Erhart Farm SWMP EErrhhaarrtt FFaarrmm Storm Water Management Study Chanhassen, MN Prepared For: Black Cherry Development, LLC 14500 Martin Drive, Suite 3000 Eden Prairie, MN 55344 Prepared By: Alliant Engineering, Inc. 733 Marquette Ave, Suite 700 Minneapolis, MN 55402 May 14th, 2021 Erhart Farm _ Stormwater Management Study May 14th, 2021 Alliant Engineering, Inc. Page 1 of 6 200-090 Introduction Included in this report are the materials necessary for review of the proposed stormwater management plan for The Erhart Farm residential development in Chanhassen, Minnesota. This stormwater management plan was designed to meet the rules established by the City of Chanhassen and Riley Purgatory Bluff Creek Watershed District. Background This hydrologic study was conducted to analyze the stormwater treatment requirements for the proposed Erhart Farm development in Chanhassen, Minnesota. The goal of the study is to design stormwater treatment facilities that can handle the increased impervious cover resulting from the new development. This study compares the following two scenarios:  Existing conditions – Wooded with single family residential home.  Proposed conditions –Low Density Single Family Development The area used for modeling stormwater management is 26.545 acres has an existing single-family home and assorted out buildings. Project Area Total Site Area based on boundary (acres) 117.07 Total SWMP Area including Offsite Area (acres) 29.205 Existing Site Impervious (acres) 0.239 Post Construction Site Impervious (acres) 4.67 New (Increase) in Site Impervious Area (acres) 4.431 Total Disturbed Area (acres)* 13.11 *Some disturbed area occurs offsite due to road connection to 96th Street and a portion of existing homes will discharge overland to the pond/filtration basin. The proposed development includes a total of 21 single family lots. The property currently contains topography varying in elevation from 942 ft (high point near west central point of the site) to 876 ft (Wetland 3 edge). Please refer to the preliminary plat submittal plan documents for additional design information on the proposed development. The stormwater management plan for proposed site conditions will meet the guidelines set forth by the City of Chanhassen and RPBCWD regarding stormwater discharge rate control, water quality, and volume abstraction. The plan will also meet rules for erosion and sediment control. The following criterion was used in designing the stormwater management system: Rate Control:  Post-development peak runoff rates from the site for the 2, 10, 100-yr, 10 day-100 yr Snowmelt MSE 3 24-hr storm events must not be greater than the existing condition rates. Erhart Farm _ Stormwater Management Study May 14th, 2021 Alliant Engineering, Inc. Page 2 of 6 200-090  Modeled using separate runoff for each CN per city rules Water Quality:  If the project conforms to the 1.1 inch rule there is no further pollutant removal requirement  No net increase for TSS, TP, and annual volume runoff Infiltration/Volume Control:  Infiltration of stormwater is required for a volume that is equal to or greater than 1.1 inches of runoff from the new impervious area created by the development.  Infiltration should occur within 48 hours or less. Wetland Protection:  Proposed discharge to wetland should not alter the bounce in water level.  Discharge to Wetland must be treated to 90% TSS and 60% TP Runoff Rate Control All rate control calculations have been performed using the SCS method via HydroCAD software. HydroCAD curve numbers were used for all calculations. Three events were modeled including: the 2- year, 10-year and 100-year, 10 day-100 yr Snowmelt event, MSE 3 24-hour storm events with ATLAS-14 precipitation amounts of 2.87, 4.26, 7.38, and 7.20 inches used, respectively. The analysis demonstrates that the proposed peak rates of runoff from the site are equal or less than the pre-development rates for all modeled events. Existing Conditions The existing project area includes a total on-site impervious surface area of 0.788 acres The site currently consists of primarily open space with a single family home, forested areas, and open space. Soil types were determined from the Geotechnical Report (attached in Appendix). Based on given information the site was modeled in HydroCAD with generally D soils. Curve numbers were approximated based on land cover types from aerial photos. Offsite drainage flows through the site due to being downstream of higher ground. Offsite area was included in the design to ensure correct water levels in existing and preserved wetlands. To compare peak discharge rates and volumes for the existing and proposed conditions, flows were analyzed at 2 discharge locations. One location is directly to Wetland 2 and the other is to the Wetland 3. Both discharge locations will be used together to compare peak runoff rates. Refer to existing conditions drainage map and HydroCAD results for additional information and calculations. Erhart Farm _ Stormwater Management Study May 14th, 2021 Alliant Engineering, Inc. Page 3 of 6 200-090 Pre-Development Runoff Rates as calculated by HydroCAD: Rainfall Event Wetland 2 Wetland 3 [cfs] [cfs] 2-year (2.87”) 4.54 47.90 10-year (4.26”) 9.32 96.21 100-year (7.38”) 21.03 213.75 10 day-100 yr Snowmelt 0.43 4.89 Proposed Conditions The proposed development will disturb 21.56 acres and includes a total on-site impervious surface area and offsite disturbed or new impervious of 6.486 acres. The proposed development will use three infiltration basins with pretreatment to provide water quality, rate control, and volume abstraction for the development. This best management practice (BMP) was the best option suitable for site conditions. Rate Control The proposed stormwater management plan decreases the total peak discharge rates to at or below existing conditions for all modeled events. Refer to proposed conditions drainage map and HydroCAD results for additional information and calculations. Post-Development Runoff Rates as calculated by HydroCAD: Rainfall Event Wetland 2 Wetland 3 [cfs] [cfs] 2-year (2.87”) 2.98 14.22 10-year (4.26”) 5.82 48.80 100-year (7.38”) 12.63 82.06 10 day-100 yr Snowmelt 0.28 5.19 See preliminary plat plans for EOF info, HWL’s and OCS structure details. Stormwater Volume Abstraction Volume Required Because the project disturbs more than 50% of the existing site impervious area and increases the overall site impervious area by more than 50%, the total volume required must be a 1.1” abstraction of the entire site impervious area, per RPBCWD rules. Parcel impervious = 203,425 SF (4.67 acres) Required Abstraction for development: 1.1 𝑖𝑛 (𝑎𝑏𝑠𝑡𝑟𝑎𝑐𝑡𝑖𝑜𝑛)∗ଵ ௙௧ ଵଶ ௜௡ ∗ (203,425 𝑠𝑓) = 18,647 𝒄𝒇 Volume Provided Due to the clay soils present on site infiltration is not feasible. The project will meet the 90% TSS removal and the 60% TP removal and the no net increase in TSS and TP. The filtration basin is located Erhart Farm _ Stormwater Management Study May 14th, 2021 Alliant Engineering, Inc. Page 4 of 6 200-090 adjacent to Wetland 3. For calculation purposes, the basin was modeled using soils with an filtration rate of 0.8 in/hr. See table below for filtration depth in each basin. OCS to be constructed to control release of runoff and set filtration depths. See planset for OCS details. The filtration basin maintains 3’ separation from groundwater levels per MPCA requirements. See planset and Geotech report for further details. Infiltration Volume Summary Basin Volume Required Volume Provided Depth Infiltration Rate Drawdown Time IB-1 18,647 CF 33,497 CF 0.69 ft (8.28 in) 0.8 in/hr 10.38 hrs Water Quality Water quality was modeled in MIDS to meet both watershed and city requirements for nutrient removal. Additionally, sump manholes and baffles will be installed in the structures immediately upstream of the pond before discharging to pond. MIDS was used to model to show No net increase in TP, TSS and Annual Volume* for BMP’s. Additionally, to be conservative sumps and baffles were not modeled in MIDS. See MIDS results in Appendix. *Annual volume was modeled however due to clay soils it was not met. Summary of MIDS results: TSS Loading (lbs) TP Loading (lbs) Annual Volume (acre-ft) Existing* 661.6 3.64 4.4619 Proposed* 139.4 3.425 13.7725 Removal % 95% 77% *Does not consider any offsite runoff where area is undisturbed in proposed conditions NURP Volume Calculation The development utilizes a NURP pond for pretreatment prior to discharge to the filtration area. The pond will be sized based on the city and watershed criteria. Summary of MIDS results: NURP Volume Required (AC-FT) NURP Volume Required (AC-FT) Pond 1.821 2.627 *Does not consider any offsite runoff where area is undisturbed in proposed conditions Erhart Farm _ Stormwater Management Study May 14th, 2021 Alliant Engineering, Inc. Page 5 of 6 200-090 Wetland Protection: As shown when discussing proposed runoff, rates going to the wetland will be below existing rates for the 2-, 10-, 100-year events and 10 day-100 year snowmelt. Additionally the pond/filtration basin will be the primary outlet for stormwater, which meets the required phosphorus and TSS removal efficiency required for the wetland and does not directly discharge to the wetland. Direct discharge to the wetland will only occur as part of disconnected rooftops. Erosion and Sediment Control Plan The following Best Management Practices (BMP’s) are proposed for the project. Temporary erosion control devices shown on the grading plan to provide sediment control during project construction include:  Silt fence  Rock construction entrance  Inlet sediment barriers at catch basins  Diversion berms  Erosion Control Blanket Permanent erosion control devices shown to be installed include:  Rip rap at storm sewer pipe outlets  Turf reinforcement mat at emergency spillways  Turf establishment including seeding, sodding, vegetation, etc. Conclusion Alliant Engineering believes that the proposed stormwater management plan is acceptable for all parties involved. The total proposed peak discharge rates for the 2-year, 10-year, 100-year and 10 day-100 yr snowmelt 24-hour storm events will be matched or reduced from existing conditions modeled rates. The proposed stormwater management system meets the volume abstraction requirements with the use of a pond/filtration basin. Water quality requirements are provided through the same pond/filtration basin and provide the TP and TSS removal efficiencies required. The proposed grading and erosion control plan will utilize BMPs whenever possible to provide adequate erosion control measures to prevent erosion and contain sediment during construction. Please call me at 612-767-9356 with any questions or comments regarding storm water issues for The Erhart Farm development project. Sincerely, Seth Loken, PE Alliant Engineering, Inc. CC: File 200-090 Black Cherry Development Erhart Farm _ Stormwater Management Study May 14th, 2021 Alliant Engineering, Inc. Page 6 of 6 200-090 APPENDIX - Existing Conditions Drainage & Cover Map - Existing Conditions - HydroCAD Results - Proposed Conditions Drainage & Cover Map - Proposed Conditions – HydroCAD Results - MIDS Results - Storm sewer Sizing Spreadsheet - Geotechnical Report S00°28'49"E 290.40 S89°34'34"W 633.00S00°28'49"E 290.40 S89°34'34"W 150.00N00°28'49"W 290.40 S89°34'34"W 300.00S89°53'00"E 514.70(M)N00°02'05"W167.28N48°05'58"W61.09N00°02'05"W201.86 N00°28'49"W 290.40 N89°34'34"E 447.59N41°54'02"E134.40R=330.00L=66.00=11°27'30"C.Brg=N42°22'13"WC=65.89R=703.00L=435.88Δ=35°31'29"N54°55'43"W 