60-day Review Waiver Emails Generous, Bob
From: Generous, Bob
Sent: Monday, August 13, 2018 3:12 PM
To: 'Cory Watkins'; apoehler@ck-law.com; Hoffman, Todd
Cc: Chad McKenney; Mike LaQua;Jon Donovan (JDonovan@loucksinc.com); Trevor Gruys;
Patrick Schneider (PatrickS@calhouncommercial.com);Jeff Gears;Zach Moen
(ZMoen@loucksinc.com); Aanenson, Kate; Bender, George
Subject: Planning Case #2018-11
Cory,
We are withdrawing your item from the City Council agenda for the meeting this evening (August 13, 2018). The city is
unable to complete the review of the proposed site plan within the 60 day review period so that we can have additional
discussion regarding the retaining walls.
Control Concepts was submitted on June 15, 2018 and the city has 60 days to review the project, which would be August
14, 2018. Since we cannot complete the review by that date, the City of Chanhassen is notifying you that we are taking
the additional 60 days to review the proposed project as permitted by state statute. The review deadline is now
October 13, 2018.
However, our intention is to try and complete our discussion this week, if possible, so that we can reschedule you to the
August 27, 2018 City Council agenda. I will send you a meeting request for this week so that we can discuss this item.
If you have any questions or need additional information, please contact me.
Bob
! Robert Generous, AICP
� 41):
Senior Planner
CITY OF CHANHASSEN
PH. 952.227.1131
i FX. 952.227.1110
s www.ci.chanhassen.mn.us
00
From: Cory Watkins<cwatkins@ccipower.com>
Sent: Friday, August 10, 2018 4:23 PM
To: Generous, Bob<bgenerous@ci.chanhassen.mn.us>; apoehler@ck-law.com; Hoffman,Todd
<thoffman@ci.chanhassen.mn.us>
Cc: Chad McKenney <chad@dmlawltd.com>; Mike LaQua <mike.l@bauerdb.com>; Jon Donovan
(JDonovan@loucksinc.com) <JDonovan@loucksinc.com>; Trevor Gruys<TGruys@loucksinc.com>; Patrick Schneider
(PatrickS@calhouncommercial.com) <PatrickS@calhouncommercial.com>; Jeff Gears<JGears@bdhyoung.com>; Zach
Moen (ZMoen@loucksinc.com) <ZMoen@loucksinc.com>
Subject: Re: Trail Proposal - 8077 Century Blvd. Site.
Thx Bob for the heads up!
Generous, Bob
From: Cory Watkins <cwatkins@ccipower.com>
Sent: Friday, August 31, 2018 10:54 AM
To: Generous, Bob
Subject: RE: Control Concepts
Bob,
This email is to confirm our request to waive the 60 day review requirement mandated by the State for the Control
Concepts site approval, and move agenda item from Sep 10" meeting and reschedule to the October 22"d City Council
meeting.
Thank you for your help.
Cory Watkins
President
Control Concepts Inc.
Tel: (952) 345-6203
Fax: (952)474-6070
WHO POWERS YOUR PROCESS?
-SCR Design Engineering Checklist
-Fusing and Fusekits
-Digital Communication Options
;OA CR. HS( 100kA
-Video Tutorials
Contact us:(952)474-6200 I (800)765-2799 I www.ccipower.com
From: Generous, Bob [mailto:bgenerous@ci,chanhassen.mn.us]
Sent: Friday, August 31, 2018 9:59 AM
To: Cory Watkins
Subject: Control Concepts
Cory,
This item is scheduled to go back to the City Council on Monday September 10, 2018. The report needs to be completed
today and will go out next Wednesday.
I have included a copy of both retaining wall options as well as the cost comparisons table. Is there anything else you
would like me to include in the City Council packet?
Bob