PC staff report west water treatmentCITY OF CHANHASSEN PC DATE: September 6, 2016 CC DATE: September 26, 2016 REVIEW DEADLINE: October 4, 2016 CASE #: 2016-21 BY: RG, TJ, ML, JM, JS, SS SUMMARY OF REQUEST: Request for a Site Plan Review and replat of Lot 1, Block 4, and Outlot A of Lake Harrison to construct the West Water Treatment Plant. LOCATION: 2070 Lake Harrison Road (Lot 1, Block 4, and Outlot A, Lake Harrison) APPLICANT: Greg Johnson, P.E. Paul Oehme, P.E., Public Works Director WSB & Associates City of Chanhassen 477 Temperance Street 7700 Market Boulevard St. Paul, MN 55101 P. O. Box 147 (651) 286-8466 Chanhassen, MN 55317 gjohnson@wsbeng.com (952) 227-1169 poehme@ci.chanhassen.mn.us PRESENT ZONING: Single-Family Residential, RSF 2020 LAND USE PLAN: Parks and Open Space ACREAGE: 6.57 acres DENSITY: 0.06 F.A.R. PROPOSED MOTION: “The Chanhassen Planning Commission recommends approval of the subdivision creating one lot and two outlots and site plan for a 16,950 water treatment facility subject to the conditions of approval and adoption of the findings of facts and recommendation.” Planning Commission West Water Treatment Plant – Planning Case 2016-21 September 6, 2016 Page 2 of 11 LEVEL OF CITY DISCRETION IN DECISION-MAKING: The city’s discretion in approving or denying a Preliminary Plat is limited to whether or not the proposed plat meets the standards outlined in the Subdivision Regulations and Zoning Ordinance. If it meets these standards, the city must approve the preliminary plat. This is a quasi-judicial decision. The city’s discretion in approving or denying a Site Plan is limited to whether or not the proposed project complies with Zoning Ordinance requirements. If it meets these standards, the city must then approve the site plan. This is a quasi-judicial decision. Notice of this public hearing has been mailed to all property owners within 500 feet. PROPOSAL/SUMMARY Request for subdivision approval to replat Lot 1, Block 4, Lake Harrison and Outlot A, Lake Harrison into one lot and two Outlots and site plan review for a 16,950 square foot water treatment facility. APPLICABLE REGULATIONS Chapter 18, Subdivision Chapter 20, Article II, Division 6, Site Plan Review Chapter 20, Article VI, Wetland Protection Chapter 20, Article XII, “RSF” Single-Family Residential District Chapter 20, Article XXIII, Division 7, Design Standards for Commercial, Industrial and Office- Institutional Developments BACKGROUND The plat for Lake Harrison was approved on July 12, 2005 as Planning Case #2005-14 creating 39 lots, 6 outlots and associated right-of-way for public streets with a variance for a private street and street grade. As part of the development, the City purchased Lot 1, Block 4, in the northeast portion of the site for a future water treatment plant. In addition, a raw water main was extended through the development from the well fields to the north and west in anticipation of the construction of the water treatment plant. On May 9, 2005, the Chanhassen City Council approved: Rezoning of the property from RR, Rural Residential, to RSF, Single Family Residential District; Preliminary plat (Subdivision) to create 40 lots, 4 outlots and public right-of-way with a variance for a private street and street grade; a 5-foot front yard Variance for Block 2; a Wetland Alteration Permit to fill and alter wetlands on site; and denied the bluff setback variance. Planning Commission West Water Treatment Plant – Planning Case 2016-21 September 6, 2016 Page 3 of 11 PRELIMINARY PLAT The city is proposing the replat of Outlot A and Lot 1, Block 4, Lake Harrison into one lot for the water treatment facility and park area and two outlots containing open space and wetlands. The lot shall be developed with a water treatment facility and a neighborhood park. Manchester Drive will be extended to provide a permanent cul-de-sac and parking area for the neighborhood park. The outlots shall contain wetlands and permanent open space. Public streets, water and sewer were provided as part of the Lake Harrison development. EASEMENTS The site plan requires replatting Lot 1, Block 4 and Outlot A, Lake Harrison, therefore the existing drainage and utility easements on these properties must be vacated prior to recording the final plat. COMPLIANCE TABLE Area (sq. ft.) Width (ft.) Depth (ft.) Hard Cover % / sq. ft. Notes Code 15,000 90 125 25 / 3,750 Lot 1 179,858 245 44,964 4.13 acres Outot A 45,411 1.04 acres, Contains wetlands (eastern outlot) Outlot B 21,718 0.5 acres, contains wetlands and slope (western outlot) Total 246,987 5.67 acres Planning Commission West Water Treatment Plant – Planning Case 2016-21 September 6, 2016 Page 4 of 11 SITE PLAN REVIEW The city is proposing a 16,950 water treatment facility with underground backwash tanks northeast of the building. In the future, a neighborhood park is being proposed at the end of Manchester Drive. Access to the site will be via a 30-foot wide