SWPPP Plan ERHART FARM SWPPP Storm Water Pollution Prevention Plan Chanhassen, MN Prepared For: Black Cherry Development, LLC 14500 Martin Drive, STE. 3000 Eden Prairie, MN 55344 Prepared By: Alliant Engineering, Inc. 733 Marquette Avenue, Suite 700 Minneapolis, MN 55402 ERHART FARM May 5, 2022 STORM WATER POLLUTION PREVENTION PLAN (SWPPP) ERHART FARM MASS GRADING AND STREET AND UTILITY DEVELOPMENT CITY OF CHANHASSEN CARVER COUNTY, MINNESOTA RILEY PURGATORY BLUFF CREEK WATERSHED DISTRICT May 5, 2022 Plans Prepared for: Black Cherry Development, LLC 14500 Martin Drive, STE. 3000 Eden Prairie, MN 55344 I hereby certify that this plan, specification or report was prepared by me or under my direct supervision and that I am a duly Registered Professional Engineer under State of Minnesota Statutes Sections 326.02 to 326.16. Mark Rausch Mark Rausch, P.E. Date: 5-5-2022 Reg. No: 43480 GENERAL INDEX I. Title Sheet II. Signature Page III. MPCA Coverage Card IV. MPCA Coverage Letter V. SWPPP Narrative VI. Location/Topographic Map VII. Grading, & Erosion Control Plan Sheets VIII. Inspection Logs IX. Geotech Report AUTHORIZATION TO DISCHARGE STORMWATER ASSOCIATED WITH CONSTRUCTION ACTIVITY UNDER THE NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES)/ STATE DISPOSAL SYSTEM (SDS) PROGRAM C00063782 Permittee (Owner): Black Cherry Development Permittee (Operator): NTK Earthworks, LLC Project Name: Erhart Farm City or Township: Chanhassen, County: Carver Location description: Parent Parcel is, E of Powers Blvd, W of Great Plains Blvd, S of Foxwood Development, N of W 96th Parent Parcel is, E of Powers Blvd, W of Great Plains Blvd, S of Foxwood Development, N of W 96thSee development plans in SWPPP for project site Issuance date: May 16, 2022 Expiration date: July 31, 2023 The state of Minnesota, on behalf of its citizens through the Minnesota Pollution Control Agency (MPCA), authorizes the Permittee named above seeking coverage under this general permit to discharge stormwater associated with construction activity to waters of the state of Minnesota in accordance with the requirements of this permit. The goal of this permit is to reduce pollutant levels in point source discharges and protect water quality in accordance with the U.S. Clean Water Act, Minnesota statutes and rules, and federal laws and regulations. This permit is effective on the issuance date identified above. This permit expires at midnight on the expiration date identified above. Signature: Ryan Anderson This document has been electronically signed. for the Minnesota Pollution Control Agency Ryan Anderson Supervisor, Stormwater Outreach, Engineering and Research Unit St. Paul Office Municipal Division Permit application: Questions on this permit? Submit via the MPCA Online eServices Portal at Contact eServices at https://rsp.pca.state.mn.us/ 651-757-2728 or 1-844-828-0942 t-wq-strm2-03 · LB 1311 · 8/22/18 May 17, 2022 Project Owner: Tim Erhart 14500 Martin Dr Ste 3000 Eden Prairie, MN 55344-2039 Project Contractor: Kevin J Miller PO Box 879 Watertown, MN 55388-0879 RE: NPDES/SDS General Stormwater Permit for Construction Activity (MNR100001) Application Permit ID Number: C00063782 Project Name: Erhart Farm The Erhart Farm project has been granted coverage by the Minnesota Pollution Control Agency (MPCA) under the National Pollutant Discharge Elimination System (NPDES)/State Disposal System (SDS) Stormwater Permit (Permit) for Construction Activity. Permit coverage is effective for this project on May 16, 2022. You are required to comply with the terms of the permit to prevent erosion and control sediment from your site with the procedures established in your stormwater pollution prevention plan (SWPPP). You are also required to upgrade your SWPPP and erosion prevention and sediment control best management practices as site and weather conditions dictate throughout the entire term of the project. Once all construction activity has been completed at this project, you must submit a notice of termination (NOT) form to the MPCA within 30 days of meeting the conditions outlined in Part II (C) of the permit. Please check the MPCA website (http://www.pca.state.mn.us/water/stormwater) or call to request an NOT form and fact sheet. Please save this letter for your records. If you have any questions about permit coverage for this project, please contact the Construction Stormwater Program at 651-757-2119 or toll free at 800-657-3804. Page 1 of 10 SWPPP Narrative Stormwater Pollution Prevention Plan (SWPPP) I. General Construction Activity Information a. Project name: Erhart Farm b. Describe the construction project location (address/city or township/county/latitude/longitude): Address or describe area: Parent Parcel is, E of Powers Blvd, W of Great Plains Blvd, S of Foxwood Development, N of W 96th City or Township: Chanhassen State: MN Zip code: 55317 Latitude/Longitude of approximate centroid of project: 44.832309 , -93.540730 c. Describe the construction activity (type of construction, phases, timelines, potential for discharge of sediment and other pollutants, etc.): • 14.912 ± Acres will be disturbed for Mass grading, utility installation, street installation, and private utility installation. • Soil disturbing activities will include: the installation of a silt fence, excavation and fill, re-spreading of topsoil, and grading restoration which will consist of seeding all disturbed areas. Utility installation, and street construction. Multiple erosion and sediment control BMP’s are planned to minimize sediment transport. See the Erosion & Sediment Control Plan for specific locations. Project type: (To check the checkboxes, ‘double click’ the box and select “checked” and select “okay”.) Residential Commercial/Industrial Road construction Residential and road construction Other (describe): Utility installation d. Number total of acres to be disturbed: 14.912 (tenths of an acre) e. Pre-construction acres of impervious surface: 1.145 (tenths of an acre) f. Post-construction acres of impervious surface: 5.345 (tenths of an acre) g. Total new impervious surface acres: 4.2 (tenths of an acre) (Examples of impervious surface include rooftops, sidewalks, patios, driveways, parking lots, storage areas, and concrete, asphalt, or gravel roads. II. Receiving Waters a. List all waters within one mile (nearest straight line distance) that are likely to receive stormwater runoff from the project site both during or after construction: Receiving waters within one mile of project property edge: Water body ID* Name of water body Type (ditch, pond, wetland, calcareous fen, lake, stream, river) Special water? (See Stormwater Permit Appendix A) Impaired Water?** (See Stormwater Permit Appendix A) Lake Riley Lake Yes No Yes No * Water Body identification (ID) might not be available for all water bodies. Use the Special and Impaired Waters Search Tool at: http://www.pca.state.mn.us/water/stormwater/stormwater-c.html. ** Impaired water for the following pollutant(s) or stressor(s): phosphorus, turbidity, dissolved oxygen, or biotic impairment. b. Use the Special and Impaired Waters Search Tool to locate special and impaired waters at http://www.pca.state.mn.us/wfhya5b). c. Incorporate into this SWPPP any additional Best Management Practices (BMPs) or other specific construction related implementation activities identified in an approved Total Maximum Daily Load and Waste Load Allocations. d. Identify adjacent public waters where the Minnesota Department of Natural Resources (DNR) has declared Page 2 of 10 “work in water restrictions” during fish spawning timeframes: Not Applicable e. Attach maps (U.S. Geologic Survey 7.5 minute quadrangle, National Wetland Inventory maps or equivalent) showing the location and type of all receiving waters, including wetlands, drainage ditches, stormwater ponds or basins, etc. that will receive runoff from the project. Use arrows showing the direction of flow and distance to the water body. See Attached Map. f. Identify wetland impacts: 1. Will construction result in any potential adverse impacts to wetlands, including excavatio n, degradation of water quality, draining, filling, permanent inundation or flooding, conversion to a stormwater pond? Yes No 2. If yes, describe impacts and mitigation measures that were taken to address the impacts (in accordance with Part D of Appendix A of the permit) and attach to this SWPPP, copies of permits or approvals from an official state wide wetland program issued specifically for this project or site: g. Describe any stormwater mitigation measures that will be implemented, as a result of an environmental review, endangered or threatened species review or archeological site review: This site was not subject to an environmental or