Approval/Denial Letter 8-29-06
~
CITY OF
CHANHASSEN
7700 Market Boulevard
PO Box 147
Chanhassen, MN 55317
Administration
Phone: 952.227.1100
Fax: 952.227.1110
Building Inspections
Phone: 952.227.1180
Fax: 952.227.1190
Engineering
Phone: 952.227.1160
Fax: 952.227.1170
Finance
Phone: 952.227.1140
Fax: 952.227.1110
Park & Recreation
Phone: 952.227.1120
Fax: 952.227.1110
Recreation Center
2310 Coulter Boulevard
Phone: 952.227.1400
Fax: 952.227.1404
Planning &
Natural Resources
Phone: 952.227.1130
Fax: 952.227.1110
Public Works
1591 Park Road
Phone: 952.227.1300
Fax: 952.227.1310
Senior Center
Phone: 952.227.1125
Fax: 952.227.1110
Web Site
www.ci.chanhassen.mn.us
August 29, 2006
Mr. Mike MacArthur
Zumbro River Constructors
312 Lake Hazeltine Blvd., Ste. 100
Chaska, MN 55318
Re: Planning Case #06-28
Interim Use Permits for Grading at 1560 Bluff Creek Drive and south of
Bluff Creek Drive and Hennepin County Regional Rail Corridor
Dear Mr. MacArthur:
This letter is to confirm that on August 28, 2006, the Chanhassen City Council
approved the following motions:
The Chanhassen City Council denied Planning Case #06-28 for Interim Use Permits
to grade and fill properties identified as Site 2 in the staff report (Harold Hesse
property located south of Bluff Creek Drive and Hennepin County Regional Rail
Corridor).
And,
The Chanhassen City Council approved Planning Case #06-28forInterim Use
Permits to grade and fill Site 3 (John K.lingelhutz property at 1560 Bluff Creek
Drive) in conformance with the grading plans prepared by Zumbro River
Constructors for the site, subject to the following conditions:
1. Overland hauling must utilize the existing creek crossing for the Bluff Creek
Drive realignment.
2. No fill shall be placed within the Bluff Creek Drive right-of-way.
3. Hours of operations are 7:00 a.m. and 6:00 p.m. Monday through Friday and
9:00 a.m. and 5:00 p.m. on Saturdays, with no work allowed on holidays.
4. Each site shall be examined by a professional wetland delineator to determine
whether jurisdictional wetlands exist on-site or within 150 feet of the
proposed fill. Any wetlands that are identified shall be delineated, then
reviewed by the City prior to any work commencing on-site. If the delineation
shows the proposed project toinc1ude wetland impact, the applicant shall obtain
a wetland alteration permit from the City prior to wetland impacts occurring.
5. A wetland buffer 16.5 to 20 feet in width (with a minimum average of 16.5
feet) shall be maintained around any aglurban wetlands. Wetland buffer areas
shall be preserved, surveyed and staked in accordance with the City's wetland
ordinance. The applicant shall install wetland buffer edge signs, under the
The City ot Chanhassen · A growing community with clean lakes, quality schools, a charming downtown, thriving businesses, winding trails. and beautiful parks. A great place to live, work, and play.
Mr. Mike MacArthur
August 29, 2006
Page 2
"
direction of City staff, before construction begins and shall pay the City $20 per sign. All
structures shall maintain a setback of at least 40 feet from aglurban wetland buffer edges.
6. Wetland replacement, if necessary, shall occur in a manner consistent with the wetland
alteration permit and the Minnesota Wetland Conservation Act (MR 8420).
7. Erosion control blanket shall be installed on all slopes greater than or equal to 3: 1. All
exposed soil areas shall have temporary erosion protection or permanent cover year round,
according to the following table of slopes and time frames:
Type of Slope
Steeper than 3: 1
10:1 to 3:1
Flatter than 10: 1
Time
7 days
14 days
21 days
(Maximum time an area can
remain open when the area
is not actively being worked.)
These areas include constructed storm water management pond side slopes, and any exposed
soil areas with a positive slope to a storm water conveyance system, such as a curb and gutter
system, storm sewer inlet, temporary or permanent drainage ditch or other natural or man
made systems that discharge to a surface water.
8. Silt fence shall be installed at the base of all proposed slopes in accordance with Chanhassen
Standard Detail Plates 5300. A rock construction entrance meeting the specifications of
Chanhassen Standard Detail Plate 5301 shall be installed where truck traffic will enter and exit
Bluff Creek Drive. Street cleaning of soil tracked onto public streets shall include daily street
scraping and street sweeping as-needed. Wimco-type inlet protection shall be installed in
accordance with Chanhassen Standard Detail Plate 5302A in all catch basins within 200 feet of
the proposed project sites and maintained as needed. The construction plans shall be revised to
show the locations of the proposed silt fence, rock construction entrances and Wimco-type inlet
protection and to include Chanhassen Standard Detail Plates 5300, 5301 and 5302A.
9. The applicant shall apply for and obtain permits from the appropriate regulatory agencies
(e.g., Riley-Purgatory-Bluff Creek Watershed District, Minnesota Pollution Control Agency
(NPDES Phase II Construction Site Permit), Minnesota Department of Natural Resources,
Minnesota Department of Transportation) and comply with their conditions of approval.
Zumbro River Constructors shall apply for and receive an amendment to their existing
NPDES Phase II Construction Permit for the Trunk Highway 212 project from the Minnesota
Pollution Control Agency to incorporate a storm water pollution prevention plan for these
sites.
10. The applicant should review proposed slopes and runoff velocities for the site and provide
additional rock checks as an erosion control mechanism if needed. Rock checks proposed
within the right-of-way for Bluff Creek Drive must be reviewed and approved by the City
prior to installation.
Mr. Mike MacArthur
August 29,2006
Page 3
If you have any questions or need additional information, please contact me at (952) 227-1131 or
Allyson Fauske at (952) 227-1164.
Sincerely;
Robert Generous, AICP
Senior Planner
ec: Kate Aanenson, Community Development Director
Alyson Fauske, Assistant City Engineer
Todd Gerhardt, City Manager
Paul Oehme, City Engineer
c: Harold Hesse
John Klingelhutz
g:\plan\2006 planning cases\06-28 zumbro river constructors 312\approve and deny letter. doc