth under the provisions of 2611.3B1a B4. Polyethylene Pipe Joints Polyethylene pipe joints shall conform to the requirements of AWWA C-906, and shall be made by the Thermal Butt-Fusion Method. C. Water Service Installations Water service facilities consisting of Tap Service Lines and Branch Service Lines, complete with all required appurtenances, shall be installed as required by in the Plans, Specifications, and Special Provisions, in accordance with all pertinent requirements for main line installations together with the provisions hereof. It shall be the responsibility of the Contractor to keep an accurate record of the location, depth and size of each service connection and other pertinent data such as the location of curb stops and pipe endings. Tap locations shall be recorded in reference to survey line stationing. Curb stops shall be tied to definable land marks such as building corners, lot corner markers, etc. Pipe terminals at the property line shall be marked to the ground surface with a suitable wood timber 4 by 4 inch, 8 feet long set vertically into the ground with the top 2 feet painted blue. Approved record keeping forms will be furnished by the Engineer and the completed records shall be submitted by the Contractor upon completion of the work. 35 Water service lines shall normally be installed by trenching and be subject to the same requirements as prescribed for the main pipeline installation, except for those which may not be pertinent or applicable. Where water service lines are installed alongside of sanitary service lines, installation shall be such as to maintain the minimum specified clearances between pipelines and provide proper and adequate bearing for all pipes and appurtenances. For separate installation, the trench width shall be not less than two feet. Subject to minimum clearances, the water lines may be laid in a common trench excavated principally for sewer installation, either by widening the trench as necessary or by providing a shelf in the trench wall where ground stability will permit. When water service pipe is placed in a common trench with sewer service pipe, the sewer service pipe shall be constructed of materials and with joints equivalent to water main standards. Water service lines shall be installed to provide for the specified cover over the top of the pipe and with not less than 18 inches of clearance between pipelines. A minimum 3 inches of clearance shall be maintained in crossing over or under other structures. Where the service pipe may be exposed to freezing due to insufficient cover or exposure from other underground structures, the water pipe shall be insulated as directed by the Engineer. C1. Tee Branch Service Lines Tee branch service piping shall be of the type, size, and wall thickness specified. The pipe and appurtenances shall have rubber gasketed push-on or mechanical joints. Tee branch service lines shall be provided as required by the Plans. Installation of tee branch service facilities shall be in accordance with all applicable requirements of these specifications as pertain to the mainline installations. C2. Tapped Service Lines Service piping shall be of the size and type specified. Unless otherwise specified, minimum pipe size for tap service installations shall be one inch nominal inside diameter. Larger size pipe may be specified for commercial and industrial uses or for some domestic service as specifically identified. Installation of service facilities shall be in accordance with all applicable requirements of these specifications as pertain to the mainline installations, subject to the exceptions and supplementary provisions set forth hereinafter. Unless otherwise indicated, service piping may be laid directly on any solid foundation soil that is free of stones and hard lumps. However, when specified or ordered, aggregate materials shall be furnished and placed as necessary to secure proper foundation drainage, pipe covering, or backfill support. Tapped service piping of 3/4 inch to and including 1-1/4 inches in diameter shall be installed in one piece without intermediate joint couplings between the corporation stop 36 and the curb stop. Service pipe of 1-1/2 inches in diameter and larger shall be furnished in standard roll lengths to eliminate any intermediate joints. When full roll lengths are less than the service length the rolls may be joined with approved couplings. Unless otherwise specified, connection of tapped service lines to the water main shall be made at an angle of not more than 22 degrees from the horizontal. A double wrap of Teflon tape shall be placed on the corporation stop threads prior to installation in the main. Expansion loops shall be directed downward or horizontal from the tap. Unless otherwise indicated, tap service lines shall be installed on a straight line at right angles to the water main or property line as directed by the Engineer. In the absence of specific requirements, the service line shall be terminated at the property line, where it shall be connected to an existing line or, in the case of undeveloped property, it shall be capped, plugged, or peened as approved by the Engineer. The flaring of copper tubing ends shall be accomplished only with the use of the proper size and type of tools as designed for the purpose. Tubing shall be cut squarely and all edge roughness shall be removed prior to flaring. All couplings shall be tightened securely, so the flared end fits snugly against the bevel of the fitting without leakage. The flared joint couplings shall be made up without the use of jointing compounds. The service pipe and curb stop coupling depth shall be such as to maintain not less than the specified minimum cover. The service box shall be connected to or centered over the curb stop and be firmly supported on concrete blocking as required by the Plans, Specifications, and Special Provisions. Clearance shall be provided so the service box does not rest on the water pipe. Service boxes shall be installed plumb. The service boxes shall be brought to proper surface grade when the final ground surface has been established. D. Setting Valves, Hydrants, Fittings and Specials Valves, hydrants, fittings, and specials shall be provided and installed as required by the Plans, Specifications, and Special Provisions, with the exact locations and setting as directed by the Engineer, and with each installation accomplished in accordance with the requirements for installation of mainline pipe to the extent applicable. Support blocking, reaction backing, and anchorage devices shall be provided as required by the Plans, Specifications, and Special Provisions, or as otherwise ordered by the Engineer. Hydrants shall be installed plumb, with the height and orientation of nozzles as shown in the Plans or as directed by the Engineer. Unless otherwise specified, the hydrants shall be connected to the mainline pipe with 6-inch diameter ductile iron pipe, controlled by an independent valve. When a hydrant with an open drain outlet is set in clay or other impervious soil, a drainage pit of at least one cubic yard shall be excavated below and around the hydrant base and the pit shall be filled with Foundation Material to a level six inches above the 37 drain outlet. Two layers of tar paper, or other material approved by the Engineer, shall be carefully placed over the rock to prevent backfill material from entering voids in the rock drain. Hydrants located where the groundwater table is above the drain outlet shall have the outlet drain hole plugged or the drain tube cut off to prevent draining, and shall be equipped with a tag stating, "Pump After Use". Valve boxes shall be centered over the valve wrench nut and be installed plumb, with the box cover flush with the surface of the finished pavement