archaeological review. h. Describe any additional (or different) stormwater management measures required for karst or drinking water supply management areas to protect groundwater standards: Not Applicable III. Project Plans and a. Attach to this SWPPP site maps and/or plan sheets that depict the following features: • The project location and construction limits. • Existing and final grades. • Locations of areas not to be disturbed (e.g., buffer zones, wetlands, etc.). • Locations of all temporary and permanent erosion and sediment control BMPs as required in Part III. C & D. and Part IV of the permit. • Buffer zones as required in Part IV.C.9 or Appendix A, Part C.3. of the permit. • Locations of potential pollution-generating activities identified in Part IV. F. of the permit. • Standard details for erosion and sediment control BMPs to be installed at the site. b. List all anticipated erosion prevention and sediment control BMP quantities needed for the life of the project (e.g., linear ft. silt fence, square feet erosion blanket, tons mulch, etc.): As a note, all erosion control quantities are an estimate. Final erosion control quantities will be field verified with owner, city, engineer, and watershed officials. Pre Grading Silt Fence – 5,400 LF Erosion Control Blanket – 8,450 SY Post Grading Silt Fence- 701 LF Seeding – 9.3 AC IV. Temporary Erosion Prevention Practices a. Describe the types of temporary erosion prevention BMPs expected to be implemented on this site during construction: 1. Methods of temporarily stabilizing soils and soil stockpiles (e.g., mulches, hydraulic tackifiers, erosion blankets, etc.): Erosion Control Blanket - This blanket shall be installed as indicated on the erosion and sediment control plan. It will provide slope protection until the turf is established. Hydromulch A hydromulch (Type 4) may be used for temporary erosion control practices after grading activities cease. Seeding Restoration - Temporary/Permanent Stabilization (Seeding) – Temporary seeding must be placed as soon as practical. Sediment Control Logs - Sediment Control Log shall be utilized in concentrated ditch and swales to Page 3 of 10 control velocities and contain sediment during construction until vegetation is established. 2. Methods of dissipating velocity along stormwater conveyance channels and at channel outlets (e.g., check dams, sediment traps, rip rap, etc.): Rip-Rap – Rip Rap shall be utilized at all pond inlets and around outlet control devices. 3. Methods to be used for stabilization of ditch and swale wetted perimeters (Note that mulch, hydraulic soil tackifiers, hydromulches, etc. are not acceptable soil stabilization methods for any part of a drainage ditch or swale): Sediment Control Logs – Sediment Control Log shall be utilized in concentrated ditch and swales to control velocities and contain sediment during construction until vegetation is established. Erosion Control Blanket – Erosion Control Blanket shall be utilized in ditch and swale areas to provide protection until permanent turf is established. 4. Methods to be used for energy dissipation at pipe outlets (e.g., rip rap, splash pads, gabions, etc.): II. Rip-Rap – Rip Rap shall be utilized at all pond inlets and around outlet control devices. 1. Methods to be used to promote infiltration and sediment removal on the site prior to offsite discharge, unless infeasible (e.g., direct stormwater flow to vegetated areas): Silt Fence – Silt fences are designed as a temporary sediment barrier consisting of a filter fabric attached to support posts. This site has four applications for silt fence. These applications are as follow: 1. The installation of silt fence along the grading limits to protect the neighboring properties from sediment during the grading and utility construction process. 2. The installation of silt fence around the created ponds after construction to control the sediment runoff until the turf is established and the development is completed. 3. The installation of silt fence surrounding temporary stockpiles. 4. The installation of post construction silt fence to protect new roads and storm sewer infrastructure. Sediment Control Log – Sediment Control Log shall be utilized in concentrated ditch and swales to control velocities and contain sediment during construction until vegetation is established. Temp Sedimentation Basins – Temporary Sedimentation Basins shall be used to protect downstream waters prior to discharge. A floating skimmer shall drain the basins from the water level in order to prevent the discharge of suspended sediment. b. Describe timelines to be implemented at this site for completing the installation of the erosion prevent ion BMPs listed in i, ii, iii, and iv. (see Part IV. B. of the permit for minimum requirements). If applicable, include the timeline for completing soil stabilization for areas within 200 feet of a public water with work in water restrictions due to fish spawning time frames (Part IV.B.2.) and soil stabilization timelines for portions of the site that drain to special or impaired waters as required in Appendix A Part C. 1.a.: 1. Prior to any construction, Silt Fence is to be installed. Dewatering plan to be provided to city, and watershed district and approved. 2. All erosion control installations shall remain in place and be maintained in good condition by the contractor until the site has been re-vegetated. 3. Disturbed areas to be re-vegetated. 4. The contractor shall schedule site grading, so that the general site can be mulched and re- seeded soon after disturbance. Areas that will not be subject to construction traffic for 7 days or longer shall be seeded and mulched or sodded as soon as practical but not later than the following end of business day. 5. Contractor shall install erosion control devices as indicated on this erosion control plan and any additional required based on means, methods and sequences of construction. Page 4 of 10 c. Describe additional erosion prevention measures that will be implemented at the site during construction (e.g., construction phasing, minimizing soil disturbance, vegetative buffers, horizontal slope grading, slope draining/terracing, etc.): Not Applicable. d. If applicable, include additional requirements in Appendix A Part C.3 regarding maintaining a 100-foot buffer zone or installing redundant BMPs for portions of the site that drain to special waters: Not Applicable e. If applicable, describe additional erosion prevention BMPs to be implemented at the site to protect planned f. infiltration areas: Post grading Silt Fence – Silt fences are designed as a temporary sediment barrier consisting of a filter fabric attached to support posts. Infiltration areas shall not be excavated to withing 3’ of the bottom of the basin until contributing drainage area is vegetated. g. Filtration areas Post grading Silt Fence – Silt fences are designed as a temporary sediment barrier consisting of a filter fabric attached to support posts. Filtration basins shall not be excavated to within 1’ of bottom until contributing drainage area is vegetated. V. Temporary Sediment Control Practices a. Describe the methods of sediment control BMPs to be implemented at this site during construction to minimize sediment impacts to surface waters, including curb and gutter systems: 1. Methods to be used for down gradient perimeter control: Silt Fence – Silt fences are designed as a temporary sediment barrier consisting of a filter fabric attached to support posts. This site has four applications for silt fence. These applications are as follow: 1. The installation of silt fence along the grading limits to protect the neighboring properties from sediment during the grading and utility construction process. 2. The installation of silt fence around the created ponds after construction to control the sedim ent runoff until the turf is established and the development is completed. 3. The installation of silt fence surrounding temporary stockpiles. 4. The installation of post construction silt fence to protect new roads and storm sewer infrastructure. Sediment Control Log – Sediment Control Log shall be utilized in concentrated ditch and swales to control velocities and contain sediment during construction until vegetation is esta blished. Sediment Control Log shall be utilized to prevent sediment transport in winter conditions. 2. Methods to be used to contain soil stockpiles: Sediment Control Log – See Above Silt Fence – See Above 3. Methods to be used for storm drain inlet protection: Page 5 of 10 Storm Drain Inlet Protection – Storm drain inlet protection is a sediment barrier placed around a storm sewer inlet. This structure traps sediment before it enters the storm sewer system. The contractor will be required to install inlet protection per the City of Chanhassen details. 