515.59R=635.83L=195.96Δ=17°39'30"R=358.31L=237.58Δ=37°59'27"R=1069.13L=138.63Δ=7°25'46"S64°26'53"E 10.91EXCEPTIONEAGLE RIDGE ROADTEMPORARYCUL-DE-SACSTATE TRUNK HWY. NO. 101(GREAT PLAINS BLVD.)96TH STREETERHART FARM EXISTING CONDITIONS DRAINAGE MAP 733 Marquette AvenueMinneapolis, MN 55402612.758.3080www.alliant-inc.comSuite 700FOR REVIEW ONLYPRELIMINARYNOT FOR CONSTRUCTION LEGEND E-1 NORTHEAST AREA E-2 SOUTH AREAOFF-1 SOUTH OFFSITE W-2 WETLAND 2 W-3 WETLAND 3 Routing Diagram for 20090edrn Prepared by {enter your company name here}, Printed 5/14/2021 HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcat Reach Pond Link 20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 2HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Area Listing (all nodes) Area (acres) CN Description (subcatchment-numbers) 1.650 80 >75% Grass cover, Good, HSG D (OFF-1) 0.788 98 Impervious, HSG D (E-2) 0.603 98 Paved roads w/curbs & sewers, HSG D (OFF-1) 24.822 77 Woods, Good, HSG D (E-1, E-2) 27.863 78 TOTAL AREA 20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 3HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Soil Listing (all nodes) Area (acres) Soil Group Subcatchment Numbers 0.000 HSG A 0.000 HSG B 0.000 HSG C 27.863 HSG D E-1, E-2, OFF-1 0.000 Other 27.863 TOTAL AREA MSE 24-hr 3 2-Year Rainfall=2.87"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 4HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Time span=0.00-400.00 hrs, dt=0.01 hrs, 40001 points Runoff by SCS TR-20 method, UH=SCS, Weighted-CN Reach routing by Dyn-Stor-Ind method - Pond routing by Dyn-Stor-Ind method Runoff Area=2.260 ac 0.00% Impervious Runoff Depth=0.98"Subcatchment E-1: NORTHEAST AREA Flow Length=282' Slope=0.0975 '/' Tc=4.0 min CN=77 Runoff=4.54 cfs 0.185 af Runoff Area=23.350 ac 3.37% Impervious Runoff Depth=1.04"Subcatchment E-2: SOUTH AREA Flow Length=520' Slope=0.0730 '/' Tc=7.4 min CN=78 Runoff=42.00 cfs 2.018 af Runoff Area=2.253 ac 26.76% Impervious Runoff Depth=1.48"Subcatchment OFF-1: SOUTH OFFSITE Tc=7.0 min CN=85 Runoff=5.93 cfs 0.278 af Inflow=4.54 cfs 0.185 afLink W-2: WETLAND 2 Primary=4.54 cfs 0.185 af Inflow=47.90 cfs 2.296 afLink W-3: WETLAND 3 Primary=47.90 cfs 2.296 af Total Runoff Area = 27.863 ac Runoff Volume = 2.481 af Average Runoff Depth = 1.07" 95.01% Pervious = 26.472 ac 4.99% Impervious = 1.391 ac MSE 24-hr 3 2-Year Rainfall=2.87"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 5HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment E-1: NORTHEAST AREA Runoff = 4.54 cfs @ 12.12 hrs, Volume= 0.185 af, Depth= 0.98" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs MSE 24-hr 3 2-Year Rainfall=2.87" Area (ac) CN Description 2.260 77 Woods, Good, HSG D 2.260 100.00% Pervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 4.0 282 0.0975 1.16 Lag/CN Method, Summary for Subcatchment E-2: SOUTH AREA Runoff = 42.00 cfs @ 12.15 hrs, Volume= 2.018 af, Depth= 1.04" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs MSE 24-hr 3 2-Year Rainfall=2.87" Area (ac) CN Description 22.562 77 Woods, Good, HSG D * 0.788 98 Impervious, HSG D 23.350 78 Weighted Average 22.562 96.63% Pervious Area 0.788 3.37% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.4 520 0.0730 1.17 Lag/CN Method, Summary for Subcatchment OFF-1: SOUTH OFFSITE Runoff = 5.93 cfs @ 12.14 hrs, Volume= 0.278 af, Depth= 1.48" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs MSE 24-hr 3 2-Year Rainfall=2.87" Area (ac) CN Description 1.650 80 >75% Grass cover, Good, HSG D 0.603 98 Paved roads w/curbs & sewers, HSG D 2.253 85 Weighted Average 1.650 73.24% Pervious Area 0.603 26.76% Impervious Area MSE 24-hr 3 2-Year Rainfall=2.87"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 6HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Link W-2: WETLAND 2 Inflow Area = 2.260 ac, 0.00% Impervious, Inflow Depth = 0.98" for 2-Year event Inflow = 4.54 cfs @ 12.12 hrs, Volume= 0.185 af Primary = 4.54 cfs @ 12.12 hrs, Volume= 0.185 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs Summary for Link W-3: WETLAND 3 Inflow Area = 25.603 ac, 5.43% Impervious, Inflow Depth = 1.08" for 2-Year event Inflow = 47.90 cfs @ 12.15 hrs, Volume= 2.296 af Primary = 47.90 cfs @ 12.15 hrs, Volume= 2.296 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 7HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Time span=0.00-400.00 hrs, dt=0.01 hrs, 40001 points Runoff by SCS TR-20 method, UH=SCS, Weighted-CN Reach routing by Dyn-Stor-Ind method - Pond routing by Dyn-Stor-Ind method Runoff Area=2.260 ac 0.00% Impervious Runoff Depth=6.96"Subcatchment E-1: NORTHEAST AREA Flow Length=282' Slope=0.0975 '/' Tc=4.0 min AMC Adjusted CN=98 Runoff=0.43 cfs 1.311 af Runoff Area=23.350 ac 3.37% Impervious Runoff Depth=6.96"Subcatchment E-2: SOUTH AREA Flow Length=520' Slope=0.0730 '/' Tc=7.4 min AMC Adjusted CN=98 Runoff=4.46 cfs 13.544 af Runoff Area=2.253 ac 26.76% Impervious Runoff Depth=6.96"Subcatchment OFF-1: SOUTH OFFSITE Tc=7.0 min AMC Adjusted CN=98 Runoff=0.43 cfs 1.307 af Inflow=0.43 cfs 1.311 afLink W-2: WETLAND 2 Primary=0.43 cfs 1.311 af Inflow=4.89 cfs 14.851 afLink W-3: WETLAND 3 Primary=4.89 cfs 14.851 af Total Runoff Area = 27.863 ac Runoff Volume = 16.162 af Average Runoff Depth = 6.96" 95.01% Pervious = 26.472 ac 4.99% Impervious = 1.391 ac Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 8HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment E-1: NORTHEAST AREA Runoff = 0.43 cfs @ 121.23 hrs, Volume= 1.311 af, Depth= 6.96" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=4 Area (ac) CN Adj Description 2.260 77 Woods, Good, HSG D 2.260 77 98 Weighted Average, AMC Adjusted 2.260 100.00% Pervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 4.0 282 0.0975 1.16 Lag/CN Method, Summary for Subcatchment E-2: SOUTH AREA Runoff = 4.46 cfs @ 121.27 hrs, Volume= 13.544 af, Depth= 6.96" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=4 Area (ac) CN Adj Description 22.562 77 Woods, Good, HSG D * 0.788 98 Impervious, HSG D 23.350 78 98 Weighted Average, AMC Adjusted 22.562 96.63% Pervious Area 0.788 3.37% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.4 520 0.0730 1.17 Lag/CN Method, Summary for Subcatchment OFF-1: SOUTH OFFSITE Runoff = 0.43 cfs @ 121.26 hrs, Volume= 1.307 af, Depth= 6.96" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=4 Area (ac) CN Adj Description 1.650 80 >75% Grass cover, Good, HSG D 0.603 98 Paved roads w/curbs & sewers, HSG D 2.253 85 98 Weighted Average, AMC Adjusted 1.650 73.24% Pervious Area 0.603 26.76% Impervious Area Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 9HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Link W-2: WETLAND 2 Inflow Area = 2.260 ac, 0.00% Impervious, Inflow Depth = 6.96" for 10 day-100 Yr Snow event Inflow = 0.43 cfs @ 121.23 hrs, Volume= 1.311 af Primary = 0.43 cfs @ 121.23 hrs, Volume= 1.311 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs Summary for Link W-3: WETLAND 3 Inflow Area = 25.603 ac, 5.43% Impervious, Inflow Depth = 6.96" for 10 day-100 Yr Snow event Inflow = 4.89 cfs @ 121.27 hrs, Volume= 14.851 af Primary = 4.89 cfs @ 121.27 hrs, Volume= 14.851 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs MSE 24-hr 3 10-Year Rainfall=4.26"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 10HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Time span=0.00-400.00 hrs, dt=0.01 hrs, 40001 points Runoff by SCS TR-20 method, UH=SCS, Weighted-CN Reach routing by Dyn-Stor-Ind method - Pond routing by Dyn-Stor-Ind method Runoff Area=2.260 ac 0.00% Impervious Runoff Depth=2.02"Subcatchment E-1: NORTHEAST AREA Flow Length=282' Slope=0.0975 '/' Tc=4.0 min CN=77 Runoff=9.32 cfs 0.380 af Runoff Area=23.350 ac 3.37% Impervious Runoff Depth=2.10"Subcatchment E-2: SOUTH AREA Flow Length=520' Slope=0.0730 '/' Tc=7.4 min CN=78 Runoff=85.65 cfs 4.079 af Runoff Area=2.253 ac 26.76% Impervious Runoff Depth=2.69"Subcatchment OFF-1: SOUTH OFFSITE Tc=7.0 min CN=85 Runoff=10.61 cfs 0.505 af Inflow=9.32 cfs 0.380 afLink W-2: WETLAND 2 Primary=9.32 cfs 0.380 af Inflow=96.21 cfs 4.584 afLink W-3: WETLAND 3 Primary=96.21 cfs 4.584 af Total Runoff Area = 27.863 ac Runoff Volume = 4.964 af Average Runoff Depth = 2.14" 95.01% Pervious = 26.472 ac 4.99% Impervious = 1.391 ac MSE 24-hr 3 10-Year Rainfall=4.26"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 11HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment E-1: NORTHEAST AREA Runoff = 9.32 cfs @ 12.12 hrs, Volume= 0.380 af, Depth= 2.02" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs MSE 24-hr 3 10-Year Rainfall=4.26" Area (ac) CN Description 2.260 77 Woods, Good, HSG D 2.260 100.00% Pervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 4.0 282 0.0975 1.16 Lag/CN Method, Summary for Subcatchment E-2: SOUTH AREA Runoff = 85.65 cfs @ 12.15 hrs, Volume= 4.079 af, Depth= 2.10" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs MSE 24-hr 3 10-Year Rainfall=4.26" Area (ac) CN Description 22.562 77 Woods, Good, HSG D * 0.788 98 Impervious, HSG D 23.350 78 Weighted Average 22.562 96.63% Pervious Area 0.788 3.37% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.4 520 0.0730 1.17 Lag/CN Method, Summary for Subcatchment OFF-1: SOUTH OFFSITE Runoff = 10.61 cfs @ 12.14 hrs, Volume= 0.505 af, Depth= 2.69" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs MSE 24-hr 3 10-Year Rainfall=4.26" Area (ac) CN Description 1.650 80 >75% Grass cover, Good, HSG D 0.603 98 Paved roads w/curbs & sewers, HSG D 2.253 85 Weighted Average 1.650 73.24% Pervious Area 0.603 26.76% Impervious Area MSE 24-hr 3 10-Year Rainfall=4.26"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 12HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Link W-2: WETLAND 2 Inflow Area = 2.260 ac, 0.00% Impervious, Inflow Depth = 2.02" for 10-Year event Inflow = 9.32 cfs @ 12.12 hrs, Volume= 0.380 af Primary = 9.32 cfs @ 12.12 hrs, Volume= 0.380 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs Summary for Link W-3: WETLAND 3 Inflow Area = 25.603 ac, 5.43% Impervious, Inflow Depth = 2.15" for 10-Year event Inflow = 96.21 cfs @ 12.15 hrs, Volume= 4.584 af Primary = 96.21 cfs @ 12.15 hrs, Volume= 4.584 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs MSE 24-hr 3 100-Year Rainfall=7.38"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 13HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Time span=0.00-400.00 hrs, dt=0.01 hrs, 40001 points Runoff by SCS TR-20 method, UH=SCS, Weighted-CN Reach routing by Dyn-Stor-Ind method - Pond routing by Dyn-Stor-Ind method Runoff Area=2.260 ac 0.00% Impervious Runoff Depth=4.71"Subcatchment E-1: NORTHEAST AREA Flow Length=282' Slope=0.0975 '/' Tc=4.0 min CN=77 Runoff=21.03 cfs 0.887 af Runoff Area=23.350 ac 3.37% Impervious Runoff Depth=4.82"Subcatchment E-2: SOUTH AREA Flow Length=520' Slope=0.0730 '/' Tc=7.4 min CN=78 Runoff=192.52 cfs 9.381 af Runoff Area=2.253 ac 26.76% Impervious Runoff Depth=5.62"Subcatchment OFF-1: SOUTH OFFSITE Tc=7.0 min CN=85 Runoff=21.29 cfs 1.055 af Inflow=21.03 cfs 0.887 afLink W-2: WETLAND 2 Primary=21.03 cfs 0.887 af Inflow=213.75 cfs 10.435 afLink W-3: WETLAND 3 Primary=213.75 cfs 10.435 af Total Runoff Area = 27.863 ac Runoff Volume = 11.322 af Average Runoff Depth = 4.88" 95.01% Pervious = 26.472 ac 4.99% Impervious = 1.391 ac MSE 24-hr 3 100-Year Rainfall=7.38"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 14HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment E-1: NORTHEAST AREA Runoff = 21.03 cfs @ 12.12 hrs, Volume= 0.887 af, Depth= 4.71" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs MSE 24-hr 3 100-Year Rainfall=7.38" Area (ac) CN Description 2.260 