access off of Lake Harrison Road. The proposed location exceeds the city’s minimum access spacing requirement from Galpin Boulevard. The plan includes a paved area in front of the building to accommodate parking and delivery vehicles. Curb and gutter are required around the parking area. The plan includes installing a 90-foot diameter cul-de-sac at the end of Manchester Drive to provide vehicular access and parking for future park amenities in the area. An 8-foot wide bituminous trail is proposed to extend from the parking area; an ADA-compliant curb ramp must be installed. UTILITIES Eight-inch lateral sanitary sewer will be extended from Galpin Boulevard to the site. A water service will be stubbed to the building from the water system improvements that will be installed. Planning Commission West Water Treatment Plant – Planning Case 2016-21 September 6, 2016 Page 5 of 11 The Metropolitan Council Environmental Services Sewer Access Charge (Metro SAC) must be paid with the building permit. The West Water Treatment Plant is not subject to the City Sewer Access Charge and Water Access Charge (City SAC and WAC). GRADING AND RETAINING WALLS The site drops 30 feet in elevation from the north (Manchester Drive) to the south (Lake Harrison Road). The water treatment plant is proposed to be built into the slope. Two, 30-foot long retaining walls are proposed at the following locations: 1) At the northwest corner of the building, maximum height of four feet, and 2) At the southwest corner of the building, maximum height 19.5 feet. The following comments must be incorporated into the final grading plan: a) The bottom of wall elevation of the northerly retaining wall is mislabeled (shown as 914.0’, appears to be 1014.0’), and b) The 984’ contour southwest of the parking area is mislabeled (shown as 884’). SURFACE WATER MANAGEMENT City code requires that a project either meets NURP recommendations or the National Pollution Discharge Elimination System (NPDES) Requirements, whichever is more restrictive. As the project will exceed the National Pollution Discharge Elimination System threshold for permanent stormwater management the NPDES permit would be the more restrictive. This requires a net reduction in runoff volume, total phosphorous and total suspended solids leaving the site post-development. This site will also be subject to the Riley Purgatory Bluff Creek Watershed District (RPBCWD) Rule J – Stormwater Management. RPBCWD requires that applicant demonstrate that they can accomplish the following goals: 1) Limit peak runoff from all points leaving the site to at or below the existing rates for the 2, 10 and 100-year return frequency storms. 2) Provide onsite abstraction for 1.1 inches of runoff from all impervious surfaces. 3) Provide, on an annual basis, removal of 60% total phosphorous and 90% total suspended solids. If the RPBCWD criteria are met, this will satisfy the city requirements for stormwater management. A stormwater management plan, including a hydraulic and hydrologic model, discussion of how the proposed best management practices will meet the volume requirements, a water quality model (either P8 or MIDS Calculator), and Walker calculations demonstrating adequate capacity within the existing and proposed conveyance system shall be submitted and approved prior to issuance of any permits. Planning Commission West Water Treatment Plant – Planning Case 2016-21 September 6, 2016 Page 6 of 11 The proposed inlet to the existing pond under the driveway (5003) will result in a short circuit condition. This must be modified to maximize the separation and reduce the probability of short circuiting. The proposed inlet into the exiting pond from the proposed cul-de-sac is greater than 16%. This has the potential to accelerate the runoff to the pond and exceed scour velocities. The pipe shall be made shallower and the Walker calculations must demonstrate that scour velocities will not occur at FES 5005. EROSION PREVENTION AND SEDIMENT CONTROL The project exceeds the NPDES permit threshold. The applicant shall prepare a Surface Water Pollution Prevention Plan (SWPPP) and submit to the city for approval prior to the issuance of any permits. No earth disturbing activities may occur until an approved SWPPP is developed. This SWPPP shall be a standalone document consistent with the NPDES Construction Permit and shall contain all required elements as listed in Parts III and IV of the permit. SITE CONSTRAINTS Wetland Protection There exists onsite two wetlands. One wetland exists adjacent to Galpin Boulevard and includes a mitigation area for wetland impacts that occurred with the Lake Harrison development. The other is located at the western limits of the property and also includes a mitigation area. These were delineated in 2008 and were reviewed by city staff this summer to verify that their boundaries have not significantly changed. Any proposed disturbance will be a minimum of 200 