4. Methods to minimize vehicle tracking at construction exits and street sweeping activities: Temporary Construction Entrance – A rock entrance berm is constructed of coarse clean rock installed at the proposed entrance point for all construction vehicles. A detail of the rock entrance berm is shown on the final grading plan. This stone pad provides a tire cleaning mechanism for all vehicles leaving the site. There is one entrance for this project. Please see the Erosion & Sediment Control Plan for location of rock entrance berm. 5. If applicable, additional sediment controls (e.g., diversion berms) to be installed to keep runoff away from planned infiltration areas when excavated prior to final stabilization of the contributing drainage area: Infiltration basins shall not be excavated to within 3’ of bottom until contributing drainage areas are stabilized. 6. Describe methods to be used to minimize soil compaction and preserve top soil (unless infeasible) at this site: 7. A minimum of 6” of top soil shall be stripped and stockpiled in a designated location determined by the contractor to prevent contamination of top soil. Contractor will respread from the stockpile per MPCA requirements. 8. Describe plans to preserve a 50-foot natural buffer between the project’s soil disturbance and a surface water or plans for redundant sediment controls if a buffer is infeasible: A second row of silt fence are propsosed. 9. Describe plans for use of sedimentation treatment chemicals (e.g., polymers, flocculants, etc.) see Part IV.C.10 of the permit: Not Applicable b. Is the project required to install a temporary sediment basin due to 10 or more acres draining to a common location or 5 acres or more if the site is within 1 mile of a special or impaired water? Yes No If yes, describe (or attach plans ) showing how the basin will be designed and constructed in accordance with Part III.C of the permit. See construciton plans. c. Will the project include dewatering, basin draining? Yes No If yes, describe measures to be used to treat/dispose of turbid or sediment-laden water and method to prevent erosion or scour of discharge points (see Part IV. D of the permit): d. Will the project include use of filters for backwash water? Yes No If yes, describe how filter backwash water will be managed on the site or properly disposed (see Part III.D.3. of the permit): VI. Permanent Stormwater Management System a. Will the project result in one acre or more of new impervious surfaces or result in one acre or more of new impervious in total if the project is part of a larger plan of development? Yes No b. If yes, a water quality volume of one inch of runoff from the cumulative new impervious surfaces must be retained on site (see Part III.D of the permit) through infiltration unless prohibited due to one of the reasons in Part III.D.1.j. If infiltration is prohibited identify other method of other volume reduction (e.g., filtration system, wet sedimentation basin, regional ponding or equivalent method: c. Attach design parameters (see Part III.D.) for the planned permanent stormwater management system, including volume calculations, discharge rate calculation, construction details including basin depth, outlet configurations, location, design of pre-treatment devices and timing for installation. For more design information consult the Minnesota Stormwater Manual on the MPCA website at http://stormwater.pca.state.mn.us/index.php/Main_Page. Page 6 of 10 There is no new stormwater management. d. For infiltration systems attach on site soil testing results verifying soil type and distance to the seasonal water table or bedrock (from bottom of the basin) in the location of the infiltration or filtration system. Not Applicable e. For linear projects with lack of right of way to install treatment systems capable of treating the entire water quality volume, identify other method(s) for providing treatment of runoff prior to discharge to surface waters (e.g., grassed swales, filtration systems, smaller ponds or grit chambers, etc.): Not Applicable 1. Attach to this SWPPP documentation of reasonable attempts made to obtain right of way for stormwater treatment systems. f. For projects that discharge to trout streams, including tributaries to trout streams, identify method of incorporating temperature controls into the permanent stormwater management system: Not Applicable VII. Inspection and Maintenance Activities a. Identify the trained individual(s) responsible for installing, supervising, repairing, inspecting, and maintaining erosion prevention and sediment control BMPs at the site: SWPPP Designer (Training Documentation Attached): Tyler Stricherz Alliant Engineering, Inc. 612-758-9330 SWPPP Inspector (Training Documentation Attached): Rae Tressler Alliant Engineering, Inc. 612-237-9451 b. Attach training documentation for each individual: Page 7 of 10 Installation Contractor to provide other certifications as identified and requested. c. Areas to be inspected and maintained (see Part IV.E.5. and 6. of the permit): 1. Inspect sediment silt fence regularly such that there is no sediment transport. 2. Replacement - shall be replaced promptly when it becomes ineffective before the barrier is no longer necessary. 3. Sediment removal - Sediment deposits should be inspected after each storm event. They must be removed when deposits reach approximately one-third the height of the barrier. Any sediment remaining in place after bmp is no longer required, shall be dressed to conform with existing grade, prepared, and seeded with the appropriate seed mix, or sodded as directed by the engineer. 4. Removal of silt fence – silt fence shall be removed when they have served their useful purpose, but not before the upward sloping area has been permanently stabilized. If the upward sloping are a is to be exposed longer than six (6) months, that area shall be covered with temporary vegetation when first exposed. 5. The contractor must routinely inspect the construction site once every seven (7) days during active construction and within 24 hours after a rainfall event greater than 0.5 inches in 24 hours. 6. All inspections and maintenance conducted during construction must be recorded in writing and these records must be retained with the SWPPP records of each inspection and maintenance activity shall include: A. Date and time of inspections. B. Name of person(s) conducting inspections. C. Findings of inspections, including recommendations for corrective actions. d. Corrective actions taken (including dates, times, and party completing mainten ance actives. e. Date and amount of all rainfall events greater than 1/2 inch (0.5 inches) in 24 hours: f. Documents of changes made to the SWPPP as required in part iii.a.4. 7. Where parts of the construction site have undergone final stabilization, but work remains on other parts of site, inspections of the stabilized areas may be reduced to once per month. Where work has been suspended due to frozen ground conditions, the required inspections and maintenance must take place as soon as runoff occurs at the site or prior to resuming construction, whichever comes first. 8. Pipe outlets must have energy dissipation within 24 hours of connecting to a surface water or permanent stormwater treatment system. 9. Stockpiles must be located outside of natural buffers or surface waters, including stormwater conveyances( curb and gutter systems) unless there is a bypass. Page 8 of 10 10. Temporary and permanent sediment basins must be drained and sediment removed when the depth of sediment collected reaches one-half the storage volume. 