or at such other level as may be directed. Masonry valve pit structures, for valves with exposed gearing or operating mechanisms, shall be constructed in accordance with the details shown in the Plans and with the applicable provisions of these Specifications. Drainage blow-offs, air vents, and other special appurtenances shall be provided and installed as required by the Plans, Specifications, and Special Provisions. All dead ends shall be closed with approved plugs or caps and shall be equipped with suitable blow-off facilities. E. Disinfection of Water Mains Before being placed in service, the completed water main shall be disinfected. Disinfection materials and procedures, and the collection and testing of water samples, shall be in accordance with the provisions of AWWA C-651. After the final flushing the water shall be tested for bacteriologic quality and found to meet the standards prescribed by the Minnesota Department of Health. Where an existing water main is cut for the installation of any fitting, the pipe and fittings proposed to be installed shall be disinfected prior to installation as follows: (1) The interior of the pipe and fittings shall be cleaned of all dirt and foreign material. (2) The interior of the pipe and fittings shall be thoroughly swabbed or sprayed with a 1 percent minimum hypochlorite solution. Unless otherwise indicated in the Plans, Specifications, and Special Provisions, the Contractor shall furnish all materials and perform the disinfecting, flushing, and testing as necessary for meeting the water quality requirements. The flushing operations and the form of chlorine and method of application to be used shall be subject to approval by the Engineer. F. Electrical Conductivity Test The Contractor shall perform a conductivity test within one week after completion of pressure testing of the main on all iron pipe water mains to establish that electrical 38 thawing may be carried out in the future The system (pipeline, valves, fittings and hydrants) shall be tested for electrical continuity and current capacity. The electrical test shall be made after the hydrostatic pressure test and while the line is at normal operating pressure. Backfilling shall have been completed. The line may be tested in sections of convenient length as approved by the Engineer. Direct current of 350 amperes + 10%, shall be passed through the pipeline for 5 minutes. Current flow through the pipe shall be measured continuously on a suitable ammeter and shall remain steady without interruption or excessive fluctuation throughout the 5-minute test period. Insufficient current or intermittent current or arcing, indicated by large fluctuation of the ammeter needle, shall be evidence of defective contact in the pipeline. The cause shall be isolated and corrected. Thereafter, the section in which the defective test occurred shall be retested as a unit and shall meet the requirements. Sources of Direct Current for these tests may be motor generators, batteries, arc welding machines, etc. Direct Current arc welding machines will probably be the usual source. These machines are available in adequate capacity for these tests and are equipped with controls for regulating the current output. All such equipment shall be furnished by the Contractor, subject to the approval of the Engineer. Cables from the power source to the section of system under test should be of sufficient size to carry the test current without overheating or excessive voltage drop. Usable sizes will probably be in the range of 2/0 to 4/0 A.W.G. Connections for the test shall be made at hydrants. The hydrants shall be in the open position with the caps on during the test. The cable shall be clamped to the body of the hydrant. Note: After the test the hydrant shall be shut off and a cap loosened to allow hydrant drainage or the hydrant shall be pumped dry. Tighten cap after drainage. In using arc welding machines, the current control should be set at minimum before starting. After starting the machines, advance the control until the current indicated on the ammeter is at the desired test value. Caution: In case of open circuits at joints or connections, the voltage across the defective joint or connection will be in order of 50- 100 volts. G. Hydrostatic Testing of Water Mains After the pipe has been laid, including fittings and valves and blocking, all newly-laid pipe or any valved section thereof, unless directed otherwise by the Engineer, shall be subject to hydrostatic pressure of 150 pounds per square inch. The duration of each such test shall be at least two hours. 39 Each section of pipe to be tested shall be filled with water and all air expelled at the highest point. The required taps to expel air or to fill the water main shall be supplied and installed by the Contractor and shall be 3/4 inch and shall include an approved service saddle when required. The test apparatus shall be applied at the lowest elevation on the section to be tested. The apparatus shall be connected to the main at a service tap or special tap location. The pressure gauge shall be a standard pressure gauge. The dial shall register from 0 - 200 psi and have a dial size of 4 1/2 inches with 1 psi increments. The hydrostatic test, pressure requirement for an acceptable test shall be a maximum pressure drop of 2 psi during the last hour of the two hour pressure test. If this test requirement cannot be met, the Contractor shall investigate the cause, make corrections, and retest until the pressure drop requirement can be met. Only if several consecutive tests indicate a consistent pressure drop and only after the Contractor has made numerous attempts to resolve the problem, acceptable to the Engineer, may the Contractor request in writing and the Engineer consider the use of the leakage test. The leakage test may be performed by the Contractor to determine the magnitude of the leak, however, meeting the leakage allowance shall not automatically be considered acceptance, in lieu of the pressure test, for the section being tested. Final acceptance shall be at the discretion of the Engineer. When allowed, the leakage test shall be performed in accordance with AWWA C-600, Section 4.1.5, 4.1.6 and the line will be accepted as per Section 4.1.7. H. Operational Inspection At the completion of the project and in the presence of the Engineer and the Contractor, representatives of the Owner shall operate all valves, hydrants, and water services to ascertain that the entire facility is in good working order; that all valve boxes are centered and valves are opened; that all hydrants operate and drain properly; that all curb boxes are plumb and centered; and that water is available at all curb stops. 2611.4 METHOD OF MEASUREMENT All items will be measured separately according to design designation as indicated in the Pay Item name and as may be detailed and defined in the Plans, Specifications, or Special Provisions. Pipe will generally be designated by size (inside diameter or span), strength class, kind or type, and laying condition. Payment shall include all component parts thereof as described or required to complete the unit, but excluding any item covered by a separate pay item. Lineal measurement of piping will include the running length of any special fittings (tees, wyes, bends, gates, etc.) installed within the line of measure between specified terminal points. 