feet from the western wetland basin. The easterly wetland is in relatively close proximity to the proposed improvements. Although no impacts are likely to occur from the project, the site must still accommodate the required buffer and setback. The plans should be updated to clearly indicate the wetland boundary and the edge of buffer. Shoreland Management District The property is at least partially within the Shoreland Management District for Lake Harrison. The site must meet the requirements for construction with the Shoreland Management District. ARCHITECTURAL COMPLIANCE The applicant is requesting site plan approval for a 16,950 square-foot water treatment facility. Planning Commission West Water Treatment Plant – Planning Case 2016-21 September 6, 2016 Page 7 of 11 Size Portion Placement The main entrance to the building is located on the south side of the building. The entrance is covered by roof overhang that is raised up from the rest of the roof. The entrance is tucked into a small entry stoop or porch type area. This facility is not intended for general visitor entry. A ten-foot-tall berm is located to the south of the building adjacent to Lake Harrison Road which will screen the parking area. An accessible ramp is located on the west side of the building. Material, Detail and Color The building materials are primarily a reddish-brown brick veneer with tan stone accent bands and columns of cultured stone veneer. The roof material is a gray metal. A hardietrim trim board and facial frame the roof and building interface as well as along the clerestory window band. Precast stone cap stone provides a ledge for the clerestory window band Height and Roof Design Height is limited to three stories or 35 feet in the Single-Family Residential District. The building has stepped roof heights as it moves up the hill with the highest roof peak 21 feet to the top of roof above grade. The building uses prairie roof style with shallow pitches (12:3) and large eves. On the west, north and east elevations of the northern part of the building and over the southern entrance, a small dormer type roof treatment provides addition height and architectural relief to the roof line and building. Facade Transparency This building is not intended for public view so minimal windows are necessary or advisable. Clerestory spandrels windows are provided on all four elevations of the building with a few clear windows to provide natural lighting within the building. Windows are provided at the office/control room area of the building to the north of the main entrance. All other areas shall include landscaping material and architectural detailing and articulation. Planning Commission West Water Treatment Plant – Planning Case 2016-21 September 6, 2016 Page 8 of 11 Site Furnishing The city is providing a trail connection from the park area above to the trail on Galpin Boulevard. The upper area of the site will be developed as a neighborhood park. Loading areas, refuse area, etc. Loading areas are located on the southwest side of the building where the loading dock is located, which is screened from public view by the building orientation, berming and landscaping. No specific outdoor refuse area is proposed. LANDSCAPING Landscaping requirements for the West Water Treatment Plant include bufferyard plantings to the north and foundation plantings around the building. Minimum landscaping requirements are as follows. Landscape Requirement Required plantings Proposed plantings Bufferyard B – 240’ 3 overstory trees 5 understory trees 9 shrubs 3 overstory trees 13 understory trees 5 shrubs The applicant exceeds quantities for understory trees but falls short for the quantity of shrubs. The understory trees are evergreen that provide year round buffering. An increased number of these plantings provide a better buffer than the shrubs. Staff recommends that the proposed buffer plantings be accepted. The applicant is proposing to preserve a number of existing trees on site and use foundation plantings to break up expanses of the building, buffer site lines from various points and create an aesthetically pleasing grounds. The locations of proposed landscape plantings will need to be field located to work around existing trees. Proposed planting will be placed on site in locations that do not conflict with preserved trees. All existing trees proposed to be preserved will be required to have tree protection fencing installed at the driplines or a minimum of 15 feet from the trunk. MISCELLANEOUS The building is required to have an automatic fire extinguishing system. Building plans must be prepared and signed by design professionals licensed in the State of Minnesota. Retaining walls over four high must be designed by a professional engineer and a permit must be obtained prior to Planning Commission West Water Treatment Plant – Planning Case 2016-21 September 6, 2016 Page 9 of 11 construction. Detailed occupancy related