11. Sediment on paved surfaces (sediment tracked from vehicles) must be removed within one calender day of discovery,. Permanent stormwater treatment BMPs must be inspected and maintained. VIII. Pollution Prevention Management Measures a. Describe practices for storage of building products with a potential to leach pollutants to minimize exposure to stormwater: All trash and construction debris from the site will be collected and deposited in a dumpster. A dumpster will be required for each new home constructed. The dumpsters shall be emptied as necessary. No construction materials shall be buried on site. All solid waste must be disposed if of in accordance with the MPCA disposal requirements b. Describe practices for storage of pesticides, herbicides, insecticides, fertilizers, treatment chemical, and landscape materials: Pesticides, Fertilizers, etc. will be applied only in the minimum amounts as recommended by the manufacturer. Once applied, the potential pollutions will be worked into the soil to limit the exposure to stormwater. c. Describe practices for storage and disposal of hazardous materials or toxic waste (e.g., oil, fuel, hydraulic fluids, paint solvents, petroleum-based products, wood preservative, additives, curing compounds, and acids) according to Minn. R. ch. 7045, including restricted access and secondary containment: • All hazardous materials like oil, gasoline and paint must be properly stored. To prevent spills and leaks, secondary containment is necessary for hazardous materials. • A leak proof containment facility shall be used for fuel storage tanks to prevent any leakage from infiltrating the ground. • An effort will be made to store only enough products to do the required job. • All materials stored on site will be stored in a neat and orderly manner. • All products will be kept in their original container, with the original labels still attached, unless they are not re-sealable. • Substances will not be mixed with one another unless recommended by the manufacturer. • Whenever possible all of a product will be used up before disposing of a container. • Manufacturers’ recommendations for proper disposal will be followed. • The site superintendent will routinely inspect the site to ensure proper disposal of all on site materials. d. Describe collection, storage and disposal of solid waste in compliance with Minn. R. ch. 7035: All trash and construction debris from the site will be collected and deposited in a dumpster. A dumpster will be required for each new home constructed. The dumpsters shall be emptied as necessary. No construction materials shall be buried on site. All solid waste must be disposed if of in accordance with the MPCA disposal requirements. e. Describe management of portable toilets to prevent tipping and disposal of sanitary wastes in accordance with Minn. R. ch. 7040: Portable Toilets must be in accordance with the above referenced standard. f. Describe spill prevention and response for fueling and equipment or vehicle maintenance: The following materials and/or substances are expected to be present onsite during construction- Fertilizers, Petroleum Based Products,Cleaning Solvents, Detergents, Adhesive Solvents, Wood Product Specific Practices – Petroleum Products: All onsite vehicles and equipment will be monitored for leaks and receive regular preventative maintenance to reduce the chance of leakage. Petroleum products will be stored in a tightly sealed container, which is clearly labeled. Any asphalt substances used onsite will be applied according to the manufacturer’s recommendations. Fertilizers: Fertilizers will be applied only in the minimum amounts as recommended by the manufacturer. Once applied, the fertilizer will be worked into the soil to limit the exposure to stormwater. Page 9 of 10 Spill Control Practices – • All spills will be cleaned up immediately after discovery, in accordance with the manufacturer’s recommended methods. • The spill area will be kept well ventilated. • Spills of toxic or hazardous materials must be reported to the Minnesota Duty Officer 1-800-422-0798. • A log of the spill type, location, date, and time will be created by the job superintendent. The spill prevention plan will be adjusted to include measures to prevent this type of spill from reoccurring. g. Describe containment and disposal of vehicle and equipment wash water and prohibiting engine degreasing on the site: External washing of trucks and other construction vehicles must be limited to a defined area of the site. Runoff must be contained and waste properly disposed of. No engine degreasing is allowed on site. h. Describe storage and disposal of concrete and other washout wastes so that wastes do not contact the ground: A leak proof containment facility shall be used for all liquid and solid wastes generat ed by concrete washout operations. Liquid and solid wastes shall not come in contact with the ground and must be disposed of in accordance with the MPCA. IX. Final Stabilization a. Describe method of final stabilization (permanent cover) of all disturbed areas: All areas disturbed by construction shall be stabilized from erosion as soon as possible and not later than the end of the next business day following substantial completion of grading in that area. Temporary or permanent seed and mulch shall cover all exposed soils if grading completion is delayed longer than 7 days. General temporary seed shall be mndot mix 21-112 @ 100 lbs. per acre or approved equal. Permanent seed shall be mndot mix 34-271 @ 12 lbs. per acre , 35-241 @ 36.5 lbs per acre 22-112 @ 40 lbs per acre or approved equal. (planting dates per spec 2575) mulch shall be mndot type 1 (clean oat straw) @ 2 tons per acre and disk anchored in place or approved equal. Fertilizer shall be 80-80-80 npk per acre (unless P restrictions apply) and incorporated into the seed bed. All temporary erosion and sediment control measures shall be properly disposed of within thirty (30) days after final site stabilization is achieved or after the temporary measures are no longer needed. b. Describe procedures for completing final stabilization and terminating permit coverage (see Part IV.G.1-5): The contractor must ensure final stabilization of the site. The contractor must submit a notice of termination (NOT) within 30 days after final stabilization is complete, or another owner/operator (permittee) has assumed control of all areas of the site that have not undergone final stabilization. Final Stabilization can be achieved when: All soil disturbing activities at the site have been completed and all soils must be stabilized by a uniform perennial vegetative cover with a density of 70 percent over the entire pervious surface area, or other equivalent means necessary to prevent soil failure under erosive conditions and; a. All drainage ditches, constructed to drain water from the site after construction is complete, must be stabilized to preclude erosion; b. All temporary synthetic, and structural erosion prevention and sediment control bmps (such as silt fence) must be removed as part of the site final stabilization; and c. The contractors must clean out all sediment from conveyances and from temporary sedimentation basins that are to be used as permanent water quality management basins. Sediment must be stabilized to prevent it from being washed back into the basin, conveyances or drainage ways discharging off-site or to surface waters. The clean out of permanent basins must be sufficient to return the basin to design capacity. Page 10 of 10 X. RPBLWD Requirements. 1. PROPOSED EROSION CONTROL CAN BE FIELD FIT AND ADJUSTED AS NEEDED WITH WATERSHED/INSPECTOR. IF CHANGES ARE NEEDED/MADE, DOCUMENT ON PLAN AND KEEP ON RECORD. 2. CONSTRUCTION ACTIVITIES ARE TO BE COMPLETED DURING WINTER CONDITIONS. CONTINUE TO ADJUST EROSION CONTROL MEASURES ACCORDING TO FIELD CONDITIONS. 3. NATURAL TOPOGRAPHY AND SOIL CONDITIONS MUST BE PROTECTED, INCLUDING RETENTION ONSITE OF NATIVE TOPSOIL TO THE GREATEST EXTENT POSSIBLE. 4. FINAL SITE STABILIZATION MEASURES MUST SPECIFY THAT AT LEAST SIX INCHES OF TOPSOIL OR ORGANIC MATTER BE SPREAD AND INCORPORATED INTO THE UNDERLYING SOIL DURING FINAL SITE TREATMENT WHEREVER TOPSOIL HAS BEEN REMOVED. 5. CONSTRUCTION SITE WASTE SUCH AS DISCARDED BUILDING MATERIALS, CONCRETE TRUCK WASHOUT, CHEMICALS, LITTER AND SANITARY WASTE MUST BE PROPERLY MANAGED. 6. ALL TEMPORARY EROSION AND SEDIMENT CONTROL BMPS MUST BE MAINTAINED UNTIL COMPLETION OF CONSTRUCTION AND VEGETATION IS ESTABLISHED SUFFICIENTLY TO ENSURE STABILITY OF THE SITE, AS DETERMINED BY THE DISTRICT. 7. ALL TEMPORARY EROSION AND SEDIMENT CONTROL BMPS MUST BE REMOVED UPON FINAL STABILIZATION. 8. SOIL SURFACES COMPACTED DURING CONSTRUCTION AND REMAINING PERVIOUS UPON COMPLETION OF CONSTRUCTION MUST BE DECOMPACTED TO ACHIEVE A SOIL COMPACTION TESTING PRESSURE OF LESS THAN 1,400 KILOPASCALS OR 200 POUNDS PER SQUARE INCH IN THE UPPER 12 INCHES OF THE SOIL PROFILE WHILE TAKING CARE TO PROTECT UTILITIES, TREE ROOTS, AND OTHER EXISTING VEGETATION. 9. ALL DISTURBED AREAS MUST BE STABILIZED WITHIN 7 CALENDAR DAYS AFTER LAND-DISTURBING WORK HAS TEMPORARILY OR PERMANENTLY CEASED ON A PROPERTY THAT DRAINS TO AN IMPAIRED WATER, WITHIN 14 DAYS ELSEWHERE. 