40 A. Water Pipe Mainline pipe and service pipe of each kind and size will be measured separately by the overall length along the axis of the pipeline, from beginning to end of each installation and without regard to intervening valves or specials. Terminal points of measure will be the spigot or cut end, base of hub or bell end, center of valves or hydrants, intersecting centers of tee or wye branch service connections, and center of corporation stop or curb stop couplings. B. Valves Valves of each size and type will be measured separately as complete units, including the required manhole or valve box setting. C. Corporation Stops Corporation stops of each size and type will be measured separately by the number of units installed, including the water main tap and saddle. D. Curb Stops Curb stops of each size and type will be measured separately by the number of units installed, including the required curb box. E. Hydrants Hydrants will be measured by the number of units installed. F. Air Vents Air vents of each type and size will be measured separately by the number of complete units installed, including the required manhole or valve box setting. G. Rearrangement of Inplace Facilities The removal, relocation, extension, or adjustment of existing inplace facilities will be measured, as indicated in the Proposal. H. Polyethylene Encasement Polyethylene encasement of pipe will be measured by the linear foot of pipe encased of each specified size. 41 I. Ductile and Gray Iron Fittings Ductile Iron and Gray Iron fittings shall be measured by the pound without joint accessories or on an each basis as specified on the Proposal or in the Special Provisions. The standard weight of Ductile Iron and Gray Iron fittings, for payment basis, shall be as published in AWWA C-110. J. Polyvinyl Chloride or Polyethylene Polyvinyl Chloride or Polyethylene fittings shall be measured on an each basis as specified and shown on the Proposal or in the Special Provisions. K. Access Structures Access structures, such as valve boxes, service boxes, manholes and vaults, will be measured for payment only when and to the extent that the Proposal contains specific items therefore. Otherwise, the required structures are included for payment as part of the pipe appurtenance (Gate Valve, Curb Stop, Air Vent, etc.) item which is served. When applicable, measurement will be by the number of individual units installed of each type and design. 2611.5 BASIS OF PAYMENT Payment for construction of water distribution facilities will be made as detailed in the method of measurement and as shown on the Bid Proposal or detailed in the Special Provisions. Payment shall include all costs of furnishing and installing the complete facility as required by the Plans, Specifications, and Special Provisions. Payment shall be made for Water Main Pipe, Service Pipe, and Tapped Service Pipe, of each size and kind at the appropriate Contract prices per linear foot installed All costs of pipeline disinfection, leakage testing, pipe jointing materials, dead end plugs and caps, making connections to existing facilities, blocking and anchorage materials, and other work necessary for proper installation of pipe as specified shall be included for payment as part of the pipe item, without any direct compensation being made therefore unless specific pay items are included on the Proposal. Payment shall be made for Valves, Corporation Stops, Curb Stops, Hydrants, Air Vents, Polyethylene Encasement, Insulation, and other specially identified appurtenant items, at the appropriate Contract prices per unit of measure for each size and type or kind installed. Access structures such as Valve Boxes, Service Boxes, Manholes, and Vaults will be paid for as separate items only when separate pay items are included on the Proposal. Payment for rearrangement of inplace facilities or vertical offset of proposed facilities shall be made under specially named items at the appropriate Contract prices per unit of 42 measure and shall be compensation in full for all costs of performing the work as specified. All costs of excavating to foundation grade, preparing the foundation, placing and compacting backfill materials, restoring surface improvements, and other work necessary for prosecution and completion of the work as specified, shall be included for payment as part of the pipe and pipe appurtenance items without any direct compensation being made therefore, unless specific pay items are included on the Proposal. When special aggregate backfill materials are required to be furnished and placed to comply with the indicated Laying Conditions, the costs thereof shall be included for payment as part of the pipe items without any direct compensation therefore. In the absence of special payment provisions, all costs of repairing, replacing, or otherwise restoring surface improvements as required by the Contract shall be included for payment as part of other Contract items without any direct compensation being made therefore. * * * END OF SECTION * * * SECTION 2621 SANITARY SEWER AND STORM SEWER INSTALLATION 43 2621 STANDARD SPECIFICATIONS FOR SANITARY SEWER AND STORM SEWER INSTALLATION 2621.1 DESCRIPTION This work shall consist of the construction of pipe sewers utilizing plant fabricated pipe and other appurtenant materials, installed for conveyance of sewage, industrial wastes, or storm water. The work includes construction of manhole and catch basin structures and other related items as specified. Use of the term "Plans, Specifications, and Special Provisions" within this specification shall be construed to mean those documents that compliment, modify, or clarify these specifications and are accepted as an enforceable component of the Contract or Contract Documents. All references to Mn/DOT Specifications shall mean the latest published edition of the Minnesota Department of Transportation Standard Specifications for Construction as modified by any Mn/DOT Supplemental Specifications issued before the date of advertisement for bids. All references to other Specifications of AASHTO, ASTM, ANSI, AWWA, etc. shall mean the latest published edition available on the date of advertisement for bids. The following specifications have been referenced in this Specification: AASHTO M198 Specification for Joints for Circular Concrete Sewer and Culvert Pipe Using Flexible Watertight Gaskets AASHTO M294 Specification for Corrugated Polyethylene Pipe, 300-to 1200-mm Diameter ASTM A48 Specification for Gray Iron Castings ASTM A74 Specification for Cast Iron Soil Pipe and Fittings ASTM C76 Specification for Reinforced Concrete Pipe ASTM C270 Mortar for Unit Masonry ASTM C361 Specification for Reinforced Concrete Low Head Pressure Pipe ASTM C425 Specification for Compression Joints for VCP and Fittings ASTM C443 Specification for Joints for Circular Concrete Sewer and Culvert Pipe, Using Rubber Gaskets ASTM C478 Specification for Precast Reinforced Concrete Manhole 44 ASTM D543 Test Method for Resistence of Plastic to Chemicals ASTM C564 Specification for Rubber Gaskets for Cast Iron Soil Pipe and Fittings ASTM C700 Specification for Vitrified Clay Pipe ASTM D2321 Recommended Practice for Installation of Flexible Thermo-plastic Sewer Pipe ASTM D2751 Specification for ABS Pipe and Fittings ASTM D3034 Specification for PVC Sewer Pipe and Fittings ASTM D3212 Specification for Joints for Drain and Sewer Plastic Pipes Using Flexible Elastomeric Seals ASTM F679 Specification for Large-Diameter PVC Sewer Pipe and Fittings ASTM F949 Specification for Poly (Vinyl Chloride) (PVC) Corrugated Sewer Pipe with a Smooth Interior and Fittings AWWA C104 American National Standard for Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water AWWA C110 American National Standard for Ductile-Iron and Gray-Iron Fittings, 3 In. Through 48 In. (75 mm Through 1200 mm), for Water and Other Liquids AWWA C111 American National Standard for Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings AWWA C115 American National Standard for Flanged Ductile-Iron Pipe With Ductile- Iron or Gray-Iron Threaded Flanges AWWA C150 American National Standard for Thickness Design of Ductile-Iron Pipe AWWA C151 American