77 Woods, Good, HSG D 2.260 100.00% Pervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 4.0 282 0.0975 1.16 Lag/CN Method, Summary for Subcatchment E-2: SOUTH AREA Runoff = 192.52 cfs @ 12.15 hrs, Volume= 9.381 af, Depth= 4.82" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs MSE 24-hr 3 100-Year Rainfall=7.38" Area (ac) CN Description 22.562 77 Woods, Good, HSG D * 0.788 98 Impervious, HSG D 23.350 78 Weighted Average 22.562 96.63% Pervious Area 0.788 3.37% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.4 520 0.0730 1.17 Lag/CN Method, Summary for Subcatchment OFF-1: SOUTH OFFSITE Runoff = 21.29 cfs @ 12.14 hrs, Volume= 1.055 af, Depth= 5.62" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs MSE 24-hr 3 100-Year Rainfall=7.38" Area (ac) CN Description 1.650 80 >75% Grass cover, Good, HSG D 0.603 98 Paved roads w/curbs & sewers, HSG D 2.253 85 Weighted Average 1.650 73.24% Pervious Area 0.603 26.76% Impervious Area MSE 24-hr 3 100-Year Rainfall=7.38"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 15HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Link W-2: WETLAND 2 Inflow Area = 2.260 ac, 0.00% Impervious, Inflow Depth = 4.71" for 100-Year event Inflow = 21.03 cfs @ 12.12 hrs, Volume= 0.887 af Primary = 21.03 cfs @ 12.12 hrs, Volume= 0.887 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs Summary for Link W-3: WETLAND 3 Inflow Area = 25.603 ac, 5.43% Impervious, Inflow Depth = 4.89" for 100-Year event Inflow = 213.75 cfs @ 12.15 hrs, Volume= 10.435 af Primary = 213.75 cfs @ 12.15 hrs, Volume= 10.435 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-400.00 hrs, dt= 0.01 hrs Table of Contents20090edrn Printed 5/14/2021Prepared by {enter your company name here} HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC TABLE OF CONTENTS Project Reports 1 Routing Diagram 2 Area Listing (all nodes) 3 Soil Listing (all nodes) 2-Year Event 4 Node Listing 5 Subcat E-1: NORTHEAST AREA 6 Subcat E-2: SOUTH AREA 6 Subcat OFF-1: SOUTH OFFSITE 7 Link W-2: WETLAND 2 7 Link W-3: WETLAND 3 10 day-100 Yr Snow Event 7 Node Listing 8 Subcat E-1: NORTHEAST AREA 9 Subcat E-2: SOUTH AREA 9 Subcat OFF-1: SOUTH OFFSITE 10 Link W-2: WETLAND 2 10 Link W-3: WETLAND 3 10-Year Event 10 Node Listing 11 Subcat E-1: NORTHEAST AREA 12 Subcat E-2: SOUTH AREA 12 Subcat OFF-1: SOUTH OFFSITE 13 Link W-2: WETLAND 2 13 Link W-3: WETLAND 3 100-Year Event 13 Node Listing 14 Subcat E-1: NORTHEAST AREA 15 Subcat E-2: SOUTH AREA 15 Subcat OFF-1: SOUTH OFFSITE 16 Link W-2: WETLAND 2 16 Link W-3: WETLAND 3 E-1 NORTHEAST AREA E-2 SOUTH AREAOFF-1 SOUTH OFFSITE W-2 WETLAND 2 W-3 WETLAND 3 Routing Diagram for 20090edrn Prepared by {enter your company name here}, Printed 5/14/2021 HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcat Reach Pond Link MSE 24-hr 3 2-Year Rainfall=2.87"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 2HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment E-1: NORTHEAST AREA Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)5 4 3 2 1 0 MSE 24-hr 3 2-Year Rainfall=2.87" Runoff Area=2.260 ac Runoff Volume=0.185 af Runoff Depth=0.98" Flow Length=282' Slope=0.0975 '/' Tc=4.0 min CN=77 4.54 cfs Subcatchment E-2: SOUTH AREA Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)46 44 42 40 38 36 34 32 30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0 MSE 24-hr 3 2-Year Rainfall=2.87" Runoff Area=23.350 ac Runoff Volume=2.018 af Runoff Depth=1.04" Flow Length=520' Slope=0.0730 '/' Tc=7.4 min CN=78 42.00 cfs MSE 24-hr 3 2-Year Rainfall=2.87"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 3HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment OFF-1: SOUTH OFFSITE Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)6 5 4 3 2 1 0 MSE 24-hr 3 2-Year Rainfall=2.87" Runoff Area=2.253 ac Runoff Volume=0.278 af Runoff Depth=1.48" Tc=7.0 min CN=85 5.93 cfs Link W-2: WETLAND 2 Inflow Primary Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)5 4 3 2 1 0 Inflow Area=2.260 ac 4.54 cfs4.54 cfs MSE 24-hr 3 2-Year Rainfall=2.87"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 4HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Link W-3: WETLAND 3 Inflow Primary Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)52 50 48 46 44 42 40 38 36 34 32 30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0 Inflow Area=25.603 ac 47.90 cfs47.90 cfs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 5HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment E-1: NORTHEAST AREA Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)0.48 0.46 0.44 0.42 0.4 0.38 0.36 0.34 0.32 0.3 0.28 0.26 0.24 0.22 0.2 0.18 0.16 0.14 0.12 0.1 0.08 0.06 0.04 0.02 0 Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20" AMC=4 Runoff Area=2.260 ac Runoff Volume=1.311 af Runoff Depth=6.96" Flow Length=282' Slope=0.0975 '/' Tc=4.0 min AMC Adjusted CN=98 0.43 cfs Subcatchment E-2: SOUTH AREA Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)4 3 2 1 0 Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20" AMC=4 Runoff Area=23.350 ac Runoff Volume=13.544 af Runoff Depth=6.96" Flow Length=520' Slope=0.0730 '/' Tc=7.4 min AMC Adjusted CN=98 4.46 cfs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 6HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment OFF-1: SOUTH OFFSITE Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)0.48 0.46 0.44 0.42 0.4 0.38 0.36 0.34 0.32 0.3 0.28 0.26 0.24 0.22 0.2 0.18 0.16 0.14 0.12 0.1 0.08 0.06 0.04 0.02 0 Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20" AMC=4 Runoff Area=2.253 ac Runoff Volume=1.307 af Runoff Depth=6.96" Tc=7.0 min AMC Adjusted CN=98 0.43 cfs Link W-2: WETLAND 2 Inflow Primary Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)0.48 0.46 0.44 0.42 0.4 0.38 0.36 0.34 0.32 0.3 0.28 0.26 0.24 0.22 0.2 0.18 0.16 0.14 0.12 0.1 0.08 0.06 0.04 0.02 0 Inflow Area=2.260 ac 0.43 cfs0.43 cfs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 7HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Link W-3: WETLAND 3 Inflow Primary Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)5 4 3 2 1 0 Inflow Area=25.603 ac 4.89 cfs4.89 cfs MSE 24-hr 3 10-Year Rainfall=4.26"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 8HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment E-1: NORTHEAST AREA Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)10 9 8 7 6 5 4 3 2 1 0 MSE 24-hr 3 10-Year Rainfall=4.26" Runoff Area=2.260 ac Runoff Volume=0.380 af Runoff Depth=2.02" Flow Length=282' Slope=0.0975 '/' Tc=4.0 min CN=77 9.32 cfs Subcatchment E-2: SOUTH AREA Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0 MSE 24-hr 3 10-Year Rainfall=4.26" Runoff Area=23.350 ac Runoff Volume=4.079 af Runoff Depth=2.10" Flow Length=520' Slope=0.0730 '/' Tc=7.4 min CN=78 85.65 cfs MSE 24-hr 3 10-Year Rainfall=4.26"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 9HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment OFF-1: SOUTH OFFSITE Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)11 10 9 8 7 6 5 4 3 2 1 0 MSE 24-hr 3 10-Year Rainfall=4.26" Runoff Area=2.253 ac Runoff Volume=0.505 af Runoff Depth=2.69" Tc=7.0 min CN=85 10.61 cfs Link W-2: WETLAND 2 Inflow Primary Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)10 9 8 7 6 5 4 3 2 1 0 Inflow Area=2.260 ac 9.32 cfs9.32 cfs MSE 24-hr 3 10-Year Rainfall=4.26"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 10HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Link W-3: WETLAND 3 Inflow Primary Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)105 100 95 90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0 Inflow Area=25.603 ac 96.21 cfs96.21 cfs MSE 24-hr 3 100-Year Rainfall=7.38"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 11HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment E-1: NORTHEAST AREA Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 MSE 24-hr 3 100-Year Rainfall=7.38" Runoff Area=2.260 ac Runoff Volume=0.887 af Runoff Depth=4.71" Flow Length=282' Slope=0.0975 '/' Tc=4.0 min CN=77 21.03 cfs Subcatchment E-2: SOUTH AREA Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)210 200 190 180 170 160 150 140 130 120 110 100 90 80 70 60 50 40 30 20 10 0 MSE 24-hr 3 100-Year Rainfall=7.38" Runoff Area=23.350 ac Runoff Volume=9.381 af Runoff Depth=4.82" Flow Length=520' Slope=0.0730 '/' Tc=7.4 min CN=78 192.52 cfs MSE 24-hr 3 100-Year Rainfall=7.38"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 12HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment OFF-1: SOUTH OFFSITE Runoff Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 MSE 24-hr 3 100-Year Rainfall=7.38" Runoff Area=2.253 ac Runoff Volume=1.055 af Runoff Depth=5.62" Tc=7.0 min CN=85 21.29 cfs Link W-2: WETLAND 2 Inflow Primary Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 Inflow Area=2.260 ac 21.03 cfs21.03 cfs MSE 24-hr 3 100-Year Rainfall=7.38"20090edrn Printed 5/14/2021Prepared by {enter your company name here} Page 13HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Link W-3: WETLAND 3 Inflow Primary Hydrograph Time (hours) 400380360340320300280260240220200180160140120100806040200Flow (cfs)230 220 210 200 190 180 170 160 150 140 130 120 110 100 90 80 70 60 50 40 30 20 10 0 Inflow Area=25.603 ac 213.75 cfs213.75 cfs Table of Contents20090edrn Printed 5/14/2021Prepared by {enter your company name here} HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC TABLE OF CONTENTS Project Reports 1 Routing Diagram 2-Year Event 2 Subcat E-1: NORTHEAST AREA 3 Subcat E-2: SOUTH AREA 3 Subcat OFF-1: SOUTH OFFSITE 4 Link W-2: WETLAND 2 4 Link W-3: WETLAND 3 10 day-100 Yr Snow Event 5 Subcat E-1: NORTHEAST AREA 6 Subcat E-2: SOUTH AREA 6 Subcat OFF-1: SOUTH OFFSITE 7 Link W-2: WETLAND 2 7 Link W-3: WETLAND 3 10-Year Event 8 Subcat E-1: NORTHEAST AREA 9 Subcat E-2: SOUTH AREA 9 Subcat OFF-1: SOUTH OFFSITE 10 Link W-2: WETLAND 2 10 Link W-3: WETLAND 3 100-Year Event 11 Subcat E-1: NORTHEAST AREA 12 Subcat E-2: SOUTH AREA 12 Subcat OFF-1: SOUTH OFFSITE 13 Link W-2: WETLAND 2 13 Link W-3: WETLAND 3 WETLAND 3WETLAND 211032456789BLOCK 1OUTLOT AWETLAND 411121314151617423INF/PONDINF/POND15OUTLOT BOUTLOT EOUTLOT DOUTLOT BOUTLOT BBLOCK 1 BLOCK 2 B L O C K 1 OUTLOT C EAGLE RIDGE WAY EAGLE RIDGE ROADEAGLE RIDGE ROAD96TH STREETS00°28'49"E 290.40 S89°34'34"W 633.00S00°28'49"E 290.40 S89°34'34"W 150.00N00°28'49"W 290.40 S89°34'34"W 300.00S89°53'00"E 514.70(M)N00°02'05"W167.28N48°05'58"W61.09N00°02'05"W201.86 N00°28'49"W 290.40 N89°34'34"E 447.59N41°54'02"E134.40R=330.00L=66.00=11°27'30"C.Brg=N42°22'13"WC=65.89R=703.00L=435.88Δ=35°31'29"N54°55'43"W 515.59R=635.83L=195.96Δ=17°39'30"R=358.31L=237.58Δ=37°59'27"R=1069.13L=138.63Δ=7°25'46"S64°26'53"E 10.91EXCEPTIONEAGLE RIDGE ROADTEMPORARYCUL-DE-SACSTATE TRUNK HWY. NO. 101(GREAT PLAINS BLVD.)96TH STREETERHART FARM PROPOSED CONDITIONS DRAINAGE MAP 733 Marquette AvenueMinneapolis, MN 55402612.758.3080www.alliant-inc.comSuite 700FOR REVIEW ONLYPRELIMINARYNOT FOR CONSTRUCTION LEGEND 1S 1S 2S 2S 3S 3S OFF-1 SOUTH OFFSITE 2P Pond/Filtration Shelf W-2 Wetland 2 W-3 Wetland 3 Routing Diagram for 20090pdrn Prepared by {enter your company name here}, Printed 5/14/2021 HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcat Reach Pond Link 20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 2HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Area Listing (selected nodes) Area (acres) CN Description (subcatchment-numbers) 15.575 80 >75% Grass cover, Good, HSG D (1S, 2S, 3S, OFF-1) 0.239 98 Existing Impervious, HSG D (1S) 0.603 98 Paved roads w/curbs & sewers, HSG D (OFF-1) 3.769 98 Proposed Impervious, HSG D (1S) 0.662 98 Unconnected roofs, HSG D (2S, 3S) 8.357 