10. THE PERMITTEES MUST, AT A MINIMUM, INSPECT, MAINTAIN AND REPAIR ALL DISTURBED SURFACES AND ALL EROSION AND SEDIMENT CONTROL FACILITIES AND SOIL STABILIZATION MEASURES EVERY DAY WORK IS PERFORMED ON THE SITE AND AT LEAST WEEKLY UNTIL LAND-DISTURBING ACTIVITY HAS CEASED. THEREAFTER, THE PERMITTEE MUST PERFORM THESE RESPONSIBILITIES AT LEAST WEEKLY UNTIL VEGETATIVE COVER IS ESTABLISHED. THE PERMITTEES WILL MAINTAIN A LOG OF ACTIVITIES UNDER THIS SECTION FOR INSPECTION BY THE DISTRICT ON REQUEST. Note: -Orange circle is a 1-mile radius of project location. - Pin in center of circle is project location. __ _________________________________________________________________________________ ___ __ ______ _______ Erosion and Sediment Control Inspection Report Form Project Name and Location: Weather: Rain in the last 24 hours (inches): Owner/Permittee: A. Beginning Date of Current Construction: B. Current Construction/Active Areas: C. Problem Areas/Special Observations (*ONLY - Note the problem areas below*) BMP Location Observations, Effectiveness & Corrective Actions Ordered Corrective Actions Needed By D. Listing of Areas where construction operations have permanently or temporarily stopped: E. Have items noted on last inspection been corrected? YES NO (If no, Explain): NOTE: Inspection comments above indicate deficiencies only. Deficiencies must be corrected, unless otherwise noted. All other Pollution Control Measures on site are considered to be in good working condition Inspector Signature Date of Inspection □ Borrow Areas □ General Site Condition (trash, etc.) □ Erosion Blankets, Hydromulch/Seed, etc □ Stabilized Construction Entrance □ Sediment Basins & Discharge Locations □ Sediment Barriers (i.e.: ditch checks) □ Seed/Sod Areas Pollution Control Measures Checklist: □ Inlet Barrier (i.e.: gravel bags) 6 GOALS: • No sediment leaves the site • Lines of defense everywhere & always • Cover quickly • Protect the swale • Ditch and channel • Inspect, clean and fix SB-3 Haugo GeoTechnical Services 2825 Cedar Avenue South Minneapolis, MN 55407 Figure #: 1 Drawn By: NA Date: 5/12/2021 Scale: None Project #: 21-0364 Soil Boring Location Sketch Erhart Property Chanhassen, Minnesota SB-2 SB-4 SB-5 SB-6 SB-1 Legend Approximate Soil Boring Location Disclaimer: Map and parcel data are believed to be accurate, but accuracy is not guaranteed. This is not a legal document and should not be substituted for a title search, appraisal, survey, or for zoning verification. HGTS# 21-0364 Figure 2: GPS Boring Locations Referencing Minnesota County Coordinates Basis – Carver County Boring Number Elevation (US Survey Feet) Northing Coordinate Easting Coordinate SB-1 878.2 169958.73 558705.895 SB-2 909.4 170790.608 558840.498 SB-3 903.4 170710.096 558778.512 SB-4 895.5 170330.988 558759.472 SB-5 879.5 170102.807 558557.468 SB-6 896.5 169801.079 558426.041 DRAFTSubject to RevisionSandy Lean Clay, trace Roots, black, wet. (Topsoil) (SC-SM) Silty Clayey Sand, fine to coarse grained, trace Gravel, gray, waterbearing, very loose to loose. (Glacial Till) (CL) Sandy Lean Clay, trace Gravel, brown and gray, wet, medium to rather stiff. (Glacial Till) Bottom of borehole at 14.5 feet. AU 1 SS 2 SS 3 SS 4 SS 5 SS 6 SS 7 1-1-1 (2) 2-2-2 (4) 3-3-4 (7) 2-12-18 (30) 2-13-18 (31) 2-2-6 (8) NOTES GROUND ELEVATION 878.2 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING 3.30 ft / Elev 874.90 ft AT END OF DRILLING --- AFTER DRILLING --- HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-1 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 DRAFTSubject to RevisionSandy Lean Clay, trace Roots, dark brown, wet. (Topsoil) (CL) Sandy Lean Clay, trace Gravel, brown, wet, rather stiff. (Glacial Till) (SC) Clayey Sand, fine to medium grained, trace Gravel, brown, moist, medium dense. (Glacial Till) Bottom of borehole at 14.5 feet. AU 8 SS 9 SS 10 SS 11 SS 12 SS 13 SS 14 2-4-6 (10) 6-18-12 (30) 7-7-7 (14) 6-6-8 (14) 6-9-11 (20) 5-8-12 (20) NOTES GROUND ELEVATION 909.4 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING --- Not Encountered AT END OF DRILLING --- Not Encountered AFTER DRILLING --- Not Encountered HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-2 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 DRAFTSubject to RevisionSilty Clay, trace Roots, black, wet. (Topsoil) (CL) Lean Clay, brown, wet, stiff to very stiff. (Glacial Till) (ML) Silty Sand, brown, moist, medium dense. (Glacial Till) (CL-ML) Sily clay, brown, moist, very stiff. (Glacial Till) (SC) Clayey Sand, fine to medium grained, trace Gravel, brown, medium dense. (Glacial Till) Bottom of borehole at 21.0 feet. AU 15 SS 16 SS 17 SS 18 SS 19 SS 20 SS 21 SS 22 6-8-10 (18) 2-6-8 (14) 8-12-11 (23) 8-10-12 (22) 4-8-11 (19) 1-8-11 (19) 7-10-11 (21) NOTES GROUND ELEVATION 903.4 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING --- Not Encountered AT END OF DRILLING --- Not Encountered AFTER DRILLING --- Not Encountered HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 15 20 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-3 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 DRAFTSubject to RevisionSandy Lean Clay, trace Roots, black, wet. (Topsoil) (SC) Clayey Sand, fine to medium grained, trace Gravel, loose to medium dense. (Glacial Till) (CL) Sandy Lean Clay, trace Gravel, wet, stiff. (Glacial Till) Bottom of borehole at 14.5 feet. AU 23 SS 24 SS 25 SS 26 SS 27 SS 28 SS 29 3-3-5 (8) 2-8-8 (16) 6-7-9 (16) 4-5-8 (13) 4-7-8 (15) 6-6-8 (14) NOTES GROUND ELEVATION 895.5 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING --- Not Encountered AT END OF DRILLING --- Not Encountered AFTER DRILLING --- Not Encountered HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-4 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 DRAFTSubject to RevisionSilty Clay, black, wet. (Topsoil) (CL) Sandy Lean Clay, trace Gravel, brown and gray, wet, soft to medium. (Glacial Till) (SC) Clayey Sand, fine to medium grained, trace Gravel, Sand Seam at 10 feet, brown and gray, waterbearing, medium dense. (Glacial Till) (CL) Sandy Lean Clay, trace Gravel, gray, wet, rather stiff. (Glacial Till) Bottom of borehole at 14.5 feet. AU 30 SS 31 SS 32 SS 33 SS 34 SS 35 SS 36 1-1-1 (2) 1-3-3 (6) 3-5-6 (11) 3-5-7 (12) 3-5-7 (12) 3-5-6 (11) NOTES GROUND ELEVATION 879.5 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING 10.80 ft / Elev 868.70 ft AT END OF DRILLING --- AFTER DRILLING --- HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-5 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 DRAFTSubject to RevisionSandy Lean Clay, trace Roots, dark brown, wet. (Topsoil) (CL) Sandy Lean Clay, trace Gravel, brown, wet, rather soft to rather stiff. (Glacial Till) (SC) Clay Sand, fine to medium grained, trace gravel, brown, moist, loose. (Glacial Till) (CL-ML) Sandy Clay, black, wet, rather stiff. (Glacil Till) Bottom of borehole at 14.5 feet. AU 37 SS 38 SS 39 SS 40 SS 41 SS 42 SS 43 2-2-4 (6) 2-2-3 (5) 3-4-5 (9) 2-4-5 (9) 3-5-6 (11) 3-6-6 (12) NOTES GROUND ELEVATION 896.5 ft LOGGED BY DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 4/14/21 COMPLETED 4/14/21 AT TIME OF DRILLING --- Not Encountered AT END OF DRILLING --- Not Encountered AFTER DRILLING --- Not Encountered HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-6 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 5/12/21 14:52 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 August 2, 2021 HGTS Project Number: 21-0364 Mr. Dan Blake Black Cherry Development, LLC 14500 Martin Drive #3000 Eden Prairie, MN 55344 RE: Double Ring Infiltrometer Test Results, Erhart Property Residential Development, Chanhassen, Minnesota. Dear Mr. Blake: We have completed the double ring infiltrometer tests and soil borings for the proposed stormwater pond within the Erhart Property Residential Development in Chanhassen, Minnesota. This letter provides a summary of the soil and groundwater conditions encountered in the soil borings and provides soil infiltration rates for use in designing the proposed stormwater ponds. Our services were performed as requested and authorized by you and under the terms of our General Conditions. Project Description Haugo Geotechnical Services (HGTS) recently competed a geotechnical exploration for the project the results of which were presented in our report dated May 22, 2021. The report presented the results of 6 soil boring and provided recommendation foundation design and construction. The report also provided estimated soil infiltration rates for use in stormwater pond design. Since completion of the report, we understand that the City of Chanhassen and/or the watershed district required double ring infiltrometer teats and soil borings to further evaluate soil conditions within the stormwater ponds. Documents Provided To aid in our evaluation, we were provided with a plan sheet titled “Erhart Farm Infiltration Test” that was prepared by Alliant Engineering dated June 28, 2021. In general, the plan sheet showed a layout of the development and the proposed and existing topographic contours. The proposed soil boring locations and double ring infiltrometer test locations along with the required soil boring depths and double ring test elevations were also shown on the plan sheet. Locations and Elevations The soil boring and double ring test locations were selected and staked in