National Standard for Ductile-Iron Pipe, Centrifugally Case, for Water or Other Liquids AWWA C153 American National Standard for Ductile-Iron Compact Fittings, 3 In. Through 24 In. (76 mm Through 610 mm) and 54 In. Through 64 In. (1,400 mm Through 1,600 mm), for Water Service 2621.2 MATERIALS All materials required for this work shall be new material conforming to requirements of the referenced specifications for the class, kind, type, size, grade, and other details 45 indicated in the Contract. Unless otherwise indicated, all required materials shall be furnished by the Contractor. If any options are provided for, as to type, grade, or design of the material, the choice shall be limited as may be stipulated in the Plans, Specifications, or Special Provisions. All manufactured products shall conform in detail to such standard design drawings as may be referenced or furnished in the Plans. Otherwise, the Owner may require advance approval of material suppliers, product design, or other unspecified details as it deems desirable for maintaining adopted standards. At the request of the Engineer, the Contractor shall submit in writing a list of materials and suppliers for approval. Suppliers shall submit a Certificate of Compliance that the materials furnished have been tested and are in compliance with the specifications. A. Sewer Pipe and Service Line Materials All pipe furnished for main sewer and service line installations shall be of the type, kind, size, and class indicated for each particular line segment as shown in the Plans and designated in the Contract Items. Wherever connection of dissimilar materials or designs is required, the method of joining and any special fittings employed shall be products specifically manufactured for this purpose and subject to approval by the Engineer. A1. Vitrified Clay Pipe and Fittings Vitrified clay extra strength pipe and fittings shall conform to the requirements of ASTM M-65 for the size and type and class specified, subject to the following supplementary provisions: (1) Unless otherwise specified, the pipe and fittings shall be non-perforated, full circular type, either glazed or unglazed. (2) All pipe and fittings manufactured with bell-and-spigot ends shall be furnished with factory fabricated compression joints conforming to the requirements of ASTM C-425. (3) In lieu of the bell-and-spigot jointing requirements, the pipe and fittings may be furnished with plain ends, in which case the jointing shall be by means of compression couplings conforming to the requirements of ASTM C-425, Type B. (4) All clay pipe fittings (wyes, tees, bends, plugs, etc.) shall be of the same pipe class and joint design as the pipe to which they are to be attached. (5) Pipe and fittings manufactured to the standards of AASHTO 52;65 may be accepted by prior approval of the Engineer. 46 A2. Ductile Iron Pipe and Ductile Iron and Gray Iron and Fittings The pipe furnished shall be Ductile Iron pipe and fittings furnished shall be of the Ductile Iron or Gray Iron type as specified for each particular use of installation. When Gray Iron is specified, either type may be furnished. Gray Iron may not be substituted for Ductile Iron unless specifically authorized in the Special Provisions. Ductile iron pipe shall conform to the requirements of AWWA C115 or C151 for water and thickness design shall conform to AWWA C150. In addition, the pipe shall comply with the following supplementary provisions: (1) Fittings shall conform to the requirements of AWWA C110 OR 153 (Gray Iron and Ductile Iron Fittings or Ductile Iron Compact Fittings) for the joint type specified. (2) Unless otherwise specified, all pipe and fittings shall be furnished with cement mortar lining meeting the requirements of AWWA C104 for standard thickness lining. All exterior surfaces of the pipe and fittings shall have an asphaltic coating at least one mil thick. Spotty or thin seal coating, or poor coating adhesion, shall be cause for rejection. (3) Rubber gasket joints for Ductile Iron Pressure Pipe and fittings shall conform to AWWA C111. A3. Reinforced Concrete Pipe and Fittings Reinforced concrete pipe, fittings and specials shall conform with the requirements of ASTM C-76 (Reinforced Concrete Pipe) with rubber O-ring or profile joints for the type, size, and strength class specified, subject to the following supplementary provisions: (1) All branch fittings such as tees, wyes, etc. shall be cast as integral parts of the pipe. All fittings and specials shall be of the same strength class as the pipe to which they are attached. (2) Joints shall meet the requirements of ASTM C-361. (3) Lift holes will not be permitted unless specifically authorized in the Plans, Specifications, and Special Provisions A4. Corrugated Steel Pipe and Fittings Corrugated steel pipe and fittings shall conform to the requirements of Mn/DOT Specification 3226 (Corrugated Steel Pipe) for the type, size and sheet thickness specified. When specifically provided for in the Plans, Specifications, and Special Provisions, the galvanized steel pipe and fittings shall be furnished with special aramid fiber bonded, bituminous, or plastic coating or concrete lining as required. 47 A5. Polyvinyl Chloride Pipe and Fittings Smooth walled polyvinyl chloride pipe and fittings shall conform with the requirements of ASTM D-3034 and ASTM F-679 for the size, standard dimension ratio (SDR), and strength requirements indicated on the Plans, Specifications, and Special Provisions. The grade used shall be resistant to aggressive soils or corrosive substances in accordance with the requirements of ASTM D-543. Unless otherwise specified, all pipe and fittings shall be SDR 35 and connections shall be push-on with elastomeric gasketed joints which are bonded to the inner wall of the gasket recess of the bell socket. Corrugated polyvinyl chloride pipe and fittings with smooth interior shall conform with the requirements of ASTM F-949 for the size and wall thickness indicated on the Plans, Specifications, and Special Provisions. Unless otherwise specified, all pipe and fittings shall be push-on with snug fit elastomeric joints meeting tightness requirements of ASTM D-3212. A6. Cast Iron Soil Pipe Unless otherwise specified in the Plans, Specifications, and Special Provisions, cast iron soil pipe shall be service weight pipe meeting the requirements of ASTM A-74 and the Plans, Specifications, and Special Provisions. Unless otherwise specified, pipe joints shall be push-on, sealed with elastomeric gaskets, meeting the requirements of ASTM C-564. A7. Acrylonitrile-Butadiene-Styrene Pipe Acrylonitrile-Butadiene-Styrene (ABS) solid wall pipe and fittings shall conform to the requirements of ASTM D-2751 for 4 inch and 6 inch diameter and shall be gasket seal joints, assembled as recommended by the pipe manufacturer. Solvent cemented joints, assembled as recommended by the pipe manufacturer, shall be provided only where specifically indicated in the Plans, Specifications, and Special Provisions. A8. Dual-Wall Corrugated Polyethylene Pipe Dual-Wall Corrugated Polyethylene Pipe shall conform to the requirements of AASHTO M-294 and Design 18 of the AASHTO Standard Specifications for Highway Bridges for storm sewer pipe sizes 12-inch through 36-inch. Joints shall be water-tight unless the engineer approves a soil-tight joint. Pipe manufacture, water-tight joint testing, and installation shall conform to current Mn/DOT requirements and/or as indicated in the Plans, Specifications, and Special Provisions. B. Metal Sewer Castings Metal castings for sewer structures such as manhole frames and covers, catch basin frames, grates and curb boxes, shall conform to the requirements of ASTM A-48 (Gray Iron Castings), subject to the following supplementary provisions: 48 (1) Casting