requirements will be addressed when complete building plans are submitted. The owner and or their representative shall meet with the Inspections Division as soon as possible to discuss plan review and permit procedures. COMPLIANCE TABLE RSF West Water Treatment Plant Building Height 3 stories 1 story 35 feet 21 feet to roof peak Building Setback N - 30' E - 10' N – 108’ E - 30' W - 10' S - 30' W - 312' S – 144’ Wetland Setback: 20’ buffer 20’ buffer Building 30’ to buffer 50’ to buffer Parking 15’ to buffer 15’ to buffer Parking Stalls 2 6 (One per employee plus one per vehicle normally parked on site.) Parking Setback N - 30’ E - 10' N - 396' E - 72' W - 10’ S - 30' W - 151' S - 120' Hard Surface Coverage 25% 13% Lot Area 0.344 acre 6.27 acres RECOMMENDATION Staff recommends that the Planning Commission approve the subdivision creating one lot and two outlots and site plan for the water treatment facility subject to the following conditions: SUBDIVISION Existing drainage and utility easements on these properties must be vacated prior to recording the final plat. Planning Commission West Water Treatment Plant – Planning Case 2016-21 September 6, 2016 Page 10 of 11 SITE PLAN Building 1. The building is required to have an automatic fire extinguishing system. 2. Building plans must be prepared and signed by design professionals licensed in the State of Minnesota. 3. Retaining walls over four high must be designed by a professional engineer and a permit must be obtained prior to construction. 4. Detailed occupancy related requirements will be addressed when complete building plans are submitted. 5. The owner and or their representative shall meet with the Inspections Division as soon as possible to discuss plan review and permit procedures. Environmental Resources Specialist 1. All existing trees to be preserved shall have tree protection fencing installed at the driplines or a minimum of 15 feet from the trunk, prior to any grading. 2. Proposed landscaping will be field located. Engineering 1. The existing drainage and utility easements must be vacated prior to recording the final plat. 2. Curb and gutter are required around the parking area. 3. An ADA-compliant curb ramp must be installed from the parking area at the Manchester Drive cul-de-sac to the 8-foot wide trail. 4. The following comments must be incorporated into the final grading plan: a) The bottom of wall elevation of the northerly retaining wall is mislabeled (shown as 914.0’, appears to be 1014.0’), and b) The 984’ contour southwest of the parking area is mislabeled (shown as 884’). 5. The Metropolitan Council Environmental Services Sewer Access Charge (Metro SAC) must be paid with the building permit. 6. The West Water Treatment Plant is not subject to the City Sewer Access Charge and Water Access Charge (City SAC and WAC). 7. The applicant shall prepare a Surface Water Pollution Prevention Plan (SWPPP) and submit to the city for approval prior to the issuance of any permits. 8. A stormwater management plan, including a hydraulic and hydrologic model, volume reduction methods, a water quality model (either P8 or MIDS Calculator), and Walker calculations demonstrating adequate capacity within the existing and proposed conveyance system shall be submitted and approved prior to issuance of any permits. 9. The applicant shall submit and receive all applicable permits from the Riley Purgatory Bluff Creek Watershed District prior to commencement of any work on the site. Planning Commission West Water Treatment Plant – Planning Case 2016-21 September 6, 2016 Page 11 of 11 10. The applicant shall submit and receive all applicable permits from the Minnesota Pollution Control Agency prior to commencement of any work on the site. 11. The plans shall be modified to clearly demarcate the wetland boundary and the edge of buffer. 12. A vegetation management plan shall be prepared and submitted for review and approval prior to the issuance of a building permit. 13. The plan shall indicate placement of wetland buffer signs. ATTACHMENTS Findings of Fact and Recommendation Development Review Application Lot Split Sketch Reduced Copy Lake Harrison Plat WSB Project Narrative with Appendices A – D Building Elevation North and West Building Elevations East and South Consortium of HOA’s Questions & Staff Responses dated August 22, 2016 Email messages from Xcel’s Jennifer Abbott & Kim Marinac re: Electric outages in the Lake Harrison neighborhood Public Hearing Notice and Mailing List Jag Reddy Letter Chlorine Plant Accidents List 1998-2013 WISE Phase 3 Water Utility Guidelines Michelle Treptau Email Consortium of HOA Robert Kline Email Email from Arjau K. Chanhassen West Water Treatment Plant Open House Sign Up Form West Water Treatment Plant Project – Open House Comments from Michelle Treptau West Water Treatment Plant Landscape Plan G:\PLAN\2016 Planning Cases\2016-21 West Water Treatment Plant\staff report west water treatment.doc