the field by Alliant Engineering. Ground surface elevations at the boring locations and double ring infiltrometer test locations were also provided by Alliant Engineering. P a g e | 2 Procedures Soil Borings Two (2) standard penetration test (SPT) borings were advanced on July 21, 2021 by Haugo GeoTechnical Services (HGTS) with a rotary drilling rig, using continuous flight augers to advance the borehole. Representative samples were obtained from the boring, using the split-barrel sampling procedures in general accordance with ASTM Specification D-1586. In the split-barrel sampling procedure, a 2-inch O.D. split-barrel spoon is driven into the ground with a 140-pound hammer falling 30 inches. The number of blows required to drive the sampling spoon the last 12 inches of an 18-inch penetration is recorded as the standard penetration resistance value, or “N” value. The results of the standard penetration tests are indicated on the boring log. The soils encountered in the SPT boring were classified in general accordance with ASTM 2488, “Description and Identification of Soils (Visual/Manual Procedures)”. Samples were placed in clean glass sample jars and returned to the laboratory at HGTS for laboratory moisture content testing and percent passing the #200 sieve (P-200). A field log of the boring was prepared by the HGTS drill crew. The log contains visual classifications of the soil materials encountered during drilling, as well as the driller’s interpretation of the subsurface conditions between samples and water observation notes. The final boring log included with this report represents an interpretation of the field log and includes modifications based on visual/manual method observation of the samples. The soil boring log, general terminology for soil description and identification, and classification of soils for engineering purposes are also included in the appendix. The soil boring log identifies and describes the materials encountered, the relative density of consistency based on the Standard Penetration resistance (N-value, “blows per foot”) and groundwater observations. The strata changes were inferred from the changes in the samples and auger cuttings. The depths shown as changes between strata are only approximate. The changes are likely transitions, variations can occur beyond the location of the boring. Double Ring Infiltrometer Tests Two (2) double ring infiltration tests were performed on July 21, 2021 to measure in-situ soil permeability and were performed in general accordance with ASTM D3385-18, “Standard Test Method for Infiltration Rate of Soils in Field Using Double-Ring Infiltrometer”. Results of the double ring infiltrometer test are summarized in the Table 2 in the “Results” section below. A copy of the test results and a sketch showing the approximate test location is attached. Results - Soil Borings Soils The soil boring encountered about 1 foot of sandy lean clay topsoil that was dark brown in color and contained some roots. Below the topsoil, the soil borings encountered glacial till deposits composed of sandy lean clay and clayey sand that extended to the termination depth of the boring. Penetration resistance values (N-Values), shown as blows per foot (bpf) on the boring log, within the glacial till ranged from 10 to 19 bpf. These values indicate the glacial till had a rather stiff to very stiff consistency. P a g e | 3 Groundwater Groundwater was not encountered in the soil boring while drilling or after removing the augers from the boreholes. Groundwater appears to be below the depth explored by these borings. Water levels were measured on the dates as noted on the boring logs and the period of water level observations was relatively short. Given the cohesive nature of the soil encountered, it is possible that insufficient time was available for groundwater to seep into the borings and rise to its hydrostatic level. Groundwater monitoring wells or piezometers would be required to more accurately determine water levels. Seasonal and annual fluctuations in the groundwater levels should be expected. Laboratory Testing Laboratory moisture content and percent passing the number 200 sieve (P-200) content tests were performed on selected samples recovered from soil boring SB-8. Moisture contents ranged from about 16 to 19 percent. The P-200 content is a measure of the silt and clay sized particles (fines) in the soils which can affect soil infiltration rates. In general, the greater the P-200 content of a sample the less permeable the soils will be. Table 1 summarizes the results of the laboratory tests. Results of the moisture content tests and P-200 tests are also shown on the boring logs adjacent to the sample tested. Table 1. Summary of Laboratory Tests Boring Number Sample Number Depth (feet) Moisture Content (%) * P-200 Content (%) * SB-8 SS-54 5 16 53 SB-8 SS-55 7 ½ 17 52 SB-8 SS-57 12 ½ 19 54 ½ *Moisture content and P-200 values rounded to the nearest ½ percent. Results - Double Ring Infiltrometer Tests Double ring infiltrometer test results are summarized in Table 2. Columns 3 and 4 of the provide an average infiltration rate and a stabilized infiltration rate, respectively, for each test. The “average” infiltration rate represents the average infiltration rate across the entire duration of each test. The initial phase of the test generally measures the “saturation” of the subgrade soils which typically results in a higher indicated infiltration rate. For that reason, the stabilized infiltration rate, which is typically the last hour, approximately, of the tests is typically used for design purposes. Table 2. Summary of Double Ring Infiltrometer Results Test Location Approximate Test Elevation Average Infiltration Rate (inches/hour)* Stabilized Infiltration Rate (inches/hour)* INF 1 881.2 2.7 2.2 INF-2 882.0 0.2 0.1 * = Test results were rounded to the nearest 0.1 inch/hour General Haugo GeoTechnical Services has used the degree of skill and care ordinarily exercised under similar circumstance by members of the profession currently practicing in this locality. No warranty expressed or implied is made. Haugo GeoTechnical Services does not practice in the field of surveying therefore the locations and elevations referenced or described above should be considered approximate. P a g e | 4 The analyses presented in this report are based on data obtained from a limited number of tests. Variations can occur away from the test locations, the nature of which may not become apparent until additional exploration work is completed or construction is conducted. It should also be noted that soil infiltration rates can vary due to; soil moisture content, soil compaction, the placement or introduction of fine-grained soils, topsoil or biofiltration media and changes or variations in local groundwater levels. These variations may result in additional construction costs and it is suggested that a contingency be provided for this purpose. We made water level measurements in the soil borings at the times and under the conditions stated on the boring logs. The data was interpreted in the text of this report. The period of observation was relatively short and fluctuations in the groundwater level may occur due to rainfall, flooding, irrigation, spring thaw, drainage, and other seasonal and annual factors not evident at the time the observations were made. Design drawings and specifications and construction planning should recognize the possibility of fluctuations. Thank you for the opportunity to assist you on this project. If you have any questions or need additional information, please contact Lucas Mol or Paul Gionfriddo at 612-729-2959. Sincerely, HAUGO GEOTECHNICAL SERVICES Lucas Mol Project Manager I hereby certify that this plan, specification or report was prepared by me or under my direct supervision and that I am a duly licensed professional engineer under the laws of the State of Minnesota. Paul Gionfriddo, P.E. Senior Engineer License Number 23093 Attachments: Soil Boring & Double Ring Infiltrometer Location Sketch Soil Boring Logs, SB-7 & SB-8 Descriptive Terminology of Soil Characteristics Double Ring Infiltrometer Test Results, INF-1 & INF-2 Haugo GeoTechnical Services, LLC 2825 Cedar Avenue S. Minneapolis, MN 55407 Figure #: 1 Drawn By: NA Date: 7/28/2021 Scale: None Project #: 21-0364 Soil Boring and INF Location Sketch Erhart Property Chanhassen, Minnesota Legend Approximate Soil Boring and INF Location Disclaimer: Map and parcel data are believed to be accurate, but accuracy is not guaranteed. This is not a legal document and should not be substituted for a title search, appraisal, survey, or for zoning verification. SB-7 INF-2 INF-1 SB-8 Sandy Lean Clay, trace Roots, dark brown, moist. (Topsoil) (CL) Sandy