assemblies or dimensions, details, weights, and class shall be as indicated in the detailed drawings for the design designation specified. Unless otherwise specified, the castings shall be Class 30 or better. (2) Lid-to-frame surfaces on round casting assemblies shall be machine milled to provide true bearing around the entire circumference. (3) Casting weight shall be not less than 95 percent of theoretical weight for a unit cast to exact dimensions, based on 442 pounds per cubic foot. (4) A Certificate of Compliance shall be furnished with each shipment of castings stating that the materials furnished have been tested and are in compliance with the specification requirements. (5) Unless otherwise specified, sanitary sewer manholes in areas subject to flooding by surface water shall have self-sealing lids and recessed pick holes. (6) Unless otherwise specified, sanitary sewer manhole lids shall have recessed pick holes. C. Precast Concrete Manhole and Catch Basin Sections Precast concrete riser sections and appurtenant units (grade rings, top and base slabs, special sections, etc.) used in the construction of manhole and catch basin structures shall conform with the requirements of ASTM C-478, Mn/DOT 2506 and the following supplementary provisions: (1) The precast sections and appurtenant units shall conform to all requirements as shown on the detailed drawings. (2) Joints of manhole riser sections shall be tongue and groove with rubber "O" ring or profile joints provided on sanitary sewer manholes. Sanitary sewer inlet and outlet pipes shall be joined to the manhole with a gasketed, flexible, watertight connection or any watertight connection arrangement that allows differential settlement of the pipe and manhole wall to take place. (3) Air-entrained concrete shall be used in the production of all units. Air content shall be maintained within the range of 5 to 7 percent. (4) A Certificate of Compliance shall be furnished with each shipment of precast manhole and catch basin sections stating that the materials furnished have been tested and are in compliance with the specification requirements. (5) Lift holes will not be permitted in precast manholes. 49 D. Concrete Concrete for cast-in-place masonry construction shall be produced and furnished in accordance with the requirements of Mn/DOT Specification 2461 for the mix designation indicated in the Plans. The requirements for Grade B concrete shall be met where a higher grade is not specified. Type 3 (air-entrained) concrete shall be furnished and used in all structures having weather exposure. E. Mortar Mortar for use in masonry construction shall be an air-entrained mixture of one part Masonry cement, Type S, and two parts mortar sand, with sufficient water to produce proper consistency, and with sufficient air-entraining agent added to maintain an air content within the range of 7 to 10 percent. Mortar shall meet the requirements of ASTM C-270. 2621.3 CONSTRUCTION REQUIREMENTS A. Installation of Pipe and Fittings A1. Inspection and Handling Proper and adequate implements, tools, and facilities satisfactory to the Engineer shall be provided and used by the Contractor for the safe and convenient prosecution of the work. During the process of unloading, all pipe and accessories shall be inspected by the Contractor for damage. The Contractor shall notify the Engineer of all material found to have cracks, flaws or other defects. The Engineer shall inspect the damaged materials and have the right to reject any materials found to be unsatisfactory. The Contractor shall promptly remove all rejected material from the site. All materials shall be handled carefully, as will prevent damage to protective coatings, linings, and joint fillings; preclude contamination of interior areas; and avoid jolting contact, dropping, or dumping. All work and materials are subject to tests by the Owner at such frequency as may be determined by the Engineer. While suspended and before being lowered into laying position, each pipe section and appurtenant unit shall be inspected by the Contractor to detect damage or unsound conditions that may need corrective action or be cause for rejection. The Contractor shall inform the Engineer of any defects discovered and the Engineer will prescribe the required corrective actions or order rejection. Immediately before placement, the joint surfaces of each pipe section and fitting shall be inspected for the presence of foreign matter, coating blisters, rough edges or projections, and any imperfections so detected shall be corrected by cleaning, trimming, or repair as needed. 50 A2. Pipe Laying Operations Trench excavation and bedding preparations shall proceed ahead of pipe placement as will permit proper laying and joining of the units at the prescribed grade and alignment without unnecessary deviation or hindrance. All foreign matter or dirt shall be removed from the inside of the pipe and fittings before they are lowered into position in the trench and they shall be kept clean by approved means during and after laying. The sewer materials shall be carefully lowered into laying position by the use of suitable restraining devices. Under no circumstances shall the pipe be dropped into the trench. At the time of pipe placement, the bedding conditions shall be such as to provide uniform and continuous support for the pipe between bell holes. Bell holes shall be excavated as necessary to make the joint connections, but they shall be no larger than would be adequate to support the pipe throughout its length. No pipe material shall be laid in water nor when the trench or bedding conditions are otherwise unsuitable or improper. When placement or handling precautions prove inadequate, in the Engineer's opinion, the Contractor shall provide and install suitable plugs or caps effectively closing the open ends of each pipe section before it is lowered into laying position, and they shall remain so covered until removal is necessary for connection of an adjoining unit. Unless otherwise permitted by the Engineer, bell and spigot pipe shall be laid with the bell ends facing upgrade and the laying shall start on the downgrade end and proceed upgrade. As each length of bell and spigot pipe is placed in laying position, the spigot end shall be centered in the bell and the pipe forced home and brought to correct line and grade. The pipe shall be secured in place with approved backfill material, which shall be thoroughly compacted by tamping around the pipe to a height of at least 12 inches above the top with hand operated mechanical tamping devices or by hand. The joint areas shall remain exposed and precautions shall be taken to prevent the soil from entering the joint space, until the joint seal is effected. Backfill in the bell area shall be left loose. Connection of pipe to existing lines or previously constructed manholes or catch basins shall be accomplished as shown in the Plans or as otherwise approved by the Engineer. Where necessary to make satisfactory closure or produce the required curvature, grade or alignment deflections at joints shall not exceed that which will assure tight joints and comply with any limitations recommended by the pipe manufacturer. Entrance of foreign matter into pipeline openings shall be prevented at all times to the extent that suitable plugs or covering can be kept in place over the openings without interfering with the installation operations. Installation of thermoplastic pipe shall conform to ASTM D-2321. 