77 Woods, Good, HSG D (1S, 2S, 3S) 29.205 82 TOTAL AREA 20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 3HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Soil Listing (selected nodes) Area (acres) Soil Group Subcatchment Numbers 0.000 HSG A 0.000 HSG B 0.000 HSG C 29.205 HSG D 1S, 2S, 3S, OFF-1 0.000 Other 29.205 TOTAL AREA MSE 24-hr 3 2-Year Rainfall=2.87"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 4HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Time span=0.00-300.00 hrs, dt=0.01 hrs, 30001 points Runoff by SCS TR-20 method, UH=SCS, Weighted-CN Reach routing by Dyn-Stor-Ind method - Pond routing by Dyn-Stor-Ind method Runoff Area=20.693 ac 19.37% Impervious Runoff Depth=1.34"Subcatchment 1S: 1S Flow Length=160' Slope=0.0200 '/' Tc=11.8 min CN=83 Runoff=40.14 cfs 2.315 af Runoff Area=4.402 ac 10.25% Impervious Runoff Depth=1.09"Subcatchment 2S: 2S Tc=7.0 min UI Adjusted CN=79 Runoff=8.55 cfs 0.401 af Runoff Area=1.450 ac 14.55% Impervious Runoff Depth=1.15"Subcatchment 3S: 3S Tc=7.0 min UI Adjusted CN=80 Runoff=2.98 cfs 0.139 af Runoff Area=2.660 ac 22.67% Impervious Runoff Depth=1.41"Subcatchment OFF-1: SOUTH OFFSITE Tc=7.0 min CN=84 Runoff=6.69 cfs 0.313 af Peak Elev=883.08' Storage=4.202 af Inflow=45.32 cfs 2.628 afPond 2P: Pond/Filtration Shelf Outflow=12.57 cfs 2.408 af Inflow=2.98 cfs 0.139 afLink W-2: Wetland 2 Primary=2.98 cfs 0.139 af Inflow=14.22 cfs 2.809 afLink W-3: Wetland 3 Primary=14.22 cfs 2.809 af Total Runoff Area = 29.205 ac Runoff Volume = 3.169 af Average Runoff Depth = 1.30" 81.94% Pervious = 23.932 ac 18.06% Impervious = 5.273 ac MSE 24-hr 3 2-Year Rainfall=2.87"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 5HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment 1S: 1S Runoff = 40.14 cfs @ 12.20 hrs, Volume= 2.315 af, Depth= 1.34" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 2-Year Rainfall=2.87" Area (ac) CN Description 11.036 80 >75% Grass cover, Good, HSG D * 3.769 98 Proposed Impervious, HSG D * 0.239 98 Existing Impervious, HSG D 5.649 77 Woods, Good, HSG D 20.693 83 Weighted Average 16.685 80.63% Pervious Area 4.008 19.37% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 10.3 100 0.0200 0.16 Sheet Flow, Grass: Short n= 0.150 P2= 2.87" 0.5 60 0.0200 2.12 Shallow Concentrated Flow, Grassed Waterway Kv= 15.0 fps 1.0 Direct Entry, Pipe Flow 11.8 160 Total Summary for Subcatchment 2S: 2S Runoff = 8.55 cfs @ 12.15 hrs, Volume= 0.401 af, Depth= 1.09" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 2-Year Rainfall=2.87" Area (ac) CN Adj Description 1.865 80 >75% Grass cover, Good, HSG D 0.451 98 Unconnected roofs, HSG D 2.086 77 Woods, Good, HSG D 4.402 80 79 Weighted Average, UI Adjusted 3.951 89.75% Pervious Area 0.451 10.25% Impervious Area 0.451 100.00% Unconnected Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, MSE 24-hr 3 2-Year Rainfall=2.87"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 6HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment 3S: 3S Runoff = 2.98 cfs @ 12.15 hrs, Volume= 0.139 af, Depth= 1.15" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 2-Year Rainfall=2.87" Area (ac) CN Adj Description 0.617 80 >75% Grass cover, Good, HSG D 0.211 98 Unconnected roofs, HSG D 0.622 77 Woods, Good, HSG D 1.450 81 80 Weighted Average, UI Adjusted 1.239 85.45% Pervious Area 0.211 14.55% Impervious Area 0.211 100.00% Unconnected Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Subcatchment OFF-1: SOUTH OFFSITE Runoff = 6.69 cfs @ 12.14 hrs, Volume= 0.313 af, Depth= 1.41" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 2-Year Rainfall=2.87" Area (ac) CN Description 2.057 80 >75% Grass cover, Good, HSG D 0.603 98 Paved roads w/curbs & sewers, HSG D 2.660 84 Weighted Average 2.057 77.33% Pervious Area 0.603 22.67% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Pond 2P: Pond/Filtration Shelf Inflow Area = 23.353 ac, 19.74% Impervious, Inflow Depth = 1.35" for 2-Year event Inflow = 45.32 cfs @ 12.19 hrs, Volume= 2.628 af Outflow = 12.57 cfs @ 12.52 hrs, Volume= 2.408 af, Atten= 72%, Lag= 20.1 min Primary = 12.57 cfs @ 12.52 hrs, Volume= 2.408 af Routing by Dyn-Stor-Ind method, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Starting Elev= 882.00' Surf.Area= 2.166 ac Storage= 2.982 af Peak Elev= 883.08' @ 12.52 hrs Surf.Area= 2.248 ac Storage= 4.202 af (1.221 af above start) Plug-Flow detention time= (not calculated: initial storage exceeds outflow) MSE 24-hr 3 2-Year Rainfall=2.87"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 7HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Center-of-Mass det. time= 1,748.3 min ( 2,563.9 - 815.6 ) Volume Invert Avail.Storage Storage Description #1 878.00' 0.138 af Forbay (Prismatic) Listed below (Recalc) #2 872.00' 2.627 af Pond Dead Storage (Prismatic) Listed below (Recalc) #3 882.00' 10.571 af Pond/Filtration Live Storage (Prismatic) Listed below (Recalc) #4 880.50' 0.216 af Sand Volume (Prismatic) Listed below (Recalc) 0.720 af Overall x 30.0% Voids 13.553 af Total Available Storage Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 878.00 0.015 0.000 0.000 880.00 0.033 0.048 0.048 882.00 0.057 0.090 0.138 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 872.00 0.105 0.000 0.000 874.00 0.158 0.263 0.263 876.00 0.217 0.375 0.638 878.00 0.284 0.502 1.139 880.00 0.358 0.642 1.782 881.00 0.397 0.377 2.159 882.00 0.539 0.468 2.627 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 882.00 1.089 0.000 0.000 884.00 1.242 2.331 2.331 886.00 1.400 2.641 4.972 890.00 1.400 5.599 10.571 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 880.50 0.480 0.000 0.000 882.00 0.480 0.720 0.720 Device Routing Invert Outlet Devices #1 Primary 878.30'30.0" Round Culvert L= 97.1' RCP, mitered to conform to fill, Ke= 0.700 Inlet / Outlet Invert= 878.30' / 878.10' S= 0.0021 '/' Cc= 0.900 n= 0.013 Concrete pipe, bends & connections, Flow Area= 4.91 sf #2 Device 1 882.69'60.0" Horiz. Orifice/Grate C= 0.600 Limited to weir flow at low heads #3 Device 1 882.00'0.800 in/hr Exfiltration over Surface area above 882.00' Excluded Surface area = 2.166 ac Phase-In= 0.01' MSE 24-hr 3 2-Year Rainfall=2.87"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 8HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Primary OutFlow Max=12.57 cfs @ 12.52 hrs HW=883.08' TW=0.00' (Dynamic Tailwater) 1=Culvert (Passes 12.57 cfs of 38.48 cfs potential flow) 2=Orifice/Grate (Weir Controls 12.50 cfs @ 2.04 fps) 3=Exfiltration (Exfiltration Controls 0.07 cfs) Summary for Link W-2: Wetland 2 Inflow Area = 1.450 ac, 14.55% Impervious, Inflow Depth = 1.15" for 2-Year event Inflow = 2.98 cfs @ 12.15 hrs, Volume= 0.139 af Primary = 2.98 cfs @ 12.15 hrs, Volume= 0.139 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Summary for Link W-3: Wetland 3 Inflow Area = 27.755 ac, 18.24% Impervious, Inflow Depth > 1.21" for 2-Year event Inflow = 14.22 cfs @ 12.49 hrs, Volume= 2.809 af Primary = 14.22 cfs @ 12.49 hrs, Volume= 2.809 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 9HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Time span=0.00-300.00 hrs, dt=0.01 hrs, 30001 points Runoff by SCS TR-20 method, UH=SCS, Weighted-CN Reach routing by Dyn-Stor-Ind method - Pond routing by Dyn-Stor-Ind method Runoff Area=20.693 ac 19.37% Impervious Runoff Depth=6.96"Subcatchment 1S: 1S Flow Length=160' Slope=0.0200 '/' Tc=11.8 min AMC Adjusted CN=98 Runoff=3.95 cfs 12.003 af Runoff Area=4.402 ac 10.25% Impervious Runoff Depth=6.96"Subcatchment 2S: 2S Tc=7.0 min AMC UI Adjusted CN=98 Runoff=0.84 cfs 2.553 af Runoff Area=1.450 ac 14.55% Impervious Runoff Depth=6.96"Subcatchment 3S: 3S Tc=7.0 min AMC UI Adjusted CN=98 Runoff=0.28 cfs 0.841 af Runoff Area=2.660 ac 22.67% Impervious Runoff Depth=6.96"Subcatchment OFF-1: SOUTH OFFSITE Tc=7.0 min AMC Adjusted CN=98 Runoff=0.51 cfs 1.543 af Peak Elev=882.88' Storage=3.972 af Inflow=4.45 cfs 13.546 afPond 2P: Pond/Filtration Shelf Outflow=4.37 cfs 12.950 af Inflow=0.28 cfs 0.841 afLink W-2: Wetland 2 Primary=0.28 cfs 0.841 af Inflow=5.19 cfs 15.503 afLink W-3: Wetland 3 Primary=5.19 cfs 15.503 af Total Runoff Area = 29.205 ac Runoff Volume = 16.941 af Average Runoff Depth = 6.96" 81.94% Pervious = 23.932 ac 18.06% Impervious = 5.273 ac Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 10HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment 1S: 1S Runoff = 3.95 cfs @ 121.32 hrs, Volume= 12.003 af, Depth= 6.96" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=4 Area (ac) CN Adj Description 11.036 80 >75% Grass cover, Good, HSG D * 3.769 98 Proposed Impervious, HSG D * 0.239 98 Existing Impervious, HSG D 5.649 77 Woods, Good, HSG D 20.693 83 98 Weighted Average, AMC Adjusted 16.685 80.63% Pervious Area 4.008 19.37% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 10.3 100 0.0200 0.16 Sheet Flow, Grass: Short n= 0.150 P2= 2.87" 0.5 60 0.0200 2.12 Shallow Concentrated Flow, Grassed Waterway Kv= 15.0 fps 1.0 Direct Entry, Pipe Flow 11.8 160 Total Summary for Subcatchment 2S: 2S Runoff = 0.84 cfs @ 121.26 hrs, Volume= 2.553 af, Depth= 6.96" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=4 Area (ac) CN Adj Description 1.865 80 >75% Grass cover, Good, HSG D 0.451 98 Unconnected roofs, HSG D 2.086 77 Woods, Good, HSG D 4.402 80 98 Weighted Average, AMC UI Adjusted 3.951 89.75% Pervious Area 0.451 10.25% Impervious Area 0.451 100.00% Unconnected Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 11HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment 3S: 3S Runoff = 0.28 cfs @ 121.26 hrs, Volume= 0.841 af, Depth= 6.96" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=4 Area (ac) CN Adj Description 0.617 80 >75% Grass cover, Good, HSG D 0.211 98 Unconnected roofs, HSG D 0.622 77 Woods, Good, HSG D 1.450 81 98 Weighted Average, AMC UI Adjusted 1.239 85.45% Pervious Area 0.211 14.55% Impervious Area 0.211 100.00% Unconnected Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Subcatchment OFF-1: SOUTH OFFSITE Runoff = 0.51 cfs @ 121.26 hrs, Volume= 1.543 af, Depth= 6.96" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=4 Area (ac) CN Adj Description 2.057 80 >75% Grass cover, Good, HSG D 0.603 98 Paved roads w/curbs & sewers, HSG D 2.660 84 98 Weighted Average, AMC Adjusted 2.057 77.33% Pervious Area 0.603 22.67% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Pond 2P: Pond/Filtration Shelf Inflow Area = 23.353 ac, 19.74% Impervious, Inflow Depth = 6.96" for 10 day-100 Yr Snow event Inflow = 4.45 cfs @ 121.32 hrs, Volume= 13.546 af Outflow = 4.37 cfs @ 121.51 hrs, Volume= 12.950 af, Atten= 2%, Lag= 11.4 min Primary = 4.37 cfs @ 121.51 hrs, Volume= 12.950 af Routing by Dyn-Stor-Ind method, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Starting Elev= 882.00' Surf.Area= 2.166 ac Storage= 2.982 af Peak Elev= 882.88' @ 121.51 hrs Surf.Area= 2.233 ac Storage= 3.972 af (0.990 af above start) Plug-Flow detention time= 3,021.4 min calculated for 9.968 af (74% of inflow) Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 12HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Center-of-Mass det. time= 529.5 min ( 7,916.3 - 7,386.8 ) Volume Invert Avail.Storage Storage Description #1 878.00' 0.138 af Forbay (Prismatic) Listed below (Recalc) #2 872.00' 2.627 af Pond Dead Storage (Prismatic) Listed below (Recalc) #3 882.00' 10.571 af Pond/Filtration Live Storage (Prismatic) Listed below (Recalc) #4 880.50' 0.216 af Sand Volume (Prismatic) Listed below (Recalc) 0.720 af Overall x 30.0% Voids 13.553 af Total Available Storage Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 878.00 0.015 0.000 0.000 880.00 0.033 0.048 0.048 882.00 