Lean Clay, trace Gravel, brown, wet, rather stiff. (Glacial Till) (SC) Clayey Sand, fine to medium grained, trace Gravel, brown and gray, moist, medium dense. (Glacial Till) (CL) Sandy Lean Clay, trace Gravel, brown, wet, stiff. (Glacial Till) Bottom of borehole at 21.0 feet. AU 44 SS 45 SS 46 SS 47 SS 48 SS 49 SS 50 SS 51 4-5-5 (10) 4-6-7 (13) 3-5-7 (12) 3-6-9 (15) 4-6-9 (15) 6-6-8 (14) 6-9-10 (19) NOTES GROUND ELEVATION 905 ft LOGGED BY MS DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 7/21/21 COMPLETED 7/21/21 AT TIME OF DRILLING --- Not Encountered AT END OF DRILLING --- AFTER DRILLING --- Not Encountered HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 15 20 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-7 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 8/2/21 09:09 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 Sandy Lean Clay, trace Roots, dark brown, moist. (Topsoil) (CL) Sandy Lean Clay, trace Gravel, brown, wet, stiff. (Glacial Till) P-200=53% P-200=52% P-200=54.5 (CL) Sandy Lean Clay, trace Gravel, gray, wet, rather stiff. (Glacial Till) Bottom of borehole at 21.0 feet. AU 52 SS 53 SS 54 SS 55 SS 56 SS 57 SS 58 SS 59 5-6-9 (15) 5-7-8 (15) 5-7-8 (15) 5-7-9 (16) 3-6-10 (16) 3-6-10 (16) 3-5-7 (12) 16 17 19 NOTES GROUND ELEVATION 887.1 ft LOGGED BY MS DRILLING METHOD Hollow Stem Auger/Split Spoon DRILLING CONTRACTOR HGTS - 750 GROUND WATER LEVELS: CHECKED BY PG DATE STARTED 7/21/21 COMPLETED 7/21/21 AT TIME OF DRILLING --- Not Encountered AT END OF DRILLING --- AFTER DRILLING --- Not Encountered HOLE SIZE 3 1/4 inches FINES CONTENT (%) 20 40 60 80 20 40 60 80 PL LLMC DEPTH(ft)0 5 10 15 20 GRAPHICLOGMATERIAL DESCRIPTION SAMPLE TYPENUMBERRECOVERY %(RQD)BLOWCOUNTS(N VALUE) SPT N VALUE 20 40 60 80 MOISTURE CONT.(%)NOTESPAGE 1 OF 1 BORING NUMBER SB-8 CLIENT Black Cherry Development LLC PROJECT NUMBER 21-0364 PROJECT NAME Erhart Property PROJECT LOCATION Chanhassen, MN GEOTECH BH PLOTS - GINT STD US LAB.GDT - 8/2/21 09:09 - C:\USERS\HGTS 3\DROPBOX (HGTS)\HAUGO GEOTECHNICAL SERVICES\GINT PROJECT BACKUP\PROJECTS\21-0364 ERHART PROPERTY.GPJHaugo GeoTechnical Services 2825 Cedar Ave South Minneapolis, MN 55407 Telephone: 612-729-2959 Fax: 763-445-2238 Constants Area cm2 Depth of Liquid (cm) Liquid Container Number Inner Ring 729 11.0 1 Elevation:Annular Space 2189 11.0 2 Liquid: Remarks Inner Ring Reading cm Inner Maroitte Tube Flow (ml) Annular Space Reading cm Annular Space Marriotte Tube Flow (ml) Inner Infiltration Rate (Inch/h) Annular Infiltration Rate (Inch/h) Ground Temp Depth (cm) Temp at Depth (F) Weather conditions Etc... Hourly Inner Infiltration Rate (Inch/h) Start Test 7/21/2021 12:15 0:15 63.0 End Test 7/21/2021 12:30 0:15 n/a n/a Start Test 7/21/2021 12:30 0:15 63.0 End Test 7/21/2021 12:45 0:30 n/a n/a Start Test 7/21/2021 12:45 0:15 63.0 End Test 7/21/2021 13:00 0:45 n/a n/a Start Test 7/21/2021 13:00 0:15 63.0 End Test 7/21/2021 13:15 1:00 n/a n/a Start Test 7/21/2021 13:15 0:15 63.0 End Test 7/21/2021 13:30 1:15 n/a n/a Start Test 7/21/2021 13:30 0:15 63.0 End Test 7/21/2021 13:45 1:30 n/a n/a Start Test 7/21/2021 13:45 0:15 63.0 End Test 7/21/2021 14:00 1:45 n/a n/a Start Test 7/21/2021 14:00 0:15 63.0 End Test 7/21/2021 14:15 2:00 n/a n/a Start Test 7/21/2021 14:30 0:00 63.0 End Test 7/21/2021 14:30 2:00 n/a n/a Start Test 7/21/2021 14:30 0:15 63.0 End Test 7/21/2021 14:45 2:15 n/a n/a Start Test 7/21/2021 14:45 0:15 63.0 End Test 7/21/2021 15:00 2:30 n/a n/a Start Test 7/21/2021 15:00 0:15 63.0 End Test 7/21/2021 15:15 2:45 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 12:15 End Test 15:15 3:00 0.00 0.00 0.00 0.00 2.16 Total Infiltration in Inches (3 Hour Test)Final Results 21 24 23 18 0.00 20 0.00 2.16 0.00 2.16 2.16 2.16 2.16 2.16 2.16 2.16 22 0.00 0.00 19 0.00 0.00 0.00 0.00170.00 0.00 9 1000 3000 2.16 0.00 0.00 0.00 0.00 13 0.00 0.00 16 8 1000 3000 2.16 0.0015 11 1000 3000 10 1000 0.0014 2.16 3000 2.16 12 1000 3000 2.16 7 1000 3000 2.16 2.16 6 1000 3000 2.16 5 1000 3000 2.16 4 1000 3000 3 1000 6000 2.16 4.32 4.32 2.16 6000 4.32 1 3000 6000 6.48 2000 2.16 Infiltrometer Recording Chart Marriotte Tube Volume 3000 10000 Project Identification:21-0364 Soil Type: Test Location: Silty Sands 881.2INF 1 East Test Trial # Tested By: Penetration Depth of Outer Ring:Depth to water table:3 inches Start / End Date MM/DD/YY Time HR:MIN Elapsed Time Chg/(Total) Min Liquid level maintained using:( X ) Flow Valve ( ) Float Valve ( ) Mariotte Tubes Liquid Temp (F) Flow Readings Inner Infiltration Rate Ground Temperature M. Swanson Water 4.32 3.782 15000 45000 2.70 2.70 8.10 0.00 0.00 Constants Area cm2 Depth of Liquid (cm) Liquid Container Number Inner Ring 729 11.0 1 Elevation:Annular Space 2189 11.0 2 Liquid: Remarks Inner Ring Reading cm Inner Maroitte Tube Flow (ml) Annular Space Reading cm Annular Space Marriotte Tube Flow (ml) Inner Infiltration Rate (Inch/h) Annular Infiltration Rate (Inch/h) Ground Temp Depth (cm) Temp at Depth (F) Weather conditions Etc... Hourly Inner Infiltration Rate (Inch/h) Start Test 7/21/2021 12:15 0:15 63.0 End Test 7/21/2021 12:30 0:15 n/a n/a Start Test 7/21/2021 12:30 0:15 63.0 End Test 7/21/2021 12:45 0:30 n/a n/a Start Test 7/21/2021 12:45 0:15 63.0 End Test 7/21/2021 13:00 0:45 n/a n/a Start Test 7/21/2021 13:00 0:15 63.0 End Test 7/21/2021 13:15 1:00 n/a n/a Start Test 7/21/2021 13:15 0:15 63.0 End Test 7/21/2021 13:30 1:15 n/a n/a Start Test 7/21/2021 13:30 0:15 63.0 End Test 7/21/2021 13:45 1:30 n/a n/a Start Test 7/21/2021 13:45 0:15 63.0 End Test 7/21/2021 14:00 1:45 n/a n/a Start Test 7/21/2021 14:00 0:15 63.0 End Test 7/21/2021 14:15 2:00 n/a n/a Start Test 7/21/2021 14:30 0:00 63.0 End Test 7/21/2021 14:30 2:00 n/a n/a Start Test 7/21/2021 14:30 0:15 63.0 End Test 7/21/2021 14:45 2:15 n/a n/a Start Test 7/21/2021 14:45 0:15 63.0 End Test 7/21/2021 15:00 2:30 n/a n/a Start Test 7/21/2021 15:00 0:15 63.0 End Test 7/21/2021 15:15 2:45 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 12:15 End Test 15:15 3:00 0.00 0.00 0.00 0.00 0.11 Total Infiltration in Inches (3 Hour Test)Final Results 21 24 23 18 0.00 20 0.00 0.11 0.00 0.36 0.36 0.36 0.36 0.36 0.36 0.36 22 0.00 0.00 19 0.00 0.00 0.00 0.00170.00 0.00 9 50 500 0.11 0.00 0.00 0.00 0.00 13 0.00 0.00 16 8 50 500 0.11 0.0015 11 50 500 10 50 0.0014 0.11 500 0.11 12 50 500 0.11 7 50 500 0.11 0.36 6 50 500 0.11 5 50 500 0.11 4 50 500 3 50 1000 0.11 0.72 0.72 0.36 1000 0.54 1 250 1000 0.54 250 0.11 Infiltrometer Recording Chart Marriotte Tube Volume 3000 10000 Project Identification:21-0364 Soil Type: Test Location: Silty Sands 882.0INF 2 West Test Trial # Tested By: Penetration Depth of Outer Ring:Depth to water table:3 inches Start / End Date MM/DD/YY Time HR:MIN Elapsed Time Chg/(Total) Min Liquid level maintained using:( X ) Flow Valve ( ) Float Valve ( ) Mariotte Tubes Liquid Temp (F) Flow Readings Inner Infiltration Rate Ground Temperature J. Fitzpatrick Water 0.72 0.322 1000 7500 0.18 0.45 0.54 0.00 0.00 Haugo GeoTechnical Services, LLC 2825 Cedar Avenue S. Minneapolis, MN 55407 Figure #: 1 Drawn By: LM Date: 9/24/2021 Scale: None Project #: 21-0364 Soil Boring and INF Location Sketch Erhart Property – Additional Infiltration Tests Chanhassen, Minnesota Legend Approximate Infiltration Test Location Disclaimer: Map and parcel data are believed to be accurate, but accuracy is not guaranteed. This is not a legal document and should not be substituted for a title search, appraisal, survey, or for zoning verification. INF-3 INF-4 INF-2 INF-1 Constants Area cm2 Depth of Liquid (cm) Liquid Container Number Inner Ring 729 11.0 1 Elevation:Annular Space 2189 11.0 2 Liquid: Remarks Inner Ring Reading cm Inner Maroitte Tube Flow Annular Space Reading cm Annular Space Marriotte Tube Flow (ml) Inner Infiltration Rate (Inch/h) Annular Infiltration Rate (Inch/h) Ground Temp Depth (in) Temp at Depth (F) Weather conditions Etc... Hourly Inner Infiltration Rate (Inch/h) Start Test 9/27/2021 9:00 0:15 63.0 End Test 9/27/2021 9:15 0:15 n/a n/a Start Test 9/27/2021 9:15 0:15 63.0 End Test 9/27/2021 9:30 0:30 n/a n/a Start Test 9/27/2021 9:30 0:15 63.0 End Test 9/27/2021 9:45 0:45 n/a n/a Start Test 9/27/2021 9:45 0:15 63.0 End Test 9/27/2021 10:00 1:00 n/a n/a Start Test 9/27/2021 10:00 0:15 63.0 End Test 9/27/2021 10:15 1:15 n/a n/a Start Test 9/27/2021 10:15 0:15 63.0 End Test 9/27/2021 10:30 1:30 n/a n/a Start Test 9/27/2021 10:30 0:15 63.0 End Test 9/27/2021 10:45 1:45 n/a n/a Start Test 9/27/2021 10:45 0:15 63.0 End Test 9/27/2021 11:00 2:00 n/a n/a Start Test 9/27/2021 11:00 0:15 63.0 End Test 9/27/2021 11:15 2:15 n/a n/a Start Test 9/27/2021 11:15 0:15 63.0 End Test 9/27/2021 11:30 2:30 n/a n/a Start Test 9/27/2021 11:30 0:15 63.0 End Test 9/27/2021 11:45 2:45 n/a n/a Start Test 9/27/2021 11:45 0:15 63.0 End Test 9/27/2021 12:00 3:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 9:00 End Test 12:00 3:00 0.00 0.22 61, Sunny 2 800 0 0.14 0.00 0.43 0.00 0.00 Tested By: Penetration Depth of Outer Ring:Depth to water table:3 inches Start / End Date MM/DD/YY Time HR:MIN Elapsed Time Chg/(Total) Min Water at 8" below test grade, Liquid level maintained using:( X ) Flow Valve ( ) Float Valve ( ) Mariotte Tubes Liquid Temp (F) Flow Readings Inner Infiltration Rate Ground Temperature N. Curtis Water 0 0.00 1 200 0 0.43 0 0.43 Infiltrometer Recording Chart Marriotte Tube Volume 3000 10000 Project Identification:21-0364 Erhart Property, North Basin Soil Type: Test Location:877INF-1 Trial # 0.00 0.00 0.00 5 0 0 0.00 4 200 0 3 0 0 0.00 0.43 7 0 0 0.00 0.00 6 0 0 0.00 8 200 0 0.43 0.0015 11 0 0 10 0 0.0014 0.00 0 0.00 12 200 0 0.00 0.00 0.00 0.00 13 0.00 0.00 16 22 0.00 0.00 19 0.00 0.00 0.00 0.00170.00 0.00 9 0 0 0.00 0.