51 A3. Connection and Assembly of Joints All pipe and fitting joints shall fit tightly and be fully closed. Spigot ends shall be marked as necessary to indicate the point of complete closure. All joints shall be soil tight, as the minimum requirement, and shall be watertight in all sanitary sewer pipe lines and in all storm sewer pipe lines installed within the limits of a paved street or highway traffic lanes. Where specified, the joints in certain assemblies shall be made structurally integral by being completely encased in concrete to form a rigid watertight unit as indicated in the standard drawings. All joints shall be sealed as follows, subject to such other approved method as the Engineer may authorize as being an acceptable alternative: (1) Concrete pipe and fitting joints - compression type rubber gasket seals conforming to the requirements of ASTM C-443, ASTM C-361 or AASHTO M-198 for circular pipe, or as otherwise approved by the Engineer in the case of non-circular pipe sections. (2) PVC pipe, and ABS solid wall pipe and fittings assembled gasket seal joints. (3) Corrugated smooth wall PVC and corrugated-double wall HDPE pipe and fittings - assembled push-on gasketed joints shall pass performance tests as listed in ASTM D- 3212. Solvent welds shall not be permitted. (4) Vitrified clay pipe and fittings - factory fabricated compression seals or compression type couplings. (5) Corrugated steel pipe and fittings - sealed with approved type compression seals. A4. Bulkheading Open Pipe Ends All pipe and fitting ends left open for future connection shall be bulkheaded by approved methods prior to backfilling. Unless otherwise specified or approved, all openings of 24 inches in diameter or less shall be closed off with prefabricated plugs or caps and all openings larger than 24 inches in diameter shall be closed off with masonry bulkheads. Prefabricated plugs and caps shall be of the same material as the pipe material, or an approved alternate material, and they shall be installed with watertight seal as required for the pipeline joints. Masonry bulkheads shall be constructed with clay or concrete brick to a wall thickness of eight inches. Bulkheads installed for temporary service during construction may be constructed with two- inch timber planking securely fastened together and adequately braced, as an alternate to the masonry construction. 52 B. Appurtenance Installations Appurtenance items such as aprons, trash guards, gates and castings shall be installed where and as required by the Plans and in accordance with such standard detail drawings or supplementary requirements as may be specified. Casting assemblies installed on manhole or catch basin structures shall be set in a full mortar bed and be adjusted to the specified elevation without the use of shims or blocking. Sewer aprons shall be subject to all applicable requirements for installation of pipe. All aprons and outfall end sections shall have the last three sections tied. Two tie bolt fasteners shall be placed in each of the last three joints, one on each side of top center at the 60 degree point (from vertical). Tie bolt diameter shall be: 1/2 inch for 12" to and including 21" pipe; 5/8 inch for 24" to and including 36" pipe; 3/4 inch for 42" to and including 54" pipe; and 1" for 60" and larger pipe. The tie bolts shall be of a design approved by the Engineer. C. Sewer Service Installations Main sewer service connections and building service sewer pipe shall be installed as provided for in the Contract and as may be directed by the Engineer. The sewer service connections and pipe lines shall be installed in conformance with all applicable requirements of the main sewer installation and as more specifically provided for herein. The Engineer, with the assistance of the Contractor, shall keep accurate records of all service installations as to type, location, elevation, point of connection and termination, etc. This service record shall be maintained jointly by the Contractor and Engineer on forms provided by the Engineer. The service installations shall not be backfilled until all required information has been obtained and recorded. The main sewer service connection shall consist of installing a Branch Tee or Wye section in the main sewer line at designated locations or providing an insert type Saddle Tee in a pipe cutout where and as permitted or required in lieu of the built-in fitting. Orientation of service connection fitting shall be as shown in the standard drawings unless otherwise directed by the Engineer. Where the depth of cover over the main sewer invert is greater than 15 feet (or such other maximum as may be indicated), the service connection shall be extended upward by means of a Service Riser Section in accordance with the details shown in the standard drawings. Unless otherwise specified, service pipe shall be installed at right angles to the main sewer and at a straight line grade to the property line. The standard and minimum grades shall be a uniform rise of one inch in four feet for sanitary service lines and one inch in eight feet for storm sewer service lines. These minimum grades may be reduced (by not 53 more than one-half pitch) where the Engineer so approves in the case of restrictive elevation differences. Building service pipe lines shall generally be kept as deep as required to serve the building elevation and maintain the specified minimum pipe grades. Pipe bends shall be provided as necessary to bring the service lines to proper location and grade. Pipe bends shall not exceed 22-1/2 degrees without approval of the Engineer. Unless otherwise indicated, service pipe installation shall terminate at property line or as designated on the Plans, with a gasketed plug placed in the end, at which point the Contractor shall furnish and set a 4 x 4 inch wooden timber 6 feet to 8 feet in length embedded 4 feet below grade, or approved steel post to mark the exact end of pipe. The timber or post shall be set vertically, with the top 2 feet painted green. Wherever service line connections to the main sewer are permitted or required to be made by the open cut-out method in the absence of a built-in Tee or Wye fitting, the connection shall be made by using an approved type of Saddle Tee fitting. The pipe cut-out shall be made with an approved type coring machine or by other approved methods producing a uniform, smooth circular cut-out as required for proper fit. The cut-out discs shall be retrieved and shall not be allowed to remain within the main sewer pipe. The Saddle Tee shall be securely fastened to the main sewer pipe by means of epoxy resin or other approved adhesive. The entire connection fitting shall be encased in concrete to a minimum thickness of six inches and as may be shown in the standard drawings. Wherever service line connections to the main sewer are required to be made by means of built-in Branch Tee or Wye fittings, the Contractor shall, in the absence of such fitting, remove a section of the main sewer pipe and replace it with the required Branch Tee or Wye section connected by means of an approved sleeve coupling. Sanitary sewer service lines shall not be connected to a manhole at an elevation more than 24 inches above the crown of the outgoing sewer. Where the elevation difference is greater than 24 inches, the connection shall be made by means of an Outside Drop Connection in accordance with the details shown in the standard drawings. All pipe and fitting openings at temporary terminal points shall be fitted with suitable plugs or shall be bulkheaded as required for the main sewer pipe. D. Manhole and Catch Basin Structures Manholes, catch basins, and other special access structures shall be constructed at designated locations as required by the Plans and in accordance with any standard detail drawings or special design requirements given therefor. Unless otherwise specified or approved, manholes and catch basins shall be constructed on a precast or cast-in-place concrete base and the barrel riser sections, cone section and top adjusting rings shall all be of precast concrete. All