0.057 0.090 0.138 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 872.00 0.105 0.000 0.000 874.00 0.158 0.263 0.263 876.00 0.217 0.375 0.638 878.00 0.284 0.502 1.139 880.00 0.358 0.642 1.782 881.00 0.397 0.377 2.159 882.00 0.539 0.468 2.627 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 882.00 1.089 0.000 0.000 884.00 1.242 2.331 2.331 886.00 1.400 2.641 4.972 890.00 1.400 5.599 10.571 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 880.50 0.480 0.000 0.000 882.00 0.480 0.720 0.720 Device Routing Invert Outlet Devices #1 Primary 878.30'30.0" Round Culvert L= 97.1' RCP, mitered to conform to fill, Ke= 0.700 Inlet / Outlet Invert= 878.30' / 878.10' S= 0.0021 '/' Cc= 0.900 n= 0.013 Concrete pipe, bends & connections, Flow Area= 4.91 sf #2 Device 1 882.69'60.0" Horiz. Orifice/Grate C= 0.600 Limited to weir flow at low heads #3 Device 1 882.00'0.800 in/hr Exfiltration over Surface area above 882.00' Excluded Surface area = 2.166 ac Phase-In= 0.01' Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 13HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Primary OutFlow Max=4.37 cfs @ 121.51 hrs HW=882.88' TW=0.00' (Dynamic Tailwater) 1=Culvert (Passes 4.37 cfs of 36.91 cfs potential flow) 2=Orifice/Grate (Weir Controls 4.32 cfs @ 1.43 fps) 3=Exfiltration (Exfiltration Controls 0.05 cfs) Summary for Link W-2: Wetland 2 Inflow Area = 1.450 ac, 14.55% Impervious, Inflow Depth = 6.96" for 10 day-100 Yr Snow event Inflow = 0.28 cfs @ 121.26 hrs, Volume= 0.841 af Primary = 0.28 cfs @ 121.26 hrs, Volume= 0.841 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Summary for Link W-3: Wetland 3 Inflow Area = 27.755 ac, 18.24% Impervious, Inflow Depth > 6.70" for 10 day-100 Yr Snow event Inflow = 5.19 cfs @ 121.42 hrs, Volume= 15.503 af Primary = 5.19 cfs @ 121.42 hrs, Volume= 15.503 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 10-Year Rainfall=4.26"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 14HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Time span=0.00-300.00 hrs, dt=0.01 hrs, 30001 points Runoff by SCS TR-20 method, UH=SCS, Weighted-CN Reach routing by Dyn-Stor-Ind method - Pond routing by Dyn-Stor-Ind method Runoff Area=20.693 ac 19.37% Impervious Runoff Depth=2.51"Subcatchment 1S: 1S Flow Length=160' Slope=0.0200 '/' Tc=11.8 min CN=83 Runoff=74.88 cfs 4.334 af Runoff Area=4.402 ac 10.25% Impervious Runoff Depth=2.18"Subcatchment 2S: 2S Tc=7.0 min UI Adjusted CN=79 Runoff=17.06 cfs 0.798 af Runoff Area=1.450 ac 14.55% Impervious Runoff Depth=2.26"Subcatchment 3S: 3S Tc=7.0 min UI Adjusted CN=80 Runoff=5.82 cfs 0.273 af Runoff Area=2.660 ac 22.67% Impervious Runoff Depth=2.60"Subcatchment OFF-1: SOUTH OFFSITE Tc=7.0 min CN=84 Runoff=12.16 cfs 0.577 af Peak Elev=883.61' Storage=4.834 af Inflow=84.52 cfs 4.911 afPond 2P: Pond/Filtration Shelf Outflow=42.02 cfs 4.690 af Inflow=5.82 cfs 0.273 afLink W-2: Wetland 2 Primary=5.82 cfs 0.273 af Inflow=48.80 cfs 5.488 afLink W-3: Wetland 3 Primary=48.80 cfs 5.488 af Total Runoff Area = 29.205 ac Runoff Volume = 5.982 af Average Runoff Depth = 2.46" 81.94% Pervious = 23.932 ac 18.06% Impervious = 5.273 ac MSE 24-hr 3 10-Year Rainfall=4.26"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 15HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment 1S: 1S Runoff = 74.88 cfs @ 12.20 hrs, Volume= 4.334 af, Depth= 2.51" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 10-Year Rainfall=4.26" Area (ac) CN Description 11.036 80 >75% Grass cover, Good, HSG D * 3.769 98 Proposed Impervious, HSG D * 0.239 98 Existing Impervious, HSG D 5.649 77 Woods, Good, HSG D 20.693 83 Weighted Average 16.685 80.63% Pervious Area 4.008 19.37% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 10.3 100 0.0200 0.16 Sheet Flow, Grass: Short n= 0.150 P2= 2.87" 0.5 60 0.0200 2.12 Shallow Concentrated Flow, Grassed Waterway Kv= 15.0 fps 1.0 Direct Entry, Pipe Flow 11.8 160 Total Summary for Subcatchment 2S: 2S Runoff = 17.06 cfs @ 12.14 hrs, Volume= 0.798 af, Depth= 2.18" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 10-Year Rainfall=4.26" Area (ac) CN Adj Description 1.865 80 >75% Grass cover, Good, HSG D 0.451 98 Unconnected roofs, HSG D 2.086 77 Woods, Good, HSG D 4.402 80 79 Weighted Average, UI Adjusted 3.951 89.75% Pervious Area 0.451 10.25% Impervious Area 0.451 100.00% Unconnected Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, MSE 24-hr 3 10-Year Rainfall=4.26"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 16HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment 3S: 3S Runoff = 5.82 cfs @ 12.14 hrs, Volume= 0.273 af, Depth= 2.26" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 10-Year Rainfall=4.26" Area (ac) CN Adj Description 0.617 80 >75% Grass cover, Good, HSG D 0.211 98 Unconnected roofs, HSG D 0.622 77 Woods, Good, HSG D 1.450 81 80 Weighted Average, UI Adjusted 1.239 85.45% Pervious Area 0.211 14.55% Impervious Area 0.211 100.00% Unconnected Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Subcatchment OFF-1: SOUTH OFFSITE Runoff = 12.16 cfs @ 12.14 hrs, Volume= 0.577 af, Depth= 2.60" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 10-Year Rainfall=4.26" Area (ac) CN Description 2.057 80 >75% Grass cover, Good, HSG D 0.603 98 Paved roads w/curbs & sewers, HSG D 2.660 84 Weighted Average 2.057 77.33% Pervious Area 0.603 22.67% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Pond 2P: Pond/Filtration Shelf Inflow Area = 23.353 ac, 19.74% Impervious, Inflow Depth = 2.52" for 10-Year event Inflow = 84.52 cfs @ 12.18 hrs, Volume= 4.911 af Outflow = 42.02 cfs @ 12.36 hrs, Volume= 4.690 af, Atten= 50%, Lag= 10.3 min Primary = 42.02 cfs @ 12.36 hrs, Volume= 4.690 af Routing by Dyn-Stor-Ind method, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Starting Elev= 882.00' Surf.Area= 2.166 ac Storage= 2.982 af Peak Elev= 883.61' @ 12.36 hrs Surf.Area= 2.289 ac Storage= 4.834 af (1.853 af above start) Plug-Flow detention time= 2,659.4 min calculated for 1.708 af (35% of inflow) MSE 24-hr 3 10-Year Rainfall=4.26"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 17HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Center-of-Mass det. time= 913.1 min ( 1,716.0 - 802.9 ) Volume Invert Avail.Storage Storage Description #1 878.00' 0.138 af Forbay (Prismatic) Listed below (Recalc) #2 872.00' 2.627 af Pond Dead Storage (Prismatic) Listed below (Recalc) #3 882.00' 10.571 af Pond/Filtration Live Storage (Prismatic) Listed below (Recalc) #4 880.50' 0.216 af Sand Volume (Prismatic) Listed below (Recalc) 0.720 af Overall x 30.0% Voids 13.553 af Total Available Storage Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 878.00 0.015 0.000 0.000 880.00 0.033 0.048 0.048 882.00 0.057 0.090 0.138 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 872.00 0.105 0.000 0.000 874.00 0.158 0.263 0.263 876.00 0.217 0.375 0.638 878.00 0.284 0.502 1.139 880.00 0.358 0.642 1.782 881.00 0.397 0.377 2.159 882.00 0.539 0.468 2.627 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 882.00 1.089 0.000 0.000 884.00 1.242 2.331 2.331 886.00 1.400 2.641 4.972 890.00 1.400 5.599 10.571 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 880.50 0.480 0.000 0.000 882.00 0.480 0.720 0.720 Device Routing Invert Outlet Devices #1 Primary 878.30'30.0" Round Culvert L= 97.1' RCP, mitered to conform to fill, Ke= 0.700 Inlet / Outlet Invert= 878.30' / 878.10' S= 0.0021 '/' Cc= 0.900 n= 0.013 Concrete pipe, bends & connections, Flow Area= 4.91 sf #2 Device 1 882.69'60.0" Horiz. Orifice/Grate C= 0.600 Limited to weir flow at low heads #3 Device 1 882.00'0.800 in/hr Exfiltration over Surface area above 882.00' Excluded Surface area = 2.166 ac Phase-In= 0.01' MSE 24-hr 3 10-Year Rainfall=4.26"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 18HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Primary OutFlow Max=42.02 cfs @ 12.36 hrs HW=883.61' TW=0.00' (Dynamic Tailwater) 1=Culvert (Inlet Controls 42.02 cfs @ 8.56 fps) 2=Orifice/Grate (Passes < 45.32 cfs potential flow) 3=Exfiltration (Passes < 0.10 cfs potential flow) Summary for Link W-2: Wetland 2 Inflow Area = 1.450 ac, 14.55% Impervious, Inflow Depth = 2.26" for 10-Year event Inflow = 5.82 cfs @ 12.14 hrs, Volume= 0.273 af Primary = 5.82 cfs @ 12.14 hrs, Volume= 0.273 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Summary for Link W-3: Wetland 3 Inflow Area = 27.755 ac, 18.24% Impervious, Inflow Depth > 2.37" for 10-Year event Inflow = 48.80 cfs @ 12.28 hrs, Volume= 5.488 af Primary = 48.80 cfs @ 12.28 hrs, Volume= 5.488 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 100-Year Rainfall=7.38"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 19HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Time span=0.00-300.00 hrs, dt=0.01 hrs, 30001 points Runoff by SCS TR-20 method, UH=SCS, Weighted-CN Reach routing by Dyn-Stor-Ind method - Pond routing by Dyn-Stor-Ind method Runoff Area=20.693 ac 19.37% Impervious Runoff Depth=5.39"Subcatchment 1S: 1S Flow Length=160' Slope=0.0200 '/' Tc=11.8 min CN=83 Runoff=156.10 cfs 9.290 af Runoff Area=4.402 ac 10.25% Impervious Runoff Depth=4.93"Subcatchment 2S: 2S Tc=7.0 min UI Adjusted CN=79 Runoff=37.65 cfs 1.810 af Runoff Area=1.450 ac 14.55% Impervious Runoff Depth=5.05"Subcatchment 3S: 3S Tc=7.0 min UI Adjusted CN=80 Runoff=12.63 cfs 0.610 af Runoff Area=2.660 ac 22.67% Impervious Runoff Depth=5.50"Subcatchment OFF-1: SOUTH OFFSITE Tc=7.0 min CN=84 Runoff=24.77 cfs 1.220 af Peak Elev=885.44' Storage=7.178 af Inflow=176.09 cfs 10.510 afPond 2P: Pond/Filtration Shelf Outflow=50.60 cfs 10.288 af Inflow=12.63 cfs 0.610 afLink W-2: Wetland 2 Primary=12.63 cfs 0.610 af Inflow=82.06 cfs 12.098 afLink W-3: Wetland 3 Primary=82.06 cfs 12.098 af Total Runoff Area = 29.205 ac Runoff Volume = 12.929 af Average Runoff Depth = 5.31" 81.94% Pervious = 23.932 ac 18.06% Impervious = 5.273 ac MSE 24-hr 3 100-Year Rainfall=7.38"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 20HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment 1S: 1S Runoff = 156.10 cfs @ 12.19 hrs, Volume= 9.290 af, Depth= 5.39" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 100-Year Rainfall=7.38" Area (ac) CN Description 11.036 80 >75% Grass cover, Good, HSG D * 3.769 98 Proposed Impervious, HSG D * 0.239 98 Existing Impervious, HSG D 5.649 77 Woods, Good, HSG D 20.693 83 Weighted Average 16.685 80.63% Pervious Area 4.008 19.37% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 10.3 100 0.0200 0.16 Sheet Flow, Grass: Short n= 0.150 P2= 2.87" 0.5 60 0.0200 2.12 Shallow Concentrated Flow, Grassed Waterway Kv= 15.0 fps 1.0 Direct Entry, Pipe Flow 11.8 160 Total Summary for Subcatchment 2S: 2S Runoff = 37.65 cfs @ 12.14 hrs, Volume= 1.810 af, Depth= 4.93" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 100-Year Rainfall=7.38" Area (ac) CN Adj Description 1.865 80 >75% Grass cover, Good, HSG D 0.451 98 Unconnected roofs, HSG D 2.086 77 Woods, Good, HSG D 4.402 80 79 Weighted Average, UI Adjusted 3.951 89.75% Pervious Area 0.451 10.25% Impervious Area 0.451 100.00% Unconnected Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, MSE 24-hr 3 100-Year Rainfall=7.38"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 21HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment 3S: 3S Runoff = 12.63 cfs @ 12.14 hrs, Volume= 0.610 af, Depth= 5.05" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 100-Year Rainfall=7.38" Area (ac) CN Adj Description 0.617 80 >75% Grass cover, Good, HSG D 0.211 98 Unconnected roofs, HSG D 0.622 77 Woods, Good, HSG D 1.450 81 80 Weighted Average, UI Adjusted 1.239 85.45% Pervious Area 0.211 14.55% Impervious Area 0.211 100.00% Unconnected Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Subcatchment OFF-1: SOUTH OFFSITE Runoff = 24.77 cfs @ 12.14 hrs, Volume= 1.220 af, Depth= 5.50" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 100-Year Rainfall=7.38" Area (ac) CN Description 2.057 80 >75% Grass cover, Good, HSG D 0.603 98 Paved roads w/curbs & sewers, HSG D 2.660 84 Weighted Average 2.057 77.33% Pervious Area 0.603 22.67% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Pond 2P: Pond/Filtration Shelf Inflow Area = 23.353 ac, 19.74% Impervious, Inflow Depth = 5.40" for 100-Year event Inflow = 176.09 cfs @ 12.18 hrs, Volume= 10.510 af Outflow = 50.60 cfs @ 12.48 hrs, Volume= 10.288 af, Atten= 71%, Lag= 17.8 min Primary = 50.60 cfs @ 12.48 hrs, Volume= 10.288 af Routing by Dyn-Stor-Ind method, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Starting Elev= 882.00' Surf.Area= 2.166 ac Storage= 2.982 af Peak Elev= 885.44' @ 12.48 hrs Surf.Area= 2.432 ac Storage= 7.178 af (4.196 af above start) Plug-Flow detention time= 716.5 min calculated for 7.307 af (70% of inflow) MSE 24-hr 3 100-Year Rainfall=7.38"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 22HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Center-of-Mass det. time= 443.9 min ( 1,231.7 - 787.8 ) Volume Invert Avail.Storage Storage Description #1 878.00' 0.138 af Forbay (Prismatic) Listed below (Recalc) #2 872.00' 2.627 af Pond Dead Storage (Prismatic) Listed below (Recalc) #3 882.00' 10.571 af Pond/Filtration Live Storage (Prismatic) Listed below (Recalc) #4 880.50' 0.216 af Sand Volume (Prismatic) Listed below (Recalc) 0.720 af Overall x 30.0% Voids 13.553 af Total Available Storage Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 878.00 0.015 0.000 0.000 880.00 0.033 0.048 0.048 882.00 0.057 0.090 0.138 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 872.00 0.105 0.000 0.000 874.00 0.158 0.263 0.263 876.00 0.217 0.375 0.638 878.00 0.284 0.502 1.139 880.00 0.358 0.642 1.782 881.00 0.397 0.377 2.159 882.00 0.539 0.468 2.627 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 882.00 1.089 0.000 0.000 884.00 1.242 2.331 2.331 886.00 1.400 2.641 4.972 890.00 1.400 5.599 10.571 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 880.50 0.480 0.000 0.000 882.00 0.480 0.720 0.720 Device Routing Invert Outlet Devices #1 Primary 878.30'30.0" Round Culvert L= 97.1' RCP, mitered to conform to fill, Ke= 0.700 Inlet / Outlet Invert= 878.30' / 878.10' S= 0.0021 '/' Cc= 0.900 n= 0.013 Concrete pipe, bends & connections, Flow Area= 4.91 sf #2 Device 1 882.69'60.0" Horiz. Orifice/Grate C= 0.600 Limited to weir flow at low heads #3 Device 1 882.00'0.800 in/hr Exfiltration over Surface area above 882.00' Excluded Surface area = 2.166 ac Phase-In= 0.01' MSE 24-hr 3 100-Year Rainfall=7.38"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 23HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Primary OutFlow Max=50.60 cfs @ 12.48 hrs HW=885.44' TW=0.00' (Dynamic Tailwater) 1=Culvert (Inlet Controls 50.60 cfs @ 10.31 fps) 2=Orifice/Grate (Passes < 156.67 cfs potential flow) 3=Exfiltration (Passes < 0.21 cfs potential flow) Summary for Link W-2: Wetland 2 Inflow Area = 1.450 ac, 14.55% Impervious, Inflow Depth = 5.05" for 100-Year event Inflow = 12.63 cfs @ 12.14 hrs, Volume= 0.610 af Primary = 12.63 cfs @ 12.14 hrs, Volume= 0.610 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Summary for Link W-3: Wetland 3 Inflow Area = 27.755 ac, 18.24% Impervious, Inflow Depth > 5.23" for 100-Year event Inflow = 82.06 cfs @ 12.15 hrs, Volume= 12.098 af Primary = 82.06 cfs @ 12.15 hrs, Volume= 12.098 af, Atten= 0%, Lag= 0.0 min Primary outflow = Inflow, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Table of Contents20090pdrn Printed 5/14/2021Prepared by {enter your company name here} HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC TABLE OF CONTENTS Project Reports 1 Routing Diagram 2 Area Listing (selected nodes) 3 Soil Listing (selected nodes) 2-Year Event 4 Node Listing 5 Subcat 1S: 1S 6 Subcat 2S: 2S 6 Subcat 3S: 3S 7 Subcat OFF-1: SOUTH OFFSITE 7 Pond 2P: Pond/Filtration Shelf 9 Link W-2: Wetland 2 9 Link W-3: Wetland 3 10 day-100 Yr Snow Event 9 Node Listing 10 Subcat 1S: 1S 11 Subcat 2S: 2S 11 Subcat 3S: 3S 12 Subcat OFF-1: SOUTH OFFSITE 12 Pond 2P: Pond/Filtration Shelf 14 Link W-2: Wetland 2 14 Link W-3: Wetland 3 10-Year Event 14 Node Listing 15 Subcat 1S: 1S 16 Subcat 2S: 2S 16 Subcat 3S: 3S 17 Subcat OFF-1: SOUTH OFFSITE 17 Pond 2P: Pond/Filtration Shelf 19 Link W-2: Wetland 2 19 Link W-3: Wetland 3 100-Year Event 19 Node Listing 20 Subcat 1S: 1S 21 Subcat 2S: 2S 21 Subcat 3S: 3S 22 Subcat OFF-1: SOUTH OFFSITE 22 Pond 2P: Pond/Filtration Shelf 24 Link W-2: Wetland 2 24 Link W-3: Wetland 3 1S 1S 2S 2S 3S 3S OFF-1 SOUTH OFFSITE 2P Pond/Filtration Shelf W-2 Wetland 2 W-3 Wetland 3 Routing Diagram for 20090pdrn Prepared by {enter your company name here}, Printed 5/14/2021 HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcat Reach Pond Link MSE 24-hr 3 2-Year Rainfall=2.87"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 2HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment 1S: 1S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)44 42 40 38 36 34 32 30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0 MSE 24-hr 3 2-Year Rainfall=2.87" Runoff Area=20.693 ac Runoff Volume=2.315 af Runoff Depth=1.34" Flow Length=160' Slope=0.0200 '/' Tc=11.8 min CN=83 40.14 cfs Subcatchment 2S: 2S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)9 8 7 6 5 4 3 2 1 0 MSE 24-hr 3 2-Year Rainfall=2.87" Runoff Area=4.402 ac Runoff Volume=0.401 af Runoff Depth=1.09" Tc=7.0 min UI Adjusted CN=79 8.55 cfs MSE 24-hr 3 2-Year Rainfall=2.87"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 3HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment 3S: 3S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)3 2 1 0 MSE 24-hr 3 2-Year Rainfall=2.87" Runoff Area=1.450 ac Runoff Volume=0.139 af Runoff Depth=1.15" Tc=7.0 min UI Adjusted CN=80 2.98 cfs Subcatchment OFF-1: SOUTH OFFSITE Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)7 6 5 4 3 2 1 0 MSE 24-hr 3 2-Year Rainfall=2.87" Runoff Area=2.660 ac Runoff Volume=0.313 af Runoff Depth=1.41" Tc=7.0 min CN=84 6.69 cfs MSE 24-hr 3 2-Year Rainfall=2.87"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 4HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Pond 2P: Pond/Filtration Shelf Inflow Primary Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)50 48 46 44 42 40 38 36 34 32 30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0 Inflow Area=23.353 ac Peak Elev=883.08' Storage=4.202 af 45.32 cfs 12.57 cfs Link W-2: Wetland 2 Inflow Primary Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)3 2 1 0 Inflow Area=1.450 ac 2.98 cfs2.98 cfs MSE 24-hr 3 2-Year Rainfall=2.87"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 5HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Link W-3: Wetland 3 Inflow Primary Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 Inflow Area=27.755 ac 14.22 cfs14.22 cfs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 6HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment 1S: 1S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)4 3 2 1 0 Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20" AMC=4 Runoff Area=20.693 ac Runoff Volume=12.003 af Runoff Depth=6.96" Flow Length=160' Slope=0.0200 '/' Tc=11.8 min AMC Adjusted CN=98 3.95 cfs Subcatchment 2S: 2S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)0.9 0.85 0.8 0.75 0.7 0.65 0.6 0.55 0.5 0.45 0.4 0.35 0.3 0.25 0.2 0.15 0.1 0.05 0 Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20" AMC=4 Runoff Area=4.402 ac Runoff Volume=2.553 af Runoff Depth=6.96" Tc=7.0 min AMC UI Adjusted CN=98 0.84 cfs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 7HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment 3S: 3S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)0.3 0.28 0.26 0.24 0.22 0.2 0.18 0.16 0.14 0.12 0.1 0.08 0.06 0.04 0.02 0 Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20" AMC=4 Runoff Area=1.450 ac Runoff Volume=0.841 af Runoff Depth=6.96" Tc=7.0 min AMC UI Adjusted CN=98 0.28 cfs Subcatchment OFF-1: SOUTH OFFSITE Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)0.55 0.5 0.45 0.4 0.35 0.3 0.25 0.2 0.15 0.1 0.05 0 Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20" AMC=4 Runoff Area=2.660 ac Runoff Volume=1.543 af Runoff Depth=6.96" Tc=7.0 min AMC Adjusted CN=98 0.51 cfs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 8HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Pond 2P: Pond/Filtration Shelf Inflow Primary Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)4 3 2 1 0 Inflow Area=23.353 ac Peak Elev=882.88' Storage=3.972 af 4.45 cfs4.37 cfs Link W-2: Wetland 2 Inflow Primary Hydrograph Time (hours) 300280260240220200180160140120100806040200Flow (cfs)0.3 0.28 0.26 0.24 0.22 0.2 0.18 0.16 0.14 0.12 0.1 0.08 0.06 0.04 0.02 0 Inflow Area=1.450 ac 0.28 cfs0.28 cfs Snowmelt_10d_100yr 10 day-100 Yr Snow Rainfall=7.20", AMC=420090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 9HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Link W-3: Wetland 3 Inflow Primary Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)5 4 3 2 1 0 Inflow Area=27.755 ac 5.19 cfs5.19 cfs MSE 24-hr 3 10-Year Rainfall=4.26"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 10HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment 1S: 1S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0 MSE 24-hr 3 10-Year Rainfall=4.26" Runoff Area=20.693 ac Runoff Volume=4.334 af Runoff Depth=2.51" Flow Length=160' Slope=0.0200 '/' Tc=11.8 min CN=83 74.88 cfs Subcatchment 2S: 2S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 MSE 24-hr 3 10-Year Rainfall=4.26" Runoff Area=4.402 ac Runoff Volume=0.798 af Runoff Depth=2.18" Tc=7.0 min UI Adjusted CN=79 17.06 cfs MSE 24-hr 3 10-Year Rainfall=4.26"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 11HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment 3S: 3S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)6 5 4 3 2 1 0 MSE 24-hr 3 10-Year Rainfall=4.26" Runoff Area=1.450 ac Runoff Volume=0.273 af Runoff Depth=2.26" Tc=7.0 min UI Adjusted CN=80 5.82 cfs Subcatchment OFF-1: SOUTH OFFSITE Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)13 12 11 10 9 8 7 6 5 4 3 2 1 0 MSE 24-hr 3 10-Year Rainfall=4.26" Runoff Area=2.660 ac Runoff Volume=0.577 af Runoff Depth=2.60" Tc=7.0 min CN=84 12.16 cfs MSE 24-hr 3 10-Year Rainfall=4.26"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 12HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Pond 2P: Pond/Filtration Shelf Inflow Primary Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0 Inflow Area=23.353 ac Peak Elev=883.61' Storage=4.834 af 84.52 cfs 42.02 cfs Link W-2: Wetland 2 Inflow Primary Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)6 5 4 3 2 1 0 Inflow Area=1.450 ac 5.82 cfs5.82 cfs MSE 24-hr 3 10-Year Rainfall=4.26"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 13HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Link W-3: Wetland 3 Inflow Primary Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)54 52 50 48 46 44 42 40 38 36 34 32 30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0 Inflow Area=27.755 ac 48.80 cfs48.80 cfs MSE 24-hr 3 100-Year Rainfall=7.38"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 14HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment 1S: 1S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)170 160 150 140 130 120 110 100 90 80 70 60 50 40 30 20 10 0 MSE 24-hr 3 100-Year Rainfall=7.38" Runoff Area=20.693 ac Runoff Volume=9.290 af Runoff Depth=5.39" Flow Length=160' Slope=0.0200 '/' Tc=11.8 min CN=83 156.10 cfs Subcatchment 2S: 2S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)42 40 38 36 34 32 30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0 MSE 24-hr 3 100-Year Rainfall=7.38" Runoff Area=4.402 ac Runoff Volume=1.810 af Runoff Depth=4.93" Tc=7.0 min UI Adjusted CN=79 37.65 cfs MSE 24-hr 3 100-Year Rainfall=7.38"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 15HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcatchment 3S: 3S Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 MSE 24-hr 3 100-Year Rainfall=7.38" Runoff Area=1.450 ac Runoff Volume=0.610 af Runoff Depth=5.05" Tc=7.0 min UI Adjusted CN=80 12.63 cfs Subcatchment OFF-1: SOUTH OFFSITE Runoff Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)26 24 22 20 18 16 14 12 10 8 6 4 2 0 MSE 24-hr 3 100-Year Rainfall=7.38" Runoff Area=2.660 ac Runoff Volume=1.220 af Runoff Depth=5.50" Tc=7.0 min CN=84 24.77 cfs MSE 24-hr 3 100-Year Rainfall=7.38"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 16HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Pond 2P: Pond/Filtration Shelf Inflow Primary Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)190 180 170 160 150 140 130 120 110 100 90 80 70 60 50 40 30 20 10 0 Inflow Area=23.353 ac Peak Elev=885.44' Storage=7.178 af 176.09 cfs 50.60 cfs Link W-2: Wetland 2 Inflow Primary Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)14 13 12 11 10 9 8 7 6 5 4 3 2 1 0 Inflow Area=1.450 ac 12.63 cfs12.63 cfs MSE 24-hr 3 100-Year Rainfall=7.38"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 17HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Link W-3: Wetland 3 Inflow Primary Hydrograph Time (hours) 3002902802702602502402302202102001901801701601501401301201101009080706050403020100Flow (cfs)90 85 80 75 70 65 60 55 50 45 40 35 30 25 20 15 10 5 0 Inflow Area=27.755 ac 82.06 cfs82.06 cfs Table of Contents20090pdrn Printed 5/14/2021Prepared by {enter your company name here} HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC TABLE OF CONTENTS Project Reports 1 Routing Diagram 2-Year Event 2 Subcat 1S: 1S 3 Subcat 2S: 2S 3 Subcat 3S: 3S 4 Subcat OFF-1: SOUTH OFFSITE 4 Pond 2P: Pond/Filtration Shelf 5 Link W-2: Wetland 2 5 Link W-3: Wetland 3 10 day-100 Yr Snow Event 6 Subcat 1S: 1S 7 Subcat 2S: 2S 7 Subcat 3S: 3S 8 Subcat OFF-1: SOUTH OFFSITE 8 Pond 2P: Pond/Filtration Shelf 9 Link W-2: Wetland 2 9 Link W-3: Wetland 3 10-Year Event 10 Subcat 1S: 1S 11 Subcat 2S: 2S 11 Subcat 3S: 3S 12 Subcat OFF-1: SOUTH OFFSITE 12 Pond 2P: Pond/Filtration Shelf 13 Link W-2: Wetland 2 13 Link W-3: Wetland 3 100-Year Event 14 Subcat 1S: 1S 15 Subcat 2S: 2S 15 Subcat 3S: 3S 16 Subcat OFF-1: SOUTH OFFSITE 16 Pond 2P: Pond/Filtration Shelf 17 Link W-2: Wetland 2 17 Link W-3: Wetland 3 1S 1S OFF-1 SOUTH OFFSITE 2P Pond/Filtration Shelf Routing Diagram for 20090pdrn Prepared by {enter your company name here}, Printed 5/14/2021 HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Subcat Reach Pond Link MSE 24-hr 3 NURP Rainfall=2.50"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 2HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Summary for Subcatchment 1S: 1S Runoff = 31.42 cfs @ 12.20 hrs, Volume= 1.821 af, Depth= 1.06" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 NURP Rainfall=2.50" Area (ac) CN Description 11.036 80 >75% Grass cover, Good, HSG D * 3.769 98 Proposed Impervious, HSG D * 0.239 98 Existing Impervious, HSG D 5.649 77 Woods, Good, HSG D 20.693 83 Weighted Average 16.685 80.63% Pervious Area 4.008 19.37% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 10.3 100 0.0200 0.16 Sheet Flow, Grass: Short n= 0.150 P2= 2.87" 0.5 60 0.0200 2.12 Shallow Concentrated Flow, Grassed Waterway Kv= 15.0 fps 1.0 Direct Entry, Pipe Flow 11.8 160 Total Summary for Subcatchment OFF-1: SOUTH OFFSITE Runoff = 5.30 cfs @ 12.15 hrs, Volume= 0.247 af, Depth= 1.12" Runoff by SCS TR-20 method, UH=SCS, Weighted-CN, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs MSE 24-hr 3 NURP Rainfall=2.50" Area (ac) CN Description 2.057 80 >75% Grass cover, Good, HSG D 0.603 98 Paved roads w/curbs & sewers, HSG D 2.660 84 Weighted Average 2.057 77.33% Pervious Area 0.603 22.67% Impervious Area Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 7.0 Direct Entry, Summary for Pond 2P: Pond/Filtration Shelf Inflow Area = 23.353 ac, 19.74% Impervious, Inflow Depth = 1.06" for NURP event Inflow = 35.50 cfs @ 12.19 hrs, Volume= 2.068 af Outflow = 6.44 cfs @ 12.67 hrs, Volume= 1.848 af, Atten= 82%, Lag= 28.5 min Primary = 6.44 cfs @ 12.67 hrs, Volume= 1.848 af MSE 24-hr 3 NURP Rainfall=2.50"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 3HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Routing by Dyn-Stor-Ind method, Time Span= 0.00-300.00 hrs, dt= 0.01 hrs Starting Elev= 882.00' Surf.Area= 2.166 ac Storage= 2.982 af Peak Elev= 882.94' @ 12.67 hrs Surf.Area= 2.238 ac Storage= 4.038 af (1.057 af above start) Plug-Flow detention time= (not calculated: initial storage exceeds outflow) Center-of-Mass det. time= 2,266.1 min ( 3,086.7 - 820.6 ) Volume Invert Avail.Storage Storage Description #1 878.00' 0.138 af Forbay (Prismatic) Listed below (Recalc) #2 872.00' 2.627 af Pond Dead Storage (Prismatic) Listed below (Recalc) #3 882.00' 10.571 af Pond/Filtration Live Storage (Prismatic) Listed below (Recalc) #4 880.50' 0.216 af Sand Volume (Prismatic) Listed below (Recalc) 0.720 af Overall x 30.0% Voids 13.553 af Total Available Storage Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 878.00 0.015 0.000 0.000 880.00 0.033 0.048 0.048 882.00 0.057 0.090 0.138 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 872.00 0.105 0.000 0.000 874.00 0.158 0.263 0.263 876.00 0.217 0.375 0.638 878.00 0.284 0.502 1.139 880.00 0.358 0.642 1.782 881.00 0.397 0.377 2.159 882.00 0.539 0.468 2.627 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 882.00 1.089 0.000 0.000 884.00 1.242 2.331 2.331 886.00 1.400 2.641 4.972 890.00 1.400 5.599 10.571 Elevation Surf.Area Inc.Store Cum.Store (feet) (acres) (acre-feet) (acre-feet) 880.50 0.480 0.000 0.000 882.00 0.480 0.720 0.720 Device Routing Invert Outlet Devices #1 Primary 878.30'30.0" Round Culvert L= 97.1' RCP, mitered to conform to fill, Ke= 0.700 Inlet / Outlet Invert= 878.30' / 878.10' S= 0.0021 '/' Cc= 0.900 n= 0.013 Concrete pipe, bends & connections, Flow Area= 4.91 sf #2 Device 1 882.69'60.0" Horiz. Orifice/Grate C= 0.600 Limited to weir flow at low heads #3 Device 1 882.00'0.800 in/hr Exfiltration over Surface area above 882.00' MSE 24-hr 3 NURP Rainfall=2.50"20090pdrn Printed 5/14/2021Prepared by {enter your company name here} Page 4HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC Excluded Surface area = 2.166 ac Phase-In= 0.01' Primary OutFlow Max=6.44 cfs @ 12.67 hrs HW=882.94' TW=0.00' (Dynamic Tailwater) 1=Culvert (Passes 6.44 cfs of 37.37 cfs potential flow) 2=Orifice/Grate (Weir Controls 6.38 cfs @ 1.63 fps) 3=Exfiltration (Exfiltration Controls 0.06 cfs) Table of Contents20090pdrn Printed 5/14/2021Prepared by {enter your company name here} HydroCAD® 10.10-5a s/n 01427 © 2020 HydroCAD Software Solutions LLC TABLE OF CONTENTS Project Reports 1 Routing Diagram NURP Event 2 Subcat 1S: 1S 3 Subcat OFF-1: SOUTH OFFSITE 3 Pond 2P: Pond/Filtration Shelf Project Information Calculator Version:Version 3: January 2017 Project Name:Existing Erhart Farm User Name / Company Name:Alliant Engineering Date:5/12/21 Project Description:Existing MIDS model for Erhart Farm Construction Permit?:No Site Information Retention Requirement (inches):1.1 Site's Zip Code:55317 Annual Rainfall (inches):29.9 Phosphorus EMC (mg/l):0.3 TSS EMC (mg/l):54.5 Total Site Area Land Cover A Soils (acres) B Soils (acres) C Soils (acres) D Soils (acres) Total (acres) Forest/Open Space -Undisturbed, protected forest/open space or reforested land 24.822 24.822 Managed Turf -disturbed, graded for yards or other turf to be mowed/managed 0 Impervious Area (acres)0.788 Total Area (acres)25.61 Site Areas Routed to BMPs Land Cover A Soils (acres) B Soils (acres) C Soils (acres) D Soils (acres) Total (acres) Forest/Open Space -Undisturbed, protected forest/open space or reforested land 0 Managed Turf -disturbed, graded for yards or other turf to be mowed/managed 0 Impervious Area (acres) Total Area (acres)0 Summary Information Performance Goal Requirement Performance goal volume retention requirement:3146 ft3 Volume removed by BMPs towards performance goal:ft3 Percent volume removed towards performance goal % Annual Volume and Pollutant Load Reductions Post development annual runoff volume 4.4619 acre-ft Annual runoff volume removed by BMPs:acre-ft Percent annual runoff volume removed:% Post development annual particulate P load:2.002 lbs Annual particulate P removed by BMPs:lbs Post development annual dissolved P load:1.638 lbs Annual dissolved P removed by BMPs:lbs Percent annual total phosphorus removed:% Post development annual TSS load:661.4 lbs Annual TSS removed by BMPs:lbs Percent annual TSS removed:% BMP Summary Performance Goal Summary BMP Name BMP Volume Capacity (ft3) Volume Recieved (ft3) Volume Retained (ft3) Volume Outflow (ft3) Percent Retained (%) Annual Volume Summary BMP Name Volume From Direct Watershed (acre-ft) Volume From Upstream BMPs (acre-ft) Volume Retained (acre-ft) Volume outflow (acre-ft) Percent Retained (%) Particulate Phosphorus Summary BMP Name Load From Direct Watershed (lbs) Load From Upstream BMPs (lbs) Load Retained (lbs) Outflow Load (lbs) Percent Retained (%) Dissolved Phosphorus Summary BMP Name Load From Direct Watershed (lbs) Load From Upstream BMPs (lbs) Load Retained (lbs) Outflow Load (lbs) Percent Retained (%) TSS Summary BMP Name Load From Direct Watershed (lbs) Load From Upstream BMPs (lbs) Load Retained (lbs) Outflow Load (lbs) Percent Retained (%) BMP Schematic Project Information Calculator Version:Version 3: January 2017 Project Name:Proposed Erhart Farm User Name / Company Name:Alliant Engineering Date:5/14/21 Project Description:Proposed Erhart Farms. 21 Single Family Homes Construction Permit?:No Site Information Retention Requirement (inches):1.1 Site's Zip Code:55317 Annual Rainfall (inches):29.9 Phosphorus EMC (mg/l):0.3 TSS EMC (mg/l):54.5 Total Site Area Land Cover A Soils (acres) B Soils (acres) C Soils (acres) D Soils (acres) Total (acres) Forest/Open Space -Undisturbed, protected forest/open space or reforested land 8.357 8.357 Managed Turf -disturbed, graded for yards or other turf to be mowed/managed 13.518 13.518 Impervious Area (acres)4.67 Total Area (acres)26.545 Site Areas Routed to BMPs Land Cover A Soils (acres) B Soils (acres) C Soils (acres) D Soils (acres) Total (acres) Forest/Open Space -Undisturbed, protected forest/open space or reforested land 8.357 8.357 Managed Turf -disturbed, graded for yards or other turf to be mowed/managed 13.518 13.518 Impervious Area (acres)4.67 Total Area (acres)26.545 Summary Information Performance Goal Requirement Performance goal volume retention requirement:18647 ft3 Volume removed by BMPs towards performance goal:10501 ft3 Percent volume removed towards performance goal 56 % Annual Volume and Pollutant Load Reductions Post development annual runoff volume 18.4644 acre-ft Annual runoff volume removed by BMPs:4.6919 acre-ft Percent annual runoff volume removed:25 % Post development annual particulate P load:8.287 lbs Annual particulate P removed by BMPs:7.331 lbs Post development annual dissolved P load:6.78 lbs Annual dissolved P removed by BMPs:4.311 lbs Percent annual total phosphorus removed:77 % Post development annual TSS load:2737.2 lbs Annual TSS removed by BMPs:2597.4 lbs Percent annual TSS removed:95 % BMP Summary Performance Goal Summary BMP Name BMP Volume Capacity (ft3) Volume Recieved (ft3) Volume Retained (ft3) Volume Outflow (ft3) Percent Retained (%) 1 -Bioretention basin (with underdrain)9003 16004 9003 7001 56 2S 1026 1801 1026 775 57 3S 472 843 472 371 56 1 -Constructed stormwater pond 0 16004 0 16004 0 Annual Volume Summary BMP Name Volume From Direct Watershed (acre-ft) Volume From Upstream BMPs (acre-ft) Volume Retained (acre-ft) Volume outflow (acre-ft) Percent Retained (%) 1 -Bioretention basin (with underdrain)0 15.359 3.3307 12.0283 22 2S 2.2403 0 0.9495 1.2908 42 3S 0.8652 0 0.4117 0.4535 48 1 -Constructed stormwater pond 15.359 0 0 15.359 0 Particulate Phosphorus Summary BMP Name Load From Direct Watershed (lbs) Load From Upstream BMPs (lbs) Load Retained (lbs) Outflow Load (lbs) Percent Retained (%) 1 -Bioretention basin (with underdrain)0 1.1029 0.9302 0.1727 84 2S 1.0054 0 0.4261 0.5793 42 3S 0.3883 0 0.1848 0.2035 48 1 -Constructed stormwater pond 6.8931 0 5.7902 1.1029 84 Dissolved Phosphorus Summary BMP Name Load From Direct Watershed (lbs) Load From Upstream BMPs (lbs) Load Retained (lbs) Outflow Load (lbs) Percent Retained (%) 1 -Bioretention basin (with underdrain)0 5.1886 3.3601 1.8285 65 2S 0.8226 0 0.3487 0.4739 42 3S 0.3177 0 0.1512 0.1665 48 1 -Constructed stormwater pond 5.6398 0 0.4512 5.1886 8 TSS Summary BMP Name Load From Direct Watershed (lbs) Load From Upstream BMPs (lbs) Load Retained (lbs) Outflow Load (lbs) Percent Retained (%) 1 -Bioretention basin (with underdrain)0 364.29 307.23 57.0600000000002 84 2S 332.1 0 270.87 61.23 82 3S 128.25 0 106.74 21.51 83 1 -Constructed stormwater pond 2276.82 0 1912.53 364.29 84 BMP Schematic IMP RUNOFF INTENSITY P. DIA. P. SLOPE P. TYPE MANNING'S P. CAP. P. VELOCITY PIPE CAP. OVER FROM TO RIM COVER STR. CAST BUILD FROM TO TOTAL IMPERVIOUS INCR. CUM. % C INCR. CUM. PIPE CUM. i INCR. CUM. D [IN] S [FT/FT] n Q [CFS] MAX [FT/S] LENGTH [FT] Q [CFS] INVERT INVERT ELEV [FT] TYPE TYPE [FT] CB 121 CBMH 120 8696 3910 0.20 0.20 0.45 0.51 0.10 0.10 10.00 10.00 6.13 0.630 0.630 12 0.0044 RCP 0.013 2.363 3.01 31.00 1.73 893.77 893.63 897.8 2.80 2'x3' R-3067-V 4.00 CBMH 120 CBMH 107 8444 3852 0.19 0.39 0.46 0.52 0.10 0.20 0.17 10.17 6.13 0.617 1.247 12 0.0044 RCP 0.013 2.363 3.01 187.47 1.12 893.53 892.71 897.8 2.94 48" R-3067-V 4.24 CB 119 CBMH 118 10528 5578 0.24 0.24 0.53 0.57 0.14 0.14 10.00 10.00 6.13 0.846 0.846 12 0.0044 RCP 0.013 2.363 3.01 31.00 1.52 892.39 892.25 896.4 2.80 2'x3' R-3067-V 4.00 CBMH 118 CBMH 117 82107 4532 1.88 2.13 0.06 0.24 0.45 0.59 0.17 10.17 6.13 2.758 3.604 12 0.012 RCP 0.013 3.903 4.97 138.19 0.30 892.15 890.5 896.4 2.95 48" R-3067-V 4.25 CBMH 117 CBMH 116 11552 1340 0.27 2.39 0.12 0.28 0.07 0.66 0.46 10.64 5.84 0.436 3.869 15 0.004 RCP 0.013 4.086 3.33 86.37 0.22 890.4 890.05 899.4 7.52 48" R-3067-V 8.97 CBMH 116 CBMH 115 18273 1042 0.42 2.81 0.06 0.24 0.10 0.76 0.43 11.07 5.84 0.588 4.457 15 0.005 RCP 0.013 4.568 3.72 55.65 0.11 889.95 889.67 901.7 10.22 48" R-3067-V 11.77 CBMH 115 CBMH 114 22642 422 0.52 3.33 0.02 0.21 0.11 0.87 0.25 11.32 5.59 0.619 4.882 15 0.006 RCP 0.013 5.004 4.08 73.85 0.12 889.57 889.13 902.7 11.60 48" R-3067-V 13.15 CBMH 114 CBMH 113 28436 1783 0.65 3.98 0.06 0.24 0.16 1.03 0.30 11.62 5.59 0.890 5.772 15 0.008 RCP 0.013 5.778 4.71 138.50 0.01 889.03 887.92 901.7 11.10 48" R-3067-V 12.65 CBMH 113 CBMH 112 72895 2875 1.67 5.66 0.04 0.23 0.38 1.41 0.49 12.11 5.37 2.043 7.585 24 0.0018 RCP 0.013 9.598 3.06 89.74 2.01 887.82 887.66 899.7 9.68 48" R-3067-V 11.88 CBMH 112 CBMH 103 45092 18739 1.04 6.69 0.42 0.49 0.51 1.92 0.49 12.60 5.37 2.726 10.312 24 0.0021 RCP 0.013 10.367 3.30 101.41 0.06 887.56 887.35 898.4 8.57 48" R-3067-V 10.87 CB 111 CBMH 110 27898 16662 0.64 0.64 0.60 0.62 0.40 0.40 10.00 10.00 6.13 2.427 2.427 12 0.005 RCP 0.013 2.519 3.21 26.09 0.09 896.88 896.75 900.9 2.80 2'x3' R-3067-V 4.00 CBMH 110 CBMH 105 27465 6915 0.63 1.27 0.25 0.38 0.24 0.63 0.14 10.14 6.13 1.455 3.882 15 0.004 RCP 0.013 4.086 3.33 55.55 0.20 896.65 896.43 901.6 3.51 48" R-3067-V 4.96 CB 109 CBMH 108 35208 20348 0.81 0.81 0.58 0.60 0.49 0.49 10.00 10.00 6.13 2.996 2.996 12 0.008 RCP 0.013 3.187 4.06 26.01 0.19 898.51 898.3 902.5 2.80 2'x3' R-3067-V 4.00 CBMH 108 CBMH 107 29245 5973 0.67 1.48 0.20 0.34 0.23 0.72 0.11 10.11 6.13 1.412 4.408 12 0.016 RCP 0.013 4.507 5.74 51.71 0.10 898.2 897.37 902.7 3.22 48" R-3067-V 4.52 CBMH 107 CBMH 106 2667 858 0.06 1.93 0.32 0.43 0.03 0.95 0.15 10.26 6.13 0.160 5.815 18 0.004 RCP 0.013 6.644 3.76 132.22 0.83 892.61 892.08 903.1 4.53 48" R-3067-V 10.49 CBMH 106 CBMH 105 31967 2015 0.73 2.67 0.06 0.24 0.18 1.13 0.59 10.84 5.84 1.046 6.586 18 0.004 RCP 0.013 6.644 3.76 90.37 0.06 891.98 891.62 902.6 8.82 48" R-3067-V 10.62 CBMH 105 CBMH 104 2762 1739 0.06 4.00 0.63 0.64 0.04 1.80 0.40 11.24 5.59 0.227 10.065 18 0.0092 RCP 0.013 10.075 5.70 288.69 0.01 891.52 888.86 901.6 8.28 48" R-3067-V 10.08 CBMH 104 CBMH 103A 55087 6464 1.26 5.27 0.12 0.28 0.36 2.16 0.84 12.09 5.37 1.914 11.578 21 0.006 RCP 0.013 12.274 5.10 221.52 0.70 888.76 887.43 898.6 7.90 48" R-3067-V 9.85 CBMH 103ACBMH 103 81312 22787 1.87 7.13 0.28 0.40 0.74 2.90 0.72 12.81 4.99 3.689 14.453 24 0.0045 RCP 0.013 15.176 4.83 8.00 0.72 887.33 887.3 897.5 7.97 48" R-3067-V 10.17 CBMH 103 CBMH 102 81312 22787 1.87 15.69 0.28 0.40 0.74 5.56 0.72 13.32 4.99 3.689 27.728 24 0.0151 RCP 0.013 27.799 8.85 31.00 0.07 887.2 886.73 897.5 8.10 48" R-3067-V 10.30 CB 102A CBMH 102 34447 18527 0.79 0.79 0.54 0.58 0.46 0.46 10.00 10.00 6.13 2.796 2.796 12 0.007 RCP 0.013 2.981 3.80 8.00 0.19 893.51 893.45 897.5 2.80 2'x3' R-3067-V 4.00 CBMH 102 MH 101 34447 18527 0.79 17.27 0.54 0.58 0.46 6.47 0.06 13.38 4.99 2.274 32.276 24 0.021 RCP 0.013 32.783 10.44 161.69 0.51 886.63 883.23 897.5 8.57 48" R-3067-V 10.87 MH 101 FES 100 0 0 0.00 17.27 0.00 0.20 0.00 6.47 0.26 13.64 4.82 0.000 31.176 36 0.0022 RCP 0.013 31.284 4.43 65.27 0.11 883.13 882.99 888 1.67 48" R-1642 4.87 OCS 201 FES 200 0 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.000 0.000 30 0.0021 RCP 0.013 0.000 0.00 97.10 0.00 878.3 878.1 882.7 0.00 60" GRATE 4.39 Q [CFS]MH/CB AREA [SF] AREA [AC] A*C TIME OF CONC. [MIN] SB-3 Haugo GeoTechnical Services 2825 Cedar Avenue South Minneapolis, MN 55407 Figure #: 1 Drawn By: NA Date: 5/12/2021 Scale: None Project #: 21-0364 Soil Boring Location Sketch Erhart Property Chanhassen, Minnesota SB-2 SB-4 SB-5 SB-6 SB-1 Legend Approximate Soil Boring Location Disclaimer: Map and parcel data are believed to be accurate, but accuracy is not guaranteed. This is not a legal document and should not be substituted for a title search, appraisal, survey, or for zoning verification. HGTS# 21-0364 Figure 2: GPS Boring Locations Referencing Minnesota County Coordinates Basis – Carver County Boring Number Elevation (US Survey Feet) Northing Coordinate Easting Coordinate SB-1 879.8 169871.939 558784.102 SB-2 909.4 170790.608 558840.498 SB-3 903.4 170710.096 558778.512 SB-4 895.5 170330.988 558759.472 SB-5 878.9 170108.476 558574.178 SB-6 896.5 169801.079 558426.041 DRAFTSubject to RevisionSandy Lean Clay, trace Roots, black, wet. (Topsoil) (SC-SM) Silty Clayey Sand, fine to coarse grained, trace Gravel, gray, waterbearing, very loose to loose. (Glacial Till) (CL) Sandy Lean Clay, trace Gravel, brown and gray, wet, medium to rather stiff. (Glacial Till) Bottom of borehole at 14.5 feet. AU 1 SS 2 SS 3 SS 4 SS 5 SS 6 SS 7 1-1-1 (2) 2-2-2 (4) 3-3-4 (7) 2-12-18 (30) 2-13-18 (31) 2-2-6 (8) NOTES GROUND ELEVATION 878.2 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING 3.30 ft / Elev 874.90 ft AT END OF DRILLING --- AFTER DRILLING --- HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-1 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 DRAFTSubject to RevisionSandy Lean Clay, trace Roots, dark brown, wet. (Topsoil) (CL) Sandy Lean Clay, trace Gravel, brown, wet, rather stiff. (Glacial Till) (SC) Clayey Sand, fine to medium grained, trace Gravel, brown, moist, medium dense. (Glacial Till) Bottom of borehole at 14.5 feet. AU 8 SS 9 SS 10 SS 11 SS 12 SS 13 SS 14 2-4-6 (10) 6-18-12 (30) 7-7-7 (14) 6-6-8 (14) 6-9-11 (20) 5-8-12 (20) NOTES GROUND ELEVATION 909.4 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING --- Not Encountered AT END OF DRILLING --- Not Encountered AFTER DRILLING --- Not Encountered HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-2 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 DRAFTSubject to RevisionSilty Clay, trace Roots, black, wet. (Topsoil) (CL) Lean Clay, brown, wet, stiff to very stiff. (Glacial Till) (ML) Silty Sand, brown, moist, medium dense. (Glacial Till) (CL-ML) Sily clay, brown, moist, very stiff. (Glacial Till) (SC) Clayey Sand, fine to medium grained, trace Gravel, brown, medium dense. (Glacial Till) Bottom of borehole at 21.0 feet. AU 15 SS 16 SS 17 SS 18 SS 19 SS 20 SS 21 SS 22 6-8-10 (18) 2-6-8 (14) 8-12-11 (23) 8-10-12 (22) 4-8-11 (19) 1-8-11 (19) 7-10-11 (21) NOTES GROUND ELEVATION 903.4 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING --- Not Encountered AT END OF DRILLING --- Not Encountered AFTER DRILLING --- Not Encountered HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 15 20 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-3 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 DRAFTSubject to RevisionSandy Lean Clay, trace Roots, black, wet. (Topsoil) (SC) Clayey Sand, fine to medium grained, trace Gravel, loose to medium dense. (Glacial Till) (CL) Sandy Lean Clay, trace Gravel, wet, stiff. (Glacial Till) Bottom of borehole at 14.5 feet. AU 23 SS 24 SS 25 SS 26 SS 27 SS 28 SS 29 3-3-5 (8) 2-8-8 (16) 6-7-9 (16) 4-5-8 (13) 4-7-8 (15) 6-6-8 (14) NOTES GROUND ELEVATION 895.5 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING --- Not Encountered AT END OF DRILLING --- Not Encountered AFTER DRILLING --- Not Encountered HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-4 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 DRAFTSubject to RevisionSilty Clay, black, wet. (Topsoil) (CL) Sandy Lean Clay, trace Gravel, brown and gray, wet, soft to medium. (Glacial Till) (SC) Clayey Sand, fine to medium grained, trace Gravel, Sand Seam at 10 feet, brown and gray, waterbearing, medium dense. (Glacial Till) (CL) Sandy Lean Clay, trace Gravel, gray, wet, rather stiff. (Glacial Till) Bottom of borehole at 14.5 feet. AU 30 SS 31 SS 32 SS 33 SS 34 SS 35 SS 36 1-1-1 (2) 1-3-3 (6) 3-5-6 (11) 3-5-7 (12) 3-5-7 (12) 3-5-6 (11) NOTES GROUND ELEVATION 879.5 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING 10.80 ft / Elev 868.70 ft AT END OF DRILLING --- AFTER DRILLING --- HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-5 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 DRAFTSubject to RevisionSandy Lean Clay, trace Roots, dark brown, wet. (Topsoil) (CL) Sandy Lean Clay, trace Gravel, brown, wet, rather soft to rather stiff. (Glacial Till) (SC) Clay Sand, fine to medium grained, trace gravel, brown, moist, loose. (Glacial Till) (CL-ML) Sandy Clay, black, wet, rather stiff. (Glacil Till) Bottom of borehole at 14.5 feet. AU 37 SS 38 SS 39 SS 40 SS 41 SS 42 SS 43 2-2-4 (6) 2-2-3 (5) 3-4-5 (9) 2-4-5 (9) 3-5-6 (11) 3-6-6 (12) NOTES GROUND ELEVATION 896.5 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING --- Not Encountered AT END OF DRILLING --- Not Encountered AFTER DRILLING --- Not Encountered HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-6 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238