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Final Results 21 24 23 18 0.00 20 0.00 0.00 0.00 0.00 0.00 0.11 Total Infiltration in Inches (3 Hour Test) Constants Area cm2 Depth of Liquid (cm) Liquid Container Number Inner Ring 729 11.0 1 Elevation:Annular Space 2189 11.0 2 Liquid: Remarks Inner Ring Reading cm Inner Maroitte Tube Flow Annular Space Reading cm Annular Space Marriotte Tube Flow (ml) Inner Infiltration Rate (Inch/h) Annular Infiltration Rate (Inch/h) Ground Temp Depth (in) Temp at Depth (F) Weather conditions Etc... Hourly Inner Infiltration Rate (Inch/h) Start Test 9/24/2021 14:15 0:15 63.0 End Test 9/24/2021 14:30 0:15 n/a n/a Start Test 9/24/2021 14:30 0:15 63.0 End Test 9/24/2021 14:45 0:30 n/a n/a Start Test 9/24/2021 14:45 0:15 63.0 End Test 9/24/2021 15:00 0:45 n/a n/a Start Test 9/24/2021 15:00 0:15 63.0 End Test 9/24/2021 15:15 1:00 n/a n/a Start Test 9/24/2021 15:15 0:15 63.0 End Test 9/24/2021 15:30 1:15 n/a n/a Start Test 9/24/2021 15:30 0:15 63.0 End Test 9/24/2021 15:45 1:30 n/a n/a Start Test 9/24/2021 15:45 0:15 63.0 End Test 9/24/2021 16:00 1:45 n/a n/a Start Test 9/24/2021 16:00 0:15 63.0 End Test 9/24/2021 16:15 2:00 n/a n/a Start Test 9/24/2021 16:15 0:15 63.0 End Test 9/24/2021 16:30 2:15 n/a n/a Start Test 9/24/2021 16:30 0:15 63.0 End Test 9/24/2021 16:45 2:30 n/a n/a Start Test 9/24/2021 16:45 0:15 63.0 End Test 9/24/2021 17:00 2:45 n/a n/a Start Test 9/24/2021 17:00 0:15 63.0 End Test 9/24/2021 17:15 3:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 14:15 End Test 17:15 3:00 3.60 4.32 54, Cloudy 54, Cloudy2 18600 39500 3.35 2.37 10.05 0.00 0.00 Tested By: Penetration Depth of Outer Ring:Depth to water table:3 inches Start / End Date MM/DD/YY Time HR:MIN Elapsed Time Chg/(Total) Min not encountered at 36" Liquid level maintained using:( X ) Flow Valve ( ) Float Valve ( ) Mariotte Tubes Liquid Temp (F) Flow Readings Inner Infiltration Rate Ground Temperature N. Curtis Water 4000 4.32 1 2500 5000 5.40 2000 3.24 Infiltrometer Recording Chart Marriotte Tube Volume 3000 10000 Project Identification:21-0364 Erhart Property, West Basin Soil Type: Test Location:904.3INF-2 Trial # 54, Cloudy 2.88 2.52 54, Cloudy2.16 5 1500 3000 3.24 4 1500 3000 3 2000 3500 4.32 2.81 7 1300 3000 2.81 2.16 6 1300 3000 2.81 8 1300 3000 2.81 0.0015 11 1300 3000 10 1300 0.0014 2.81 3000 2.81 12 1300 3000 0.00 0.00 0.00 0.00 13 0.00 0.00 16 22 0.00 0.00 19 0.00 0.00 0.00 0.00170.00 0.00 9 1300 3000 2.81 2.92 0.00 2.16 2.16 2.16 2.16 2.16 2.16 54, Cloudy 54, Cloudy2.16 54, Cloudy 54, Cloudy Final Results 21 24 54, Cloudy 54, Cloudy 54, Cloudy 23 18 0.00 20 0.00 0.00 0.00 0.00 0.00 2.81 Total Infiltration in Inches (3 Hour Test) 54, Cloudy Constants Area cm2 Depth of Liquid (cm) Liquid Container Number Inner Ring 729 11.0 1 Elevation:Annular Space 2189 11.0 2 Liquid: Remarks Inner Ring Reading cm Inner Maroitte Tube Flow Annular Space Reading cm Annular Space Marriotte Tube Flow (ml) Inner Infiltration Rate (Inch/h) Annular Infiltration Rate (Inch/h) Ground Temp Depth (in) Temp at Depth (F) Weather conditions Etc... Hourly Inner Infiltration Rate (Inch/h) Start Test 9/24/2021 10:45 0:15 63.0 End Test 9/24/2021 11:00 0:15 n/a n/a Start Test 9/24/2021 11:00 0:15 63.0 End Test 9/24/2021 11:15 0:30 n/a n/a Start Test 9/24/2021 11:15 0:15 63.0 End Test 9/24/2021 11:30 0:45 n/a n/a Start Test 9/24/2021 11:30 0:15 63.0 End Test 9/24/2021 11:45 1:00 n/a n/a Start Test 9/24/2021 11:45 0:15 63.0 End Test 9/24/2021 12:00 1:15 n/a n/a Start Test 9/24/2021 12:00 0:15 63.0 End Test 9/24/2021 12:15 1:30 n/a n/a Start Test 9/24/2021 12:15 0:15 63.0 End Test 9/24/2021 12:30 1:45 n/a n/a Start Test 9/24/2021 12:30 0:15 63.0 End Test 9/24/2021 12:45 2:00 n/a n/a Start Test 9/24/2021 12:45 0:15 63.0 End Test 9/24/2021 13:00 2:15 n/a n/a Start Test 9/24/2021 13:00 0:15 63.0 End Test 9/24/2021 13:15 2:30 n/a n/a Start Test 9/24/2021 13:15 0:15 63.0 End Test 9/24/2021 13:30 2:45 n/a n/a Start Test 9/24/2021 13:30 0:15 63.0 End Test 9/24/2021 13:45 3:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 10:45 End Test 13:45 3:00 4.32 4.05 59, Cloudy 59, Cloudy2 16000 32000 2.88 1.92 8.64 0.00 0.00 Tested By: Penetration Depth of Outer Ring:Depth to water table:3 inches Start / End Date MM/DD/YY Time HR:MIN Elapsed Time Chg/(Total) Min not encountered at 36" Liquid level maintained using:( X ) Flow Valve ( ) Float Valve ( ) Mariotte Tubes Liquid Temp (F) Flow Readings Inner Infiltration Rate Ground Temperature N. Curtis Water 5000 4.32 1 2500 6000 5.40 2000 3.24 Infiltrometer Recording Chart Marriotte Tube Volume 3000 10000 Project Identification:21-0364 Erhart Property, South Basin Soil Type: Test Location:880.4INF-3 West Side Trial # 59, Cloudy 3.60 3.24 59, Cloudy2.16 5 1500 2500 3.24 4 1500 3000 3 1500 4500 3.24 2.16 7 1000 1500 2.16 1.08 6 1000 2000 2.16 8 1000 1500 2.16 0.0015 11 1000 1500 10 1000 0.0014 2.16 1500 2.16 12 1000 1500 0.00 0.00 0.00 0.00 13 0.00 0.00 16 22 0.00 0.00 19 0.00 0.00 0.00 0.00170.00 0.00 9 1000 1500 2.16 2.43 0.00 1.08 1.08 1.08 1.08 1.44 1.80 54, Cloudy 54, Cloudy1.08 59, Cloudy 59, Cloudy Final Results 21 24 59, Cloudy 59, Cloudy 54, Cloudy 23 18 0.00 20 0.00 0.00 0.00 0.00 0.00 2.16 Total Infiltration in Inches (3 Hour Test) 54, Cloudy Constants Area cm2 Depth of Liquid (cm) Liquid Container Number Inner Ring 729 11.0 1 Elevation:Annular Space 2189 11.0 2 Liquid: Remarks Inner Ring Reading cm Inner Maroitte Tube Flow Annular Space Reading cm Annular Space Marriotte Tube Flow (ml) Inner Infiltration Rate (Inch/h) Annular Infiltration Rate (Inch/h) Ground Temp Depth (in) Temp at Depth (F) Weather conditions Etc... Hourly Inner Infiltration Rate (Inch/h) Start Test 9/24/2021 10:15 0:15 63.0 End Test 9/24/2021 10:30 0:15 n/a n/a Start Test 9/24/2021 10:30 0:15 63.0 End Test 9/24/2021 10:45 0:30 n/a n/a Start Test 9/24/2021 10:45 0:15 63.0 End Test 9/24/2021 11:00 0:45 n/a n/a Start Test 9/24/2021 11:00 0:15 63.0 End Test 9/24/2021 11:15 1:00 n/a n/a Start Test 9/24/2021 11:15 0:15 63.0 End Test 9/24/2021 11:30 1:15 n/a n/a Start Test 9/24/2021 11:30 0:15 63.0 End Test 9/24/2021 11:45 1:30 n/a n/a Start Test 9/24/2021 11:45 0:15 63.0 End Test 9/24/2021 12:00 1:45 n/a n/a Start Test 9/24/2021 12:00 0:15 63.0 End Test 9/24/2021 12:15 2:00 n/a n/a Start Test 9/24/2021 12:15 0:15 63.0 End Test 9/24/2021 12:30 2:15 n/a n/a Start Test 9/24/2021 12:30 0:15 63.0 End Test 9/24/2021 12:45 2:30 n/a n/a Start Test 9/24/2021 12:45 0:15 63.0 End Test 9/24/2021 13:00 2:45 n/a n/a Start Test 9/24/2021 13:00 0:15 63.0 End Test 9/24/2021 13:15 3:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 0:00 63.0 End Test 0:00 n/a n/a Start Test 10:15 End Test 13:15 3:00 0.00 0.00 0.00 0.00 3.24 Total Infiltration in Inches (3 Hour Test) 59, Cloudy 59, Cloudy 59, Cloudy Final Results 21 24 59, Cloudy 59, Cloudy 59, Cloudy 23 18 0.00 20 0.00 3.24 0.00 1.80 1.80 1.80 1.80 2.16 2.52 59, Cloudy 59, Cloudy1.80 22 0.00 0.00 19 0.00 0.00 0.00 0.00170.00 0.00 9 1500 2500 3.24 0.00 0.00 0.00 0.00 13 0.00 0.00 16 8 1500 2500 3.24 0.0015 11 1500 2500 10 1500 0.0014 3.24 2500 3.24 12 1500 2500 3.24 7 1500 3000 3.24 2.16 6 1500 3000 3.24 5 1500 3500 3.24 4 1500 3500 3 1500 3500 3.24 59, Cloudy 2.88 2.52 59, Cloudy2.52 4000 3.24 1 2000 7000 4.32 1500 3.24 Infiltrometer Recording Chart Marriotte Tube Volume 3000 10000 Project Identification:21-0364 Erhart Property, South Basin Soil Type: Test Location:880.6INF-4 East Trial # Tested By: Penetration Depth of Outer Ring:Depth to water table:3 inches Start / End Date MM/DD/YY Time HR:MIN Elapsed Time Chg/(Total) Min not encountered at 36" Liquid level maintained using:( X ) Flow Valve ( ) Float Valve ( ) Mariotte Tubes Liquid Temp (F) Flow Readings Inner Infiltration Rate Ground Temperature N. Curtis Water 5.04 3.51 59, Cloudy 59, Cloudy2 18500 40000 3.33 2.40 9.99 0.00 0.00