units shall be properly fitted and 54 sealed to form a completely watertight structure. Barrel and cone height shall be such as to permit placement of at least two and not more than six standard two-inch precast concrete adjusting rings or as shown on the plan immediately below the casting assembly. Unless otherwise specified or approved, manholes and catch basins shall have an inside barrel diameter at the bottom of 48 inches minimum and the inside diameter at the top of the cone section and all adjusting rings shall be of the same size and shape as the casting frame. Casting assemblies shall be as specified in the Plans. Catch basin grate elevation shall be adjusted as necessary to maintain the required dip below normal gutter grade. as shown on the plans. Concrete cast-in-place base shall be poured on undisturbed or firmly compacted foundation material that shall be trimmed to proper elevation. The bottom riser section shall be set in fresh concrete or mortar and all other riser section joints of the tongue and groove design shall be sealed with rubber gaskets. The concrete base under an outside drop connection shall be monolithic with the manhole base. Wherever special designs so require or permit, and as otherwise may be approved by the Engineer, a precast concrete base may be used or the structure may be constructed with solid sewer brick or block units or with cast-in-place concrete. Any combination of cast- in-place concrete and brick or block mortar construction will be allowed and may be required where it is impossible to complete the construction with standard precast manhole sections. All annular wall space surrounding the inplace storm sewer pipes shall be completely filled with mortar or concrete, and the inside bottom of each manhole and catch basin shall be shaped with fresh concrete to form free flow through invert troughs as directed. E. Reconnecting Existing Facilities Disposition of abandoned facilities and reconnection of existing facilities shall be as provided for in the Plans, Specifications, and Special Provisions. F. Sanitary Sewer Leakage Testing All sanitary sewer lines, including service connections, shall be substantially watertight and shall be tested for excessive leakage upon completion and before connections are made to the service by Others. Each test section of the sewer shall be subjected to exfiltration testing, either by hydrostatic or air test method as described below and at the Contractor's option. The requirements set forth for maximum leakage shall be met as a condition for acceptance of the sewer section represented by the test. If the ground water level is greater than three feet above the invert elevation of the upper manhole and the Engineer so approves, infiltration testing may be allowed in lieu of the exfiltration testing, in which case the allowable leakage shall be the same as would be allowed for the Hydrostatic Test. 55 All testing shall be performed by the Contractor without any direct compensation being made therefor, and the Contractor shall furnish all necessary equipment and materials, including plugs and standpipes as required. F1. Air Test Method The pipeline shall be sealed with plug whose sealing length is greater than the diameter of the pipe and constructed in such a nature that it will not require external blocking or bracing and maintain a seal against the line's test pressure. All wyes, tees, outlets or ends of lateral streets shall be suitably capped and braced to withstand the internal pressures. Such caps or plugs shall be easily removable. One plug shall be tapped for the air supply hose and the return air pressure hose. The air supply hose, connected from the compressor to the plug shall be a throttling valve, bleeding valve and shut off valve for control. The air pressure tap shall have a sensitive pressure gauge, 0 to 10 psi range, protected by a gauge cock and a pressure relief valve set at 10 psi. In performing the test, air is added slowly to the pipeline until pressure inside the pipeline reaches 4.0 psi. If air is added too rapidly, the test accuracy will decrease because a change in temperature also has an effect on the change in pressure. When the air pressure inside the pipeline reaches 4.0 psig above external hydrostatic pressure, the supply air is stopped. A minimum two-minute time interval is allowed for the temperature difference to stabilize before the actual test is performed. If the air pressure drops below 3.5 psig during this time interval, more air will be supplied to the pipeline and throttled to maintain a pressure between 3.5 psig and 4.0 psig for a minimum of two minutes after which time the supply air will be shut off. The portion of line being tested shall be accepted if the portion under test does not lose air at a rate greater than 0.0015 cfm per square foot (for PVC) or 0.003 cfm per square foot (for RCP) per internal pipe end area at an average pressure of 3.0 psig greater than any back pressure exerted by groundwater that may be over the pipe at the time of test. The test shall be accomplished by determining the time in minutes for the pressure to decrease from 3.5 psig to 3.0 psig greater than the average groundwater that may be over the pipe. That time shall not be less than the time shown on the given diameter in the following table: Pipe Diameter in Inches Minutes for PVC Minutes for RCP 4 1.9 1.0 6 2.8 1.4 8 3.8 1.9 56 10 4.7 2.4 12 5.7 2.9 15 7.1 3.4 18 8.5 4.3 21 9.9 5.0 24 11.3 5.7 If the pipeline fails to meet the requirements of the test, the Contractor shall, at their own expense, determine the source of leakage and then repair or replace all defective material and/or workmanship. In determining the pressure greater than the average groundwater, the groundwater height in feet above the pipeline must be measured. When the water elevation has been established, the height in feet above the pipeline shall be divided by 2.31 and that pressure added to gauge pressure of test. A table for converting water height to gauge pressure is as follows: Groundwater Level over Added Pressure to be Applied Top of Pipeline to Gauge Pressure Readings 1 foot - 0.43 psig 2 feet - 0.86 psig 3 feet - 1.29 psig 4 feet - 1.72 psig 5 feet - 2.16 psig 6 feet - 2.59 psig 7 feet - 3.01 psig 8 feet - 3.44 psig 9 feet - 3.87 psig 57 10 - feet 4.30 psig F2. Hydrostatic Test Method After bulkheading the test section, the pipe shall be subjected to a hydrostatic pressure produced by a head of water at a depth of three feet above the invert elevation of the sewer at the manhole of the test section. In areas where ground water exists, this head of water shall be three feet above the existing water table. The water head shall be maintained for a period of one hour during which time it will be presumed that full absorption of the pipe body has taken place, and thereafter for an extended period of one hour the water head shall be maintained as the test period. During the one hour test period, the measured water loss within the test section, including service stubs, shall not exceed the Maximum Allowable Loss (in Gallons Per Hour per 100 Feet of Pipe) given below for the applicable Main Sewer Diameter. Main Sewer Diameter (In Inches) Maximum Allowable Loss* (In Gallons Per Hour Per 100 Feet) 6 0.5 8 0.6 10 0.8 12 1 15 1.2 18 1.4 21 1.7 24 & Larger 1.9 * Based on 100 Gallons Per Day Per Pipe Diameter Inch Per Mile If measurements indicate exfiltration within a test action section is not greater than the allowable maximum, the section will be accepted as passing the test. F3. Test Failure and Remedy In the event of test failure on any test section, testing shall be continued until all leakage has been detected and corrected to meet the requirements. All repair work shall be subject to approval of the Engineer. Introduction of sealant substances by means of the test water will not be permitted. Unsatisfactory repairs or test results may result in an order to remove and replace pipe as the Engineer considers necessary for test conformance. All repair and replacement work shall be at the Contractor's expense. 58 G. Deflection Test Deflection tests shall be performed on all plastic gravity sewer pipes. The test shall be conducted after the sewer trench has been backfilled to the desired finished grade and has been in place for 30 days. The deflection test shall be performed by pulling a rigid ball or nine-point mandrel (Mn/DOT Technical Memorandum 98-24-B-01 or latest revision) through the pipe without the aid of mechanical pulling devices. The ball or mandrel shall have a minimum diameter equal to 95% of the actual inside diameter of the pipe. The maximum allowable deflection shall not exceed five percent of the pipe's internal diameter. The line will be considered acceptable if the mandrel can progress through the line without binding. The time of the test, method of testing, and the equipment to be used for the test shall be subject to the approval of the Engineer. All testing shall be performed by the Contractor at his expense without any direct compensation being made therefor, and he shall furnish all necessary equipment and materials required. G1. Test Failure and Remedy In the event of test failure on any test section, the section shall be replaced, with all repair work subject to approval of the Engineer. The replaced section shall be retested for leakage and deflection in conformance with the specifications contained herein. All repairs, replacement, and retesting shall be at the Contractor's expense. H. Televising Sewer line televising may be required by the Engineer, at the cost of the Contractor, if visual inspection, leakage testing, or deflection testing indicate the sewer has not been constructed in accordance with these specifications and the requirements of the Plans, Specifications, and Special Provisions. 2621.4 METHOD OF MEASUREMENT All items will be measured separately according to design designation as indicated in the Pay Item name and as may be detailed and defined in the Plans, Specifications, or Special Provisions. Pipe will generally be designated by size (inside diameter or span), strength class, kind or type, and laying condition. Complete-in-place items shall include all component parts thereof as described or required to complete the unit, but excluding any excesses covered by separate Pay Items. Linear measurement of piping will include the running length of any special fittings (tees, wyes, elbows, gates, etc.) installed within the line of measure between specified terminal points. 59 A. Sewer Pipe Sewer pipe of each design designation will be measured by length in linear feet along the line of pipe. Terminal points of measurement will be the pipe end at free outlets; the point of connection with inplace pipe; the center of manholes or catch basins; the point of centerline intersections at branch fittings; or the point of juncture with other appurtenances or units as defined. Separation of quantities according to "depth zone classification", when so designated in the Pay Item, will be determined by depth of pipe invert below the ground surface profile. B. Manholes Manholes of each design designation will be measured by number of each constructed complete-in-place, including the base and castings as required, but excluding any excess depth greater than 8.0 feet measured from top of manhole cover to invert elevation of lowest pipe. Excess manhole depth of each design designation will be measured by the linear foot difference in depth between the 8.0 feet allowed as standard and the actual increased depth as constructed. C. Catch Basins Catch basins of each design designation will be measured by number of each constructed complete-in-place, including the base and castings as required, but excluding any excess depth greater than 5.0 feet measured from top of grate (low point) to invert elevation of lowest outlet pipe. Excess catch basin depth of each design designation will be measured by the linear foot difference in depth between the 5.0 feet allowed as standard and the actual increased depth as constructed. D. Outside Drop Connection Outside drop connections of each design will be measured by number of each constructed complete-in-place, including granular encasement, fittings, and any special piping details as required, including two holes into existing manholes for the drop connection, but excluding any excess vertical drop greater than 2.0 feet measured between invert of high pipe inlet and invert of low pipe outlet. Excess drop connection depth will be measured by the linear foot difference in vertical drop between the 2.0 feet allowed as standard and the actual increased vertical drop as constructed. 60 E. Service Connection Service Connections of each design will be measured by number of each constructed complete-in-place as specified. F. Service Pipe Service pipe of each design will be measured separately by length in linear feet, horizontally along the line of installation, between the service end and the point of juncture with the main pipe connection fitting. G. Special Pipe Fittings Special pipe fittings (wyes, tees, bends, etc.) of each design designation will be measured by number of each installed complete-in-place as specified, but excluding any such fittings required to be installed as a component part of any other Work Unit. H. Appurtenant Items Appurtenant items such as aprons, trash guards, gates and other prefabricated units or assemblies as identified by Pay Item name will be measured separately by number of each installed complete-in-place as specified. 2621.5 BASIS OF PAYMENT Payment for sewer pipe and service pipe items at the Contract prices per linear foot of pipe of each design shall be compensation in full for all costs of providing a complete-in- place pipeline, including excavation, foundation preparation, backfilling, leakage testing, restoration of surface improvements, disposal of surplus or waste materials, final cleanup, and such other work as may be specified, but excluding the construction of other structures or special sections and the placement of special fittings, appurtenances or materials specifically designated for payment under other Contract Items. Payment for manhole, catch basin, outside drop connection, service connection, and other structures as specified, at the Contract prices per structure, shall be compensation in full for all costs of constructing each unit complete-in-place as specified, including all required castings, special fittings, base or encasement, and appurtenant materials as specified for the complete structure or section, but excluding such additional work as may be designated for payment under other Contract Items. Where the specified standard manhole, catch basin, or outside drop connection depths are exceeded, the excess depth of each design will be paid for separately as linear footage items and payment at the Contract prices therefor shall be compensation in full for all costs of providing the extra depth. 61 Special pipe fittings such as wyes, tees and bends will be paid for as separate Contract Items to the extent they are required to be installed in the sewer pipe and service pipe lines and not as a component part of a complete-in-place structure (outside drop connections, service connections, etc.) Appurtenant items such as aprons, trash guards, drainage gates, and other prefabricated units or assemblies and specials as designated will be paid for as separate Contract Items to the extent they are not included as a component part of any complete